PAS Update

Noted Executive 2 papers

AI summaryThurrock Cabinet noted continued progress on the Planning Service Transformation and Improvement Plan (PSTIP2), following a positive Planning Advisory Service peer review revisit in January 2025.

AI summaryIn plain English

Written from the decision and the officer reportPDF Pro
OutcomeNotedFollowing a positive PAS revisit in January 2025
MoneyNo new direct costsWork funded from existing Planning Services budgets
What happens nextContinue PSTIP2 work; six-monthly Cabinet updatesNext Developer Forum later in November 2025
Who it affectsAll wardsPlanning applicants, agents, developers, residents

What was decided

Cabinet noted the continued progress with the implementation of PSTIP2, following the PAS revisit in January 2025, as set out in the report presented to Cabinet on 07 May 2025. Report P13

Why

The PAS peer review group reassessed progress against 11 recommendations in January 2025 and reported positive findings to Cabinet in May 2025. Report 4.2, P14

A second iteration of the improvement programme (PSTIP2) was developed to focus on PAS priority activities and 2025/26 Service Plan delivery. Report 4.3, 4.4

What happens next

Continue work under PSTIP2 governance, with progress monitored every three weeks at the Planning Improvement Board and reported to the CEO and Cabinet. Report 4.4, 4.8, P26

Press ahead with the Regulation 19 Draft Local Plan Consultation, scheduled for Spring 2026, and further Developer Forum engagement. Report P37, P41

Undertake further post-restructure adjustments over the coming months and continue recruitment to remaining vacant roles. Report P23, 4.7

Options considered

  • Chosen: Deliver the 11 key PAS recommendations through a Planning Improvement Programme (agreed March 2024). Cabinet agreed this was the basis for restoring confidence in the Planning Service; no further options were evaluated. Report P45

Implications

  • Financial: No new direct financial implications; activity managed within existing Planning Services budgets, with graduate roles funded via the LGA Pathways to Planning scheme. Report P47, 4.7
  • Legal: No direct legal implications; any restructuring may have staffing implications and legal advice will be sought as required, with some changes potentially needing further governance including Constitution changes. Report P57
  • Risk: Programme risks are tracked and mitigated at the bi-weekly Planning Improvement Board and reported in monthly PSTIP highlight reports; recruitment risk rated AMBER after mitigations. Report P50, P51
  • Equalities: No direct Equality and Diversity implications; Community Equality Impact Assessments will be produced for relevant options as required. Report P60
  • Staffing: Restructure completed with new Head of Development Management appointed; full post-restructure review took place in September 2025 with further adjustments to follow. Report 4.7, P23

Who and where

  • All wards across the borough Report P7
  • Planning applicants and agents, including Accredited Planning Agents attending forum sessions Report 4.8
  • Developers (around 40 attended the 17 June 2025 Developer Forum) Report P39
  • Planning Committee members who received training in April and May 2025 Report 4.6
  • Newsletter recipients receiving regular planning updates Report 4.9

Timeline

  • April 2025: Greenbelt and Infrastructure training delivered to Planning Committee Report 4.6
  • 29 Apr 2025: PSTIP2 launched Report 4.5
  • 07 May 2025: PAS update and formal report presented to Cabinet Report 4.5, P13
  • 22 May 2025: Mandatory Planning Committee face-to-face training session held Report 4.6
  • 17 Jun 2025: Developer Forum hosted to share progress on the Local Plan Report P37
  • Sept 2025: Two Graduate Planning Assistants onboarded ahead of schedule Report 4.7
  • Sept 2025: Full post-restructure review of the Planning Service took place Report P23
  • Later in Nov 2025: Next Developer Forum meeting planned to update on Local Plan evidence base and draft policies Report P41
  • Spring 2026: Regulation 19 Draft Local Plan Consultation scheduled Report P37

Plain English for the jargon

  • PAS: Planning Advisory Service, the body that carried out the peer review of the Council's planning service.
  • PSTIP2: Planning Service Transformation and Improvement Programme part 2, the current iteration of the Council's planning improvement plan.
  • PIB: Planning Improvement Board, the governance group that oversees PSTIP2 and meets every three weeks.
  • NMA: Non-material amendment application, used to amend details or conditions of a previously approved application.
  • TPOCA: Application to work on a tree covered by a Tree Preservation Order in a conservation area.
What was decided, why, and what happens next

Pro reads every officer report for you and explains each decision in plain English: the money, the options, the risks, the timeline, each with the paragraph it came from.

Written by AI from the council's published papers. AI can get things wrong: the council's own wording below is the record.Report a problem
Item263

Resolved

2.1 Cabinet noted the continued progress with the implementation of the Planning Service Transformation and Improvement Plan (PSTIP2) following the very positive PAS revisit to Thurrock Council in January 2025, as outlined in the PAS review report presented to Cabinet on 07 May 2025.
Word for word from the decision Thurrock published for this meeting. Source: democracy.thurrock.gov.uk

Follow this further

Built from Thurrock's papers

What the report saysPro

Report to Cabinet

Report to Cabinet Report Title Planning Advice Service Update

Date of Meeting Wednesday, 19 November 2025

Report Author Ashley Baldwin, Chief Planning Officer

Corporate Director Claire Demmel, Executive Director Place

Lead Cabinet Member(s) Cabinet Member for Good Growth

Why is this a key 1. Expenditure over £500K NO decision? 2. Significant impact on 2 or more wards YES

Wards Affected (All Wards);

Identify exempt Choose an item. information and exemption category Public

Is report Urgent? No

Reasons for urgency N/A (only where applicable)

Appendices (if any) Appendix 1 – Progress Review Feedback_Final_February 2025

1. Executive Summary 1.1 Following the decision by Cabinet in May 2025 to review the Planning Improvement progress every 6 months, this report asks that Cabinet note the progress with the ongoing Planning Service improvements being rolled out under the governance of the Planning Improvement Board (PIB) as it oversees the Planning Service Transformation and Improvement Programme part 2 (PSTIP2).

