Resolved
That Cabinet: 1. Supported the approach to Housing Delivery as set out in the report. Reason for decision: as outlined in the report This decision is subject to call-in
Cabinet decided this item on Wednesday 7 July 2021. Below is the council's own wording, with the papers it was decided on.
Resolved
That Cabinet: 1. Supported the approach to Housing Delivery as set out in the report. Reason for decision: as outlined in the report This decision is subject to call-in
The emerging local plan identifies a need for around 32,000 new homes in Thurrock by 2038. The Council has previously agreed ambitious targets to contribute to this – to build 500 affordable HRA homes between 2019 and 2029 and 1,000 homes for sale and rent by 2023. 29 units were completed by 2020, a further 56 in early 2021 with an additional 35 units now on site completing later this year.
To date, the latest Government Housing Delivery Test for 2020 shows that housebuilding in Thurrock has only met 59% of the overall Government target for the area. 3,088 houses needed to be constructed between 2017 and 2020, but only 1,823 were actually built.
A report was presented to Cabinet on 9 December 2020, which explored various approaches to increase the Council’s capacity to deliver housing development schemes and to assist in the wider regeneration of the borough. Cabinet agreed to adopt a mixed approach to Housing Development Delivery that would ensure that more affordable homes would be built.
A further report on Assets Disposals was taken to Cabinet on 10 March 2021, where an Assets Disposals Policy was approved with a clear process identified to Reuse, Retain or Release an asset and a proposed approach to towards identifying the route for additional housing as set in Appendix 3 of that report. This report further explores the options for disposal when the assets would be suitable for housing and proposes a process to help determine delivery routes. The report also highlights the role that Thurrock Regeneration Ltd (TRL) can play in helping to increase good quality housing across the borough.
1. Recommendation(s)
1.1That Cabinet support the approach to Housing Delivery as set out in this report.
2. Introduction and Background
2.1The emerging Local Plan identifies a need for around 32,000 new homes in Thurrock by 2038.
2.2The Council has previously agreed its targets for housebuilding as a contribution to this, both through the Housing Revenue Account (HRA) and Thurrock Regeneration Limited (TRL). The previously agreed targets are to build:
500 affordable HRA homes to be built between 2019 and 2029 of which 85 units have been completed to date; and 1,000 homes for sale and rent by TRL by 2023. There have been no starts or completions by TRL since the introduction of this target in February 2018.
2.3To date, the latest Government Housing Delivery Test for 2020 shows that housebuilding in Thurrock has only met 59% of the overall Government target for the area. 3,088 houses were required between 2017 and 2020, but only 1,823 were actually built.
2.4Housing delivery is primarily through the private sector and developers have a range of reasons for not bringing forward developments – local land values often being one aspect, along with planning permissions and other factors.
2.5Delivery of new housing through the Council programme has been impacted on the need to limit and revise how resident engagement could take place during the Covid pandemic, but new ways of working have now been established. The operation of TRL has also been subject to pause and review and further reports on that operating model are being prepared.
2.6On 29 October 2019 and 15 January 2020 respectively, Housing Overview and Scrutiny and Cabinet established the process and criteria by which Council owned sites are to be identified as potential housing development sites.
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
PDF |
Housing Delivery Approach (Decision: 110571)Decisions | 188 KB | DownloadRead as text |
PDF |
Housing Delivery Approach: Appendix 1Appendix | 374 KB | Download |
Follow Cabinet at Thurrock and we tell you when its next papers are published, before the meeting rather than after it.
| Meeting | Decision | Outcome | |
|---|---|---|---|
| 16 Sep 2026 | Corporate and Improvement Plan - 2025/26 Quarter 4 and End of Year Performance Report and Annual Report3.1 Cabinet Noted the quarterly Corporate Performance Report at Appendix 1 and consider which performance issues Cabi... | Noted | Open |
| 16 Sep 2026 | Thurrock Transport Strategy Adoption2.1 Cabinet approved the Thurrock Transport Strategy given in Appendix 1 to be progressed to Full Council for adoptio... | Approved | Open |
| 16 Sep 2026 | Proposed Changes to the Essex Coast Recreational Disturbance Avoidance and Mitigation Strategy (RAMS) and Tariff2.1 Cabinet approved the £476 RAMS tariff, as set out in section 9.1 of the Cabinet report; 2.2 Cabinet agreed to wit... | Approved | Open |
| 16 Sep 2026 | High Priority Housing Policies - Housing Adaptations Policy2.1 Cabinet agreed the Council’s Housing Adaptations Policy in Appendix 1 to commence with effect from 1 October 2026... | Agreed | Open |
| 16 Sep 2026 | Matrix Agency Worker 1 year contract extension2.1 Cabinet agreed to utilise the one-year extension option contained within the current contract and extend the exis... | Agreed | Open |
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Keeps you signed in and runs your free-paper allowance. Always on.
Counts visits and which pages are used. First-party only, no advertising, never shared.