Resolved

1.1 Th a t C a bin e t no t e s t h e DCO pre-examination process and draft examination timetable and the ongoing role of the Lower Thames Crossing Task Force. 1.2 That Cabinet approves entering into a further Planning Performance Agreement with National Highways and delegates authority to the Director of Place to effect this decision. Reason for decision: as outlined in the report This decision is subject to call-in
Word for word from the decision Thurrock published for this meeting. Source: democracy.thurrock.gov.uk

Follow this further

Built from Thurrock's papers

What the report saysPro

Report to Cabinet

Executive summary

The National Highways (NH) submission of its Lower Thames Crossing (LTC) application for a Development Consent Order (DCO) was formally accepted by the Planning Inspectorate (PINS) in October 2022.

This report sets out the Council’s current understanding of the LTC DCO pre-examination work process and timescales of the LTC DCO Examination.

In May 2023 the Council attended the LTC DCO Programming Meeting to make representation and formally request a delay to the programme in consideration of the suspension of work necessary due to the Council’s financial situation and subsequent S114 notice. The Council requested the LTC DCO process was extended by 7 weeks.

Following a pause whilst the S.114 implications of proceeding with the Council’s objection were assessed the technical review team has been remobilised and is undertaking a review of the LTC DCO documents submitted as these are likely to be different to the information previously provided by National Highways (NH) prior to submission. This is complex work and requires substantial external resource and management.

Despite a strong case for an extension and support from other stakeholders the Examining Authority (ExA) confirmed in its Rule 8 letter, issued after the Preliminary Meeting (Part 1) which was held on 6 June, that the programme would be unchanged.

The Examination therefore commenced on 20th June and is scheduled to be completed by 20th December 2023. The ExA will then take 3 months to make its recommendation report to the Secretary of State for Transport. The ExA recommendation report is then sent confidentially to the Secretary of State for Transport to consider the recommendations.

A formal announcement on planning determination for this scheme might be expected from summer to late 2024, although this may be influenced by the dates of the General Election currently expected in May 2024.

Part of the cost of Thurrock Council’s engagement with the process to date is met by National Highways as set out in a Planning Performance Agreement (PPA) between the Council and National Highways. That PPA terminated when the DCO was accepted by PINS.

Officers have worked closely with National Highways to agree the terms of a new Agreement to take us through the Pre-Examination and Examination phase. Terms have now been agreed that will deliver a higher contribution from National Highways than the previous PPA (and greater than agreed with other affected authorities to reflect Thurrock’s current financial position). The agreed draft is attached as appendix 2.

The Department for Transport (DfT), the Department for Levelling Up, Housing & Communities (DLUHC) and more recently the ExA have made clear the importance of Thurrock Council being properly resourced to fully participate in the Examination process.

The ExA has asked for confirmation that the PPA will be approved and signed early in the Examination process.

Commissioner Commentary

The LTC has consequences for the ‘Place Leadership and Growth’ theme within the Improvement and Recovery Plan. Unless properly mitigated, the LTC presents a significant risk to Thurrock, in terms of economic, environmental, and social impacts.

1. Recommendation(s)

1.1That Cabinet notes the DCO pre-examination process and draft examination timetable and the ongoing role of the Lower Thames Crossing Task Force.

1.2That Cabinet approves entering into a further Planning Performance Agreement with National Highways and delegates authority to the Director of Place to effect this decision.

2. Introduction and Background

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
PPA Variation LetterAppendix 2 1.7 MB Download
PDF
Lower Thames Crossing Development Consent Order Update and Planning Performance Agreement (Decision: 110657)Decisions 130 KB DownloadRead as text

At this meeting

Whole meeting

Who was there

7 of 15 attended
AJ
Councillor Andrew JefferiesChair, present
DA
Councillor Deborah ArnoldDeputy Chair, present
AC
Councillor Adam CarterCommittee Member, present
BJ
Councillor Barry JohnsonCommittee Member, present
BM
Councillor Ben ManeyCommittee Member, present
GC
Councillor George CoxshallCommittee Member, present
GS
Councillor Graham SnellCommittee Member, present
JB
Jo BroadbentOfficer, expected
MB
Mark BradburyOfficer, expected
AH
Asmat HussainOfficer, expected
SM
Steven MairOfficer, expected
DS
Dr Dave SmithPublic, expected

All 15 on the meeting page

On this subject at Thurrock

Search all
  1. Lower Thames Crossing Development Consent Order Update and Planning Performance Agreement (Decision: 110657)This decision
  2. Lower Thames Crossing (LTC) Task Force ReportAgreed
  3. Lower Thames Crossing UpdateNoted
  4. Lower Thames Crossing Task Force Update Report (Decision: 110633)Noted
  5. Lower Thames Crossing - Delegation of Authority to Respond (Decision: 110622)Decided
  6. Lower Thames Crossing Task Force Update Report (Decision: 110566)Noted

More from Thurrock Cabinet

All decisions
MeetingDecisionOutcome
16 Sep 2026 Corporate and Improvement Plan - 2025/26 Quarter 4 and End of Year Performance Report and Annual Report3.1 Cabinet Noted the quarterly Corporate Performance Report at Appendix 1 and consider which performance issues Cabi... Noted Open
16 Sep 2026 Thurrock Transport Strategy Adoption2.1 Cabinet approved the Thurrock Transport Strategy given in Appendix 1 to be progressed to Full Council for adoptio... Approved Open
16 Sep 2026 Proposed Changes to the Essex Coast Recreational Disturbance Avoidance and Mitigation Strategy (RAMS) and Tariff2.1 Cabinet approved the £476 RAMS tariff, as set out in section 9.1 of the Cabinet report; 2.2 Cabinet agreed to wit... Approved Open
16 Sep 2026 High Priority Housing Policies - Housing Adaptations Policy2.1 Cabinet agreed the Council’s Housing Adaptations Policy in Appendix 1 to commence with effect from 1 October 2026... Agreed Open
16 Sep 2026 Matrix Agency Worker 1 year contract extension2.1 Cabinet agreed to utilise the one-year extension option contained within the current contract and extend the exis... Agreed Open