2. Recommendations For the reasons set out in this report, the Cabinet is recommended to: 2.1 Note the continued progress with the implementation of the Planning Service Transformation and Improvement Plan (PSTIP2) following the very positive PAS revisit to Thurrock Council in January 2025, as outlined in the PAS review report presented to Cabinet on 07 May 2025.

3. Commissioner’s Comments 3.1 Commissioners note the improvements made to the Planning service and the continued focus on the development of the service as detailed in the PAS review.

4. The rationale and evidence for the recommendations 4.1 The PAS peer review group re-visited the Council on 29th and 30th January 2025 to assess the progress made with implementing the 11 recommendations for improvement that were outlined to the Council when they last visited at the end of 2023.

4.2The outcome of their visit was reported to Cabinet in May 2025 (See Appendix 1)

4.3Following their visit, a second iteration of the Planning Service Improvement and Transformation Programme (PSTIP2) was developed. This now focusses on the activities identified by PAS as a being priority plus the key activities required to deliver the 2025/26 Service Plans that may not already form part of the improvement programme.

4.4Whilst the PSTIP2 refocuses on the key priorities identified by PAS in January, many of which were already progressing towards completion, it will also continue to move forward with the existing activities. Such as: • Continued governance of the programme through the Planning Improvement Board (PIB) • Recruiting to the vacant roles – in particular, ensuring the Head of Service layer of the structure is fully resourced. • Continuous monitoring of progress and regular reporting to the Exec Director of Place, the CEO and Cabinet throughout the duration.

Notable work to date since May can be summarised as follows:

4.5Governance & Reporting: PSTIP2 was launched (29 Apr 2025); PAS update and formal report presented to Cabinet (May 2025) with positive commissioner feedback. The Corporate Risk Register was updated with all key planning risks.

4.6Planning Committee Training: We delivered Greenbelt and Infrastructure training in April 2025 in the form of both hybrid face to face and a virtual “Planning Knowledge Nugget”, and a Mandatory Planning Committee face to face session on 22 May 2025.

4.7Recruitment and staffing: Secured funding for an additional two Graduate Planning Assistants via the LGA’s Pathways to Planning scheme; recruitment process has been completed, offers accepted, onboarded ahead of schedule in Sept. Advertised and interviewed for remaining vacancies following the restructure, appointed new Head of Development Management.

A full post-restructure review took place in September 2025 and any further adjustments will be made over the coming months.

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
PAS Progress Review Feedback_Final_February 2025Appendix 1 330 KB Download
PDF
PAS UpdateReport 279 KB DownloadRead as text

At this meeting

Whole meeting

Who was there

9 of 18 attended
LW
Councillor Lynn WorrallChair, present
LW
Councillor Lee WatsonVice-Chair, present
VH
Councillor Vikki HartsteanCommittee Member, present
LH
Councillor Lynda HeathCommittee Member, present
VH
Councillor Victoria HollowayCommittee Member, present
MH
Councillor Mark HooperCommittee Member, present
MH
Councillor Mark HurrellCommittee Member, present
JK
Councillor John KentCommittee Member, present
VM
Councillor Valerie Morris-CookCommittee Member, present
AB
Ashley BaldwinOfficer, in attendance
DC
Dawn CalvertOfficer, in attendance
PC
Paul CrickOfficer, in attendance

All 18 on the meeting page

On this subject at Thurrock

Search all
  1. PAS UpdateThis decision
  2. PAS Review Update - Planning Service ImprovementsNoted
  3. PAS Review Update - Planning Service ImprovementsNoted
  4. Planning Advisory Service (PAS) Review actions (Decision: 110721)Noted
  5. Grays Underpass Update ReportDecided
  6. Grays South: Delivering the Pedestrian Underpass - Project Progress (Decision: 110577)Decided

More from Thurrock Cabinet

All decisions
MeetingDecisionOutcome
16 Sep 2026 Corporate and Improvement Plan - 2025/26 Quarter 4 and End of Year Performance Report and Annual Report3.1 Cabinet Noted the quarterly Corporate Performance Report at Appendix 1 and consider which performance issues Cabi... Noted Open
16 Sep 2026 Thurrock Transport Strategy Adoption2.1 Cabinet approved the Thurrock Transport Strategy given in Appendix 1 to be progressed to Full Council for adoptio... Approved Open
16 Sep 2026 Proposed Changes to the Essex Coast Recreational Disturbance Avoidance and Mitigation Strategy (RAMS) and Tariff2.1 Cabinet approved the £476 RAMS tariff, as set out in section 9.1 of the Cabinet report; 2.2 Cabinet agreed to wit... Approved Open
16 Sep 2026 High Priority Housing Policies - Housing Adaptations Policy2.1 Cabinet agreed the Council’s Housing Adaptations Policy in Appendix 1 to commence with effect from 1 October 2026... Agreed Open
16 Sep 2026 Matrix Agency Worker 1 year contract extension2.1 Cabinet agreed to utilise the one-year extension option contained within the current contract and extend the exis... Agreed Open