Corporate and Improvement Plan - Q1 and Q2 Performance Report
AgreedExecutive2 papers
AI summaryThurrock Cabinet agrees Q1 and Q2 2025/26 performance milestones and metrics, noting 83% of milestones on track but pressures in EHCPs, homelessness, agency spend and smoking.
Written from the decision and the officer reportPDF Pro
OutcomeAgreedQ1 and Q2 2025/26 performance report noted
MoneyNo specific financial implicationsCosts built into service budgets
What happens nextQuarterly reporting continuesAreas of concern may go to scrutiny
Who it affectsCouncil services and residentsThree priority themes covered
What was decided
Cabinet agreed the Corporate and Improvement Plan milestones and metrics set out in the Corporate Performance Report at Appendix 1. Report 2.1
Cabinet noted the quarterly Corporate Performance Report and progress made up to the end of the second quarter of 2025/26. Report 2.2
Cabinet considered whether to recommend any areas of concern to the chairs of the relevant Overview and Scrutiny Committees. Report 2.3
Why
The Corporate and Improvement Plan 2025 to 2029 was adopted by Full Council on 22 October 2025, and the milestones and metrics were developed with services and Cabinet members to monitor delivery against its priorities. Report 1.1, 4.1
Commissioners welcomed the report's clear format and considered it shows growing maturity in corporate performance, with good progress on activity and maintained performance in key services, though demand-led areas such as EHCPs, homelessness, agency staff spend and smoking remain under pressure. Report 3.1, 1.3
What happens next
Milestones and metrics will be reported to the Senior Leadership Team, Corporate Overview and Scrutiny and Cabinet on a quarterly basis, and shared with chairs and vice-chairs of other scrutiny committees. Report 4.8
The set of milestones and metrics will be reviewed and updated for 2026/27 to ensure they remain relevant and stretching. Report 4.9
Red and Amber metrics with a worsening direction of travel are flagged as 'areas to watch' and will be continually monitored. Report 10.1
Options considered
Chosen: Agree the Corporate and Improvement Plan milestones and metrics as set out in Appendix 1. Required to monitor delivery of the Plan adopted by Full Council on 22 October 2025 Report 7.1, 2.1
Rejected: Not agree the milestones and metrics. Would not be in line with the Full Council decision to adopt the Corporate and Improvement Plan Report 7.1
Implications
Financial: The report carries no specific financial implications; costs are managed within service revenue budgets and monthly budget monitoring. Report 9.4
Risk: Red, Amber and Green ratings and direction of travel act as an indicator of risk to service delivery, with non-delivery of milestones rated Amber overall and mitigated through quarterly reporting. Report 10.1, 10.2, P53
Legal: The Council is required under updated Secretary of State Directions of July 2025 to develop and maintain a revised Corporate Plan; the report also supports compliance with the Best Value Duty, the Accounts and Audit Regulations 2015 and the CIPFA/Solace governance framework. Report 11.1, 11.3, 11.4
Equalities: Services must consider the impact of new ways of working through Community and Equality Impact Assessