Thurrock Council
General Services Committee, Monday 3 August 2020 at 6.00pm

Lower Thames Crossing Supplementary Consultation Response

Agreed Committee 3 papers

General Services Committee agreed this item on Monday 3 August 2020. Below is the council's own wording, with the papers it was decided on.

Item43

Resolved

Resolved That: 1. The Committee maintains its objection in principle to the Lower Thames Crossing in Thurrock. 2. The Committee agrees the consultation response set out in appendix A (Local Authority Response) for submission to Highways England by 12 August 2020. 3. The Committee agrees to delegate authority to the Chief Executive and Director of Place, in consultation with group leaders, Portfolio Holder for Regeneration and Chair of the LTC Task Force to make any final minor changes to the consultation response in Appendix A which may arise during the consideration of the consultation response by General Services Committee and the LTC Task Force. 4. The Committee agrees ... view the full minutes text for item 43.
Word for word from the decision Thurrock published for this meeting. Source: democracy.thurrock.gov.uk

Follow this further

Built from Thurrock's papers

What the report saysPro

Report to General Services Committee

Lower Thames Crossing Executive Summary - Review of Design Refinement Consultation

On behalf of Thurrock Council

Project Ref: 43879 | Rev: A | Date: July 2020

Registered Office: Buckingham Court Kingsmead Business Park, London Road, High Wycombe, Buckinghamshire, HP11 1JU Office Address: T: E: Executive Summary Introduction 1. Highways England is applying for a Development Consent Order (DCO) to construct and operate the Lower Thames Crossing (LTC) which is approximately 14.3 miles (23 km) of new road connecting the existing road network from the A2/M2, south-east of Gravesend, to the M25, to the north of North Ockendon. The scheme incorporates two 2.6 mile (4.3 km) tunnels under the River Thames and associated modifications to the M25, A2 and A13, and fee flowing charging systems.

2. The scheme is classified as a Nationally Significant Infrastructure Project (NSIP) therefore consent will be sought via a Development Consent Order (DCO) under the Planning Act 2008 (PA 2008) and the Planning Inspectorate (PINS) will consider the application on behalf of the Secretary of State for Transport. Highways England programme is to submit to the DCO application in Autumn 2020.

3. At the end of 2018, Highways England presented its ‘Statutory Consultation Scheme’ for the proposed LTC. A series of design changes was the subject of a Supplementary Consultation exercise which ended in April 2020 and now, a further round of design refinement is the subject of non-statutory consultation, being undertaken virtually, from 14 July to 12 August 2020.

4. This report has been prepared for Thurrock Council to provide a review of the material presented as part of the Design Refinement Consultation exercise. Its purpose is to identify areas of concern, potentially significant issues and identify areas of further work required to be carried out by Highways England in order to allow the scheme to be properly and proportionately assessed.

5. Overall, the Council has continued to actively engage with Highways England however, based upon the consultation material available, and as with the Supplementary Consultation (January 2020) material, the information presented by Highways England is deficient in the detail required for stakeholders, including the Council, to provide an informed response to the proposed design changes and the wider scheme. Moreover, progress on the environmental and health impact assessment work has been slow such that the Council is likely to be unable to engage meaningfully with Highways England on the potential effects of the scheme and the effectiveness of any mitigation proposals prior to the planned submission of the DCO application this Autumn.

Design Refinement Consultation Scheme 6. Highways England commenced its Design Refinement Consultation exercise on 14 July 2020, ending on 12 August 2020. Within Thurrock, the proposed design refinements are:

 Tilbury area - northern tunnel landscaping and maintenance road refinements. Realignment of two footpaths and an option for a shared path on Muckingford Road providing improved connectivity between Chadwell St Mary and East Tilbury. Water supply utility work to provide water to the construction sites and TBM and, other utility diversion works.

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
ITEM 5: Lower Thames Crossing Supplementary Response Appendix 1 Summary: 3 August 2020.docxSupplementary 182 KB DownloadRead as text
PDF
ITEM 5: Lower Thames Crossing Supplementary Response Appendix 1- 3 August 2020.docxSupplementary 1.1 MB Download
PDF
Lower Thames Crossing Supplementary Consultation ResponseSupplementary 297 KB Withheld: personal details

At this meeting

Whole meeting
40MinutesOn the agenda
43Lower Thames Crossing Supplementary Consultation ResponseThis decision
44Lower Thames Crossing Task ForceOn the agenda

Who was there

8 of 11 attended
RG
Councillor Rob GledhillChair, present
MC
Councillor Mark CoxshallCommittee Member, present
SH
Councillor Shane HebbCommittee Member, apologies, sent representative
FM
Councillor Fraser MasseyCommittee Member, present
BO
Councillor Bukky OkunadeCommittee Member, present
JH
Councillor James HaldenSubstitute, present as substitute
JK
Councillor John KentCommittee Member, present
GB
Councillor Gary ByrneCommittee Member, present
LC
Lyn CarpenterOfficer, in attendance
AE
Anna EastgateOfficer, in attendance
MB
Matthew BoulterSecretary, in attendance

On this subject at Thurrock

Search all
  1. Lower Thames Crossing Supplementary Consultation ResponseThis decision
  2. Lower Thames Crossing (LTC) Task Force ReportAgreed
  3. Lower Thames Crossing UpdateNoted
  4. Lower Thames Crossing Development Consent Order Update and Planning Performance Agreement (Decision: 110657)Approved
  5. Lower Thames Crossing Task Force Update Report (Decision: 110633)Noted
  6. Lower Thames Crossing - Delegation of Authority to Respond (Decision: 110622)Decided

More from Thurrock General Services Committee

All decisions
MeetingDecisionOutcome
29 Sep 2026 Appointment of Interim Executive Director of Landlord ServicesRESOLVED For the reasons set out in this report, the General Services Committee is recommended to: 2.1 Note the decis... Noted Open
29 Sep 2026 Constitutional Review: Financial Procedure RulesRESOLVED For the reasons set out in this report, the Committee is recommended to recommend the Financial Procedure Ru... Approved Open
24 Jun 2026 Recruitment of Chief Executive and Head of Paid ServiceRESOLVED The membership of the Members’ Appointment Panel (a sub committee of the committee) would be Councillors R B... Decided Open
25 Mar 2026 Appointment of a new Chief ExecutiveRESOLVED For the reasons set out in this report, the General Services Committee agreed the timetable for endorsement ... Agreed Open
3 Feb 2026 Constitution Review: Executive & CouncilRESOLVED 2.1 For the reasons set out in this report, the Committee is recommended to approve the amended rules in the... Approved Open

We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies