That Cabinet: 1. Authorised the Director Strategy, Engagement and Growth, after consultation with the Leader of the Council and the Portfolio Holder, to undertake all necessary work in connection with the Council’s response to the Lower Thames Crossing Development Consent Order (DCO) and for ensuring that the Council is properly represented at an Examination in Public, and for making decisions in the best interests of the Council during negotiations. This will involve Council responses to make representations following LTC DCO submission, prior to examination, and during examination. Responses will include, but are not limited to, Adequacy of Consultation Response, Statement of Common Ground (and its subsequent revisions), Local Impact reports, PINS written questions, and other relevant representations related to LTC. Reason for decision: as outlined in the report This decision is subject to call-in
Word for word from the decision Thurrock published for this meeting.Source: democracy.thurrock.gov.uk
To ensure that Thurrock Council is able to act in line with its statutory function throughout the Development Consent Order (DCO) process and to respond quickly to the Planning Inspectorate (PINS) up to and during the DCO examination, it is important that the delegated responsibilities are clearly articulated.
1. Recommendation(s):
1.1That Cabinet authorises the Director Strategy Engagement and Growth, after consultation with the Leader of the Council and the Portfolio Holder, to undertake all necessary work in connection with the Council`s response to the Lower Thames Crossing DCO and for ensuring that the Council is properly represented at any Examination in Public, and for making decisions in the best interests of the Council during negotiations. This will involve Council responses to make representation following LTC DCO submission, prior to examination, and during examination. Responses will include, but are not limited to, Adequacy of Consultation Response, Statement of Common Ground (and its subsequent revisions), Local Impact Reports, PINS written questions, and other relevant representations related to LTC.
2. Introduction and Background
2.1The Council remains opposed to key elements of the proposed road crossing of the Thames into Thurrock in the current alignment. The focus of ongoing work with National Highways (NH) is to collaborate to ensure that the LTC scheme presented by NH is workable, its impact minimised, and the benefits to residents and businesses in the Borough optimised through constructive opposition. The Council will also continue to hold National Highways to account to ensure that all statutory obligations are clearly met.
2.2NH has indicated that it intends to submit its DCO in November 2022 or by end March 2023 at the latest. Statutory consultation was undertaken in 2018 and the scheme has been amended through four subsequent rounds of non-statutory consultation since. NH submitted its DCO first in October 2020 which it subsequently withdrew following serious concerns expressed by the Planning Inspectorate about the adequacy of its consultation.
2.3A substantial workload of technical discussions, and analysis of data has been undertaken by a consistent team over recent years ensuring continuity of approach and resource efficiency.
2.4As the LTC DCO submission approaches there will be a significant increase in the number of responses that Thurrock Council will need to make as part of its statutory functions. A summary of these key DCO events is provided in the table below (based on a November 2022 DCO submission). There will not be sufficient time to take all papers for decision through committee, so it is important that delegated powers are agreed in advance.
Work Programme & DCO Timetable
Legend Urgent, but reasonable PINS or LTC timetable or lead-in Very urgent and short PINS timetable with limited lead-in
Key DCO Event What is Required Deadlines
Comments on DCOV1 Detailed technical input Done through many (Pre-DCOV2 Submission) depending on the topic Technical Document responses during 2021 and then CIC and LRC consultation responses Ongoing discussions on Review of DCOv1 + technical To match the next wave of Issues Logs/Themes and responses from LTC + Issues meetings up to hence the Statement of attendance at SoCG September/October 2022 Common Ground (SoCG) meetings DCO SUBMISSION N/A November 2022 QC Con Initial preparation of March 2022 and then Examination Strategy probably September)
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
Thurrock Transport Strategy Adoption2.1 Cabinet approved the Thurrock Transport Strategy given in Appendix 1 to be progressed to Full Council for adoptio...
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.