RESOLVED 1. That Cabinet noted the significant work undertaken by officers and consultants acting on behalf of the Council to present the Council’s position at the Lower Thames Crossing Development Control Order Examination between June and December 2023. 2. That Cabinet endorsed the Council’s continued position that the proposals submitted by National Highways do not meet their own objectives for the crossing and that they should be recommended for refusal, unless approval was conditional on a range of improvements and mitigation measures as set out by the Council in its submissions to the Examination.
Word for word from the decision Thurrock published for this meeting.Source: democracy.thurrock.gov.uk
The Council has consistently opposed National Highway’s current proposals for the crossing as they do not meet National Highways own objectives for the crossing and will create significant issues for Thurrock and Thurrock residents and businesses. We have fought hard for changes to the proposals or at the very least for improvements and mitigations that will help to address our concerns. National Highways have consistently failed to address these.
The Council’s Lower Thames Crossing team negotiated hard with National Highways last year, to secure an improved agreement with National Highway to ensure that most of the cost of our attending the Examination into the proposal, between June and December last year, would be met by National Highways and not by the Council or Council taxpayers.
The Council was as a result able to present our case in the strongest possible terms at the Examination, entering 31 submissions in response to the proposals. The Council’s response has been praised by the Thames Crossing Action Group in their latest newsletter where they acknowledged ‘What was clear to us, was what a great job the council's LTC team did.’
A decision is now in the hands of the Secretary of State, Michael Gove. It is the Council’s view that his Examiners should either recommend refusal of the proposals as they stand or at the very least, make approval conditional on a range of improvements and mitigation measures that we have put forward being delivered.
Commissioner Comment:
No comments
1. Recommendation(s)
Version Cabinet – Final version ready for Cabinet/Executive decision 1.1 That Cabinet notes the significant work undertaken by officers and consultants acting on behalf of the Council to present the Council’s position at the Lower Thames Crossing Development Control Order Examination between June and December 2023
1.2That Cabinet endorses the Council’s continued position that the proposals submitted by National Highways do not meet their own objectives for the crossing and that they should be recommended for refusal, unless approval is conditional on a range of improvements and mitigation measures as set out by the Council in its submissions to the Examination
2. Introduction and Background
2.1The Lower Thames Crossing is intended to create additional road capacity across the Thames and relieve pressure on the Dartford Crossing. The proposed route includes 14.3 miles of new road connecting the M2/A2, A13 and M25 and the longest road tunnel in the UK, stretching for 2.6 miles. The project also includes around 50 new bridges and viaducts. About 70% of the infrastructure will be in Thurrock.
2.2The Council has endeavoured to work with National Highways to influence and improve the scheme but remains opposed to the scheme in its current form due to the magnitude of unmitigated economic, environmental, and social impacts levied disproportionately on Thurrock and the Council’s concerns about the ability of the scheme to deliver its stated objectives.
2.3The Lower Thames Crossing Task Force has met regularly from September 2017 and has consistently sought to hold National Highways to account. Cabinet has received regular updates in accordance with agreed terms of reference.
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
Thurrock Transport Strategy Adoption2.1 Cabinet approved the Thurrock Transport Strategy given in Appendix 1 to be progressed to Full Council for adoptio...
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.