That Cabinet: 1. Approved the appropriation of the area of land referred to in this report and shown edged red on the plan at Appendix 2, for planning purposes to facilitate the redevelopment of land to extend the Civic Offices. 2. In respect of the area of land edged red on the plan at Appendix 2 to this report: ( i ) noted that it is necessary to use Section 203 of the Housing and Planning Act 2016 to facilitate the development and improvement of the land as part of the planning permission in order for any and all private rights and restrictions that affect the land to be overridden. (ii) Noted that no objections were received as a result of the public consultation exercise. (iii) Authorised officers to take such necessary administrative and accounting steps to give effect to the appropriation (including settling claims for compensation arising out of the extinguishment of any rights in the appropriated land pursuant to Section 203 of the Housing and Planning Act 2016). Reason for decision: as outlined in the report This decision is subject to call-in
Word for word from the decision Thurrock published for this meeting.Source: democracy.thurrock.gov.uk
The Grays South Regeneration area comprises a range of interventions that will support the economic and social vitality of Grays. In December 2018, Cabinet agreed proposals for an extension to Civic Offices providing space for Council functions as well as other ancillary and associated uses. This scheme forms the first phase of the Grays South Regeneration Area. In September 2019 planning permission was granted and the project has now moved into delivery.
The Council own all the land required for the scheme, however, the land known as Mulberry Square now needs to be appropriated to planning purposes from its existing use as informal open space to enable delivery to commence.
This report outlines the purpose of appropriation and describes the public consultation undertaken and the legal considerations that have been assessed in order to determine that the appropriation is proportionate and justified.
The report concludes that the process undertaken satisfactorily addresses these considerations and therefore seeks approval for the appropriation of the site to facilitate the redevelopment of the land and to address any residual rights over it.
1. Recommendation(s)
1.1That Cabinet resolves to:
a. approve the appropriation of the area of land referred to in this report and shown edged red on the plan at Appendix 2, for
planning purposes to facilitate the redevelopment of land to extend the Civic Offices.
b. in respect of the area of land shown edged red on the plan at Appendix 2 to this report:
(i) to note that it is necessary to use Section 203 of the Housing and Planning Act 2016 to facilitate the development and improvement of the land as part of the planning permission in order for any and all private rights and restrictions that affect the land to be overridden.
(ii) to note that no objections were received as a result of the public consultation exercise.
(iii) to authorise Officers to take such necessary administrative and accounting steps to give effect to the appropriation (including settling claims for compensation arising out of the extinguishment of any rights in the appropriated land pursuant to Section 203 of the Housing and Planning Act 2016).
2. Introduction and Background
2.1In December 2018, Cabinet approved a scheme for an extension of the Civic Offices in Grays and authorised Council officers to submit a planning application for the extension. In September 2019, the Council’s Planning Committee resolved to grant planning permission for the Civic Office scheme under the Council’s planning reference 19/00617/FUL.
2.2The Site of the scheme is shown on the plan at Appendix 1. The Council has acquired 1-3 New Road, 81 and 83 High Street to enable delivery of the scheme. Mulberry Square is held by the Council as informal open space and needs to be appropriated from its current use as informal open space to planning purposes to enable the delivery of the scheme (as shown on the plan at Appendix 2). The demolition of buildings immediately outside the area of Mulberry Square has already started and construction of the new extension is expected to be completed in Spring 2022.
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
Thurrock Transport Strategy Adoption2.1 Cabinet approved the Thurrock Transport Strategy given in Appendix 1 to be progressed to Full Council for adoptio...
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.