Note the projected final outturn figure as set out in Table 1 of this report and approve the allocation of £ 49.637m to meet Thurrock Council’s commitment to scheme costs. 2. Delegate authority to the Director of Place, in conjunction with the Portfolio Holder for Regeneration, to conclude the Settlement Agreement and all outstanding compensation claims. 3. Note the lesson learnt recommendations and instruct that these are incorporated into Council’s Improvement & Recovery Plan. Reason for decision: as outlined in the report This decision is subject to call-in
Word for word from the decision Thurrock published for this meeting.Source: democracy.thurrock.gov.uk
Please change this to an image Kevin Munnelly suitable for your presentation Assistant Director Regeneration & Place Delivery
June 2023 A13 Widening – Project Overview • OBJECTIVES • Scope: The project will complete a Dual 3 x lane All Purpose (D3AP) standard carriageway along the A13 from junction 30 of the M25 to the A1014 junction. The A13 Widening project will tie in with the existing three lane section of the A13 to the west of the junction with the A128 (Orsett Cock). Alterations to the Orsett Cock interchange and two overbridges accommodate the widened A13. . • *Original Approved Construction Budget: £78,866,596 • *Initial Programme: Completed by February 2019 (* at time of tendering & detailed design – Aug 2016) Figure 5.1: Location of the • *£100,202,194 in 2023 prices Project A13 Widening – Project Overview • NEEDS – The A13 Widening project addresses the following TC business and Regeneration needs • Increase capacity along A13 • Previously operating above capacity at 77,000 vehicles per day. Widening provides a 50% capacity increase on the road. • Increase capacity at Orsett Roundabout. Forecast to be operating above capacity by opening year. • Support continued development at London Gateway Port • Will employ 12,000 when fully completed, 85% of employees live locally. • Forecast to handle 30% of the countries containerised trade. • No more than 3 berths are permitted without A13 Widening works completed. (Currently working on £350M 4th Berth) • Support continued development of other business around Thurrock; London Gateway Logistics Park, Thames Enterprise Park, London Distribution Park, Lakeside, Purfleet Centre, growth in Grays and Canvey Gateway Scale of the A13 Widening – Project
Stats at December 2020 (Below) Project Stats at March 2023 • 18,000m of drainage • 262 Steet Lighting Columns • 362 chambers • 197 traffic signs • 104,000m2 of new surfacing • 10,000m of fencing • 1,850m of Environmental Barrier • 4 x Bridges • 3,800m of Central reserve A13 Widening – : 2015 to 2017 Programme
Key Decision Points shown The Harbour Empowerment Order (HEO) • This act of Parliament gave powers to create the Thames Gateway Port. It placed obligations on the developer of the port to provide supporting infrastructure in order to allow the expansion of the ports capacity. Rail and Highway schemes were defined by the HEO that would improve and minimise the impact of the port on the local infrastructure. A13 Widening : 2018 - 2020 Construction COVID LOCKDOWN
Programme COVID LOCKDOWN 26/03 to 15/06 22/09 to 02/12 A13 Widening 2021 – 2023 Construction COVID LOCKDOWN 06/01 to 29/03 Programme Stages and Cumulative Expenditure Graph Feasibility Develo Prelim Business Kier Appoint : Jan 2015 p Design: Case: ed – July Contra Feb 2016 May 2016 – Mar June Kier Delivery 17 2015 ct June Thurroc Kie 2017 Thurrock 2016 r Council Award: k Thurro Council Jul Thurroc ck Detailed Design: Mott Atkins: Continued Detailed Design Atkins: 2015k Council MacDonal Aug 2017 – Feb 2019 Feasibilit Jan Council AECO d Atkins: Detailed £147.5m 2016 M: y Study Mott Prelim Design £ Forecast Spend Mac Donal Design Tenderin Concurre 143,018,624 g: nt Activity d Aug 2016 July 2017 Thurro ck Council £ £ Mott MacDonal 95,009,123 133,595,373 d £ AECOM 62,947,721 Support £ 29,945,773 £ 16,144,839 £ 2,736,551 £ 336,809 Cumulative Spend Above £ 308,676 £ £ 13,408,287 £ £ £ £ £ 9,423,250 Fin Year Spend 2,399,742 Fin Year Spend Fin Year Spend 13,800,934 Fin Year Spend 33,001,948 Fin Year Spend 32,061,401 Fin Year Spend 38,586,249 Fin Year Spend Fin Year Spend
Apr 15 - Mar 16 Apr 16 - Mar 17 Apr 17 - Mar 18 Apr 18 - Mar 19 Apr 19 - Mar 20 Apr 20 - Mar 21 Apr 21 - Mar 22 Apr 22 - Mar 23 Apr 23 - Mar 24 Cost Chart – Drivers of Change Risk and commercial certainty Millions
Cost related with DoV pond Cost related to construction Cost related to structures drainage design design Cost related to delay due to statutory Cumulative Value
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
Thurrock Transport Strategy Adoption2.1 Cabinet approved the Thurrock Transport Strategy given in Appendix 1 to be progressed to Full Council for adoptio...
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.