Grays Underpass Update Report

Decided Planning 1 paper

Planning, Transport, Regeneration Overview and Scrutiny Committee decided this item on Thursday 28 September 2023. Below is the council's own wording, with the papers it was decided on.

Item15

Resolved

That Planning, Transport and Regeneration Overview and Scrutiny Committee notes the action to cease further development work on the Underpass scheme and withdraw the planning application. That Planning, Transport and Regeneration Overview and Scrutiny Committee notes the delegation to the Director of Place, in consultation with the Portfolio Holder for Regeneration, Strategic Planning and External Relationships and Commissioners authority to implement the development strategy set out in Paragraphs 4.1- 4.3 and to negotiate the terms of a Memorandum of Understanding cover a potential Station Quarter development partnership with Network Rail and other strategic partners .
Word for word from the decision Thurrock published for this meeting. Source: democracy.thurrock.gov.uk

Follow this further

Built from Thurrock's papers

What the report saysPro

Report to Planning, Transport, Regeneration Overview and Scrutiny Committee

Executive summary

The forecasted project costs for the selected Underpass Design have increased significantly since the original budget of £27.4m was approved by Cabinet in 2017. Cabinet approved a further increase in the forecasted budget to £37.3m in 2021. The current budget forecast is £46m, based on the latest costings from Network Rail (GRIP 4) design. Forecasted cost estimates have consistently increased as the detailed design for the Underpass have been developed and greater certainty around the implementation impacts on the operational railway. This has resulted in a significantly longer build programme and more expensive technical solutions required to deal with utility diversions, track possessions and changes required for planning. The main increases on the 2021 forecast relate to a revised construction programme of works, changed construction methodology and works sequencing. Additional costs have been incurred in developing a revised rail access strategy, accommodating design changes proposed as part of the planning process and taking account of the inflationary impact of 15.4% due to revised pricing base dates.

The project review process has highlighted that in addition to the spiralling forecasted costs there have been significant issues with the management of the programme, with reference to design process management, planning and utility diversion planning. The findings of the review process are that the Underpass scheme in its current form is not in a technical state to move forward, and it does not continue to represent value for money. In addition, it is considered that the Council is holding too much of the financial risk on this project given current funding imbalance and benefits arising. The recommendation of the review process is that the Underpass design should not be pursued and that the current planning application for the Underpass be withdrawn.

However, the Review did acknowledge that the existing level crossing continues to represent a clear safety risk and whilst there have been no fatalities or serious injuries the number of ‘near misses’ has increased significantly. The review recommends that an alternative design and delivery approach is examined based on the development of the Station Quarter concept. This would seek to deliver the new pedestrian crossing over the railway, potentially as part of a new station and mixed- use residential development. It is proposed that Cabinet approve the adoption of this approach and instruct officers to examine the potential for the establishment of a strategic partnership with Network Rail and others, including the drafting of an initial Memorandum of Understanding (MOU) covering possible design options, partnership arrangements for delivery and roles and responsibilities. A further report on development options, including funding options will be brought back to Cabinet for consideration before the SELEP (Southeast Local Enterprise Partnership) Accountability Board meeting in February 2024.

Recommendations

1.1That Planning, Transport and Regeneration Overview and Scrutiny Committee notes the action to cease further development work on the Underpass scheme and withdraw the planning application.

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
Grays Underpass Update ReportReport 590 KB DownloadRead as text

At this meeting

Whole meeting

Who was there

6 of 9 attended
LS
Councillor Luke SpillmanChair, present
AA
Councillor Alex AndersonVice-Chair, present
VH
Councillor Vikki HartsteanCommittee Member, present
TK
Councillor Tom KellyCommittee Member, present
JM
Councillor Jacqui ManeyCommittee Member, present
LW
Councillor Lee WatsonCommittee Member, present
MK
Mat KielyOfficer, expected
KR
Keith RumseyOfficer, expected
NT
Navtej TungOfficer, expected

On this subject at Thurrock

Search all
  1. Grays Underpass Update ReportThis decision
  2. Grays South: Delivering the Pedestrian Underpass - Project Progress (Decision: 110577)Decided
  3. Grays South: Delivering the Pedestrian Underpass - Land Assembly (Decision: 110578)Noted
  4. Grays South Regeneration Area: Underpass and Public Realm Option SelectionApproved
  5. Grays South: Delivering the Pedestrian UnderpassDecided
  6. Grays South: Delivering the pedestrian underpassDecided

More from Thurrock Planning, Transport, Regeneration Overview and Scrutiny Committee

All decisions
MeetingDecisionOutcome
21 Feb 2024 ITB Capital Programme 2024/251.1 That the Committee provide comments on the 2024/25 Integrated Transport Block capital programme allocations and p... Agreed Open
21 Feb 2024 Tilbury and Grays Towns Fund Update - to follow1.1 That the Committee notes the proposed changes to the original programmes and the progress on delivering the Tilbu... Decided Open
21 Feb 2024 Regeneration Projects Update - to follow1.1 That the committee notes the proposed changes to the original programmes and the progress on delivering the Regen... Decided Open
17 Oct 2023 Thurrock Scheduled Ancient Monuments: Assessment of Settings - April 2023That the Planning, Transportation and Regeneration Overview and Scrutiny Committee note and provide comment on the Th... Decided Open
17 Oct 2023 East Tilbury (Bata Village) & Corringham Conservation Areas Character Appraisal and Management Plans - April 2023That the Planning, Transport and Regeneration Overview and Scrutiny Committee notes and comments on the East Tilbury ... Decided Open

We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies