Thurrock Council
Cabinet, Wednesday 12 July 2023 at 7.00pm

A13 Dualling Final Outturn Report (Decision: 110664)

Noted Executive 2 papers

Cabinet noted this item on Wednesday 12 July 2023. Below is the council's own wording, with the papers it was decided on.

Item158

Resolved

Note the projected final outturn figure as set out in Table 1 of this report and approve the allocation of £ 49.637m to meet Thurrock Council’s commitment to scheme costs. 2. Delegate authority to the Director of Place, in conjunction with the Portfolio Holder for Regeneration, to conclude the Settlement Agreement and all outstanding compensation claims. 3. Note the lesson learnt recommendations and instruct that these are incorporated into Council’s Improvement & Recovery Plan. Reason for decision: as outlined in the report This decision is subject to call-in
Word for word from the decision Thurrock published for this meeting. Source: democracy.thurrock.gov.uk

Follow this further

Built from Thurrock's papers

What the report saysPro

Report to Cabinet

A13 Widening Programme Review & Lesson Learnt

Please change this to an image Kevin Munnelly suitable for your presentation Assistant Director Regeneration & Place Delivery

June 2023 A13 Widening – Project Overview • OBJECTIVES • Scope: The project will complete a Dual 3 x lane All Purpose (D3AP) standard carriageway along the A13 from junction 30 of the M25 to the A1014 junction. The A13 Widening project will tie in with the existing three lane section of the A13 to the west of the junction with the A128 (Orsett Cock). Alterations to the Orsett Cock interchange and two overbridges accommodate the widened A13. . • *Original Approved Construction Budget: £78,866,596 • *Initial Programme: Completed by February 2019 (* at time of tendering & detailed design – Aug 2016) Figure 5.1: Location of the • *£100,202,194 in 2023 prices Project A13 Widening – Project Overview • NEEDS – The A13 Widening project addresses the following TC business and Regeneration needs • Increase capacity along A13 • Previously operating above capacity at 77,000 vehicles per day. Widening provides a 50% capacity increase on the road. • Increase capacity at Orsett Roundabout. Forecast to be operating above capacity by opening year. • Support continued development at London Gateway Port • Will employ 12,000 when fully completed, 85% of employees live locally. • Forecast to handle 30% of the countries containerised trade. • No more than 3 berths are permitted without A13 Widening works completed. (Currently working on £350M 4th Berth) • Support continued development of other business around Thurrock; London Gateway Logistics Park, Thames Enterprise Park, London Distribution Park, Lakeside, Purfleet Centre, growth in Grays and Canvey Gateway Scale of the A13 Widening – Project

Stats at December 2020 (Below) Project Stats at March 2023 • 18,000m of drainage • 262 Steet Lighting Columns • 362 chambers • 197 traffic signs • 104,000m2 of new surfacing • 10,000m of fencing • 1,850m of Environmental Barrier • 4 x Bridges • 3,800m of Central reserve A13 Widening – : 2015 to 2017 Programme

Key Decision Points shown The Harbour Empowerment Order (HEO) • This act of Parliament gave powers to create the Thames Gateway Port. It placed obligations on the developer of the port to provide supporting infrastructure in order to allow the expansion of the ports capacity. Rail and Highway schemes were defined by the HEO that would improve and minimise the impact of the port on the local infrastructure. A13 Widening : 2018 - 2020 Construction COVID LOCKDOWN

Programme COVID LOCKDOWN 26/03 to 15/06 22/09 to 02/12 A13 Widening 2021 – 2023 Construction COVID LOCKDOWN 06/01 to 29/03 Programme Stages and Cumulative Expenditure Graph Feasibility Develo Prelim Business Kier Appoint : Jan 2015 p Design: Case: ed – July Contra Feb 2016 May 2016 – Mar June Kier Delivery 17 2015 ct June Thurroc Kie 2017 Thurrock 2016 r Council Award: k Thurro Council Jul Thurroc ck Detailed Design: Mott Atkins: Continued Detailed Design Atkins: 2015k Council MacDonal Aug 2017 – Feb 2019 Feasibilit Jan Council AECO d Atkins: Detailed £147.5m 2016 M: y Study Mott Prelim Design £ Forecast Spend Mac Donal Design Tenderin Concurre 143,018,624 g: nt Activity d Aug 2016 July 2017 Thurro ck Council £ £ Mott MacDonal 95,009,123 133,595,373 d £ AECOM 62,947,721 Support £ 29,945,773 £ 16,144,839 £ 2,736,551 £ 336,809 Cumulative Spend Above £ 308,676 £ £ 13,408,287 £ £ £ £ £ 9,423,250 Fin Year Spend 2,399,742 Fin Year Spend Fin Year Spend 13,800,934 Fin Year Spend 33,001,948 Fin Year Spend 32,061,401 Fin Year Spend 38,586,249 Fin Year Spend Fin Year Spend

Apr 15 - Mar 16 Apr 16 - Mar 17 Apr 17 - Mar 18 Apr 18 - Mar 19 Apr 19 - Mar 20 Apr 20 - Mar 21 Apr 21 - Mar 22 Apr 22 - Mar 23 Apr 23 - Mar 24 Cost Chart – Drivers of Change Risk and commercial certainty Millions

Cost related with DoV pond Cost related to construction Cost related to structures drainage design design Cost related to delay due to statutory Cumulative Value

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
A13 Dualling Final Outturn Report (Decision: 110664)Decisions 929 KB Download
PDF
A13 PowerpointReport 5.2 MB DownloadRead as text

At this meeting

Whole meeting

Who was there

7 of 15 attended
AJ
Councillor Andrew JefferiesChair, present
DA
Councillor Deborah ArnoldDeputy Chair, present
AC
Councillor Adam CarterCommittee Member, present
BJ
Councillor Barry JohnsonCommittee Member, present
BM
Councillor Ben ManeyCommittee Member, present
GC
Councillor George CoxshallCommittee Member, present
GS
Councillor Graham SnellCommittee Member, present
JB
Jo BroadbentOfficer, expected
MB
Mark BradburyOfficer, expected
AH
Asmat HussainOfficer, expected
SM
Steven MairOfficer, expected
DS
Dr Dave SmithPublic, expected

All 15 on the meeting page

More from Thurrock Cabinet

All decisions
MeetingDecisionOutcome
16 Sep 2026 Corporate and Improvement Plan - 2025/26 Quarter 4 and End of Year Performance Report and Annual Report3.1 Cabinet Noted the quarterly Corporate Performance Report at Appendix 1 and consider which performance issues Cabi... Noted Open
16 Sep 2026 Thurrock Transport Strategy Adoption2.1 Cabinet approved the Thurrock Transport Strategy given in Appendix 1 to be progressed to Full Council for adoptio... Approved Open
16 Sep 2026 Proposed Changes to the Essex Coast Recreational Disturbance Avoidance and Mitigation Strategy (RAMS) and Tariff2.1 Cabinet approved the £476 RAMS tariff, as set out in section 9.1 of the Cabinet report; 2.2 Cabinet agreed to wit... Approved Open
16 Sep 2026 High Priority Housing Policies - Housing Adaptations Policy2.1 Cabinet agreed the Council’s Housing Adaptations Policy in Appendix 1 to commence with effect from 1 October 2026... Agreed Open
16 Sep 2026 Matrix Agency Worker 1 year contract extension2.1 Cabinet agreed to utilise the one-year extension option contained within the current contract and extend the exis... Agreed Open

We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies