That Cabinet: 1. Endorsed the next steps in the programme for the project. 2. Delegated to the Corporate Director of Resources and Place Delivery, in consultation with the Portfolio Holder for Regeneration, Strategic Planning and External Relationships, the procurement for the next contract stages set out in the programme. Regular briefing notes on project progress would be provided to the relevant overview and scrutiny ... view the full minutes text for item 31.
Word for word from the decision Thurrock published for this meeting.Source: democracy.thurrock.gov.uk
Cabinet have agreed a scheme that will deliver an alternative to the level crossing in Grays High Street as a means of crossing the rail line.
The most recent Cabinet report supported a preferred design option but highlighted a potential budget issue and suggested that a further update would be presented after the next iteration of the cost plan. Design work has progressed and the next cost plan has been received. This report outlines the output of the cost plan and the next steps required to progress the project to delivery.
There are two reports relating to this project on the July Cabinet agenda. This report provides an update on project progress, sets out the project costs and budget and the next steps to design and construction. The following report seeks Cabinet approval to commence a Compulsory Purchase Order to ensure the required land can be acquired to enable scheme delivery. The second report relies on this report to confirm that there are no foreseen impediments to delivery so that when approving the use of Compulsory Purchase powers decision makers can be confident in the deliverability of the scheme.
1. Recommendation(s)
Cabinet are asked to;
a) Endorse the next steps in the programme for the project.
b) Delegate to the Corporate Director of Resources and Place Delivery, in consultation with the Portfolio Holder for Regeneration and External Affairs, the procurement for the next contract stages set out in the programme
c) Approve the latest iteration of the cost plan appended to this report, inc paragraphs 3.8 and 3.9 and note the efforts made to continue to drive cost efficiency.
2. Introduction and Background
2.1Members will be aware of the safety concerns related to the level crossing in Grays and of the way in which the gate closures create a barrier to movement between the town centre and the southern side of the level crossing towards the riverfront. In response to these issues, in July 2013 Cabinet agreed to work up a scheme to replace the level crossing with a high quality pedestrian underpass. Since then Cabinet has been kept informed of progress as below:
April 2017 – Agreement of a joint delivery approach with Network Rail, a funding strategy and a land assembly strategy. July 2020 – Approval in principle of the design output from the delivery agreement with Network Rail and selection of Option C – the Plaza as the preferred option.
2.2The most recent report highlighted that the forecast costs were significantly in excess of the approved budget. An approach to cost mitigation was set out and it was noted that the next iteration of the cost plan would be reported to Cabinet once available. The following sections of this report describe the further design work, the output of the latest cost plan and outline the next steps required to continue progressing the delivery of the project.
2.3NR have produced a revised cost plan which can be found at appendix 1. As the next stage of works is not yet in contract the breakdown remains commercially sensitive and is therefore exempt from publication. This cost plan is not a binding commitment but a foundation to move forward to the next project stage with NR, the GRIP (Governance for Railway Investment Projects process.
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
Thurrock Transport Strategy Adoption2.1 Cabinet approved the Thurrock Transport Strategy given in Appendix 1 to be progressed to Full Council for adoptio...
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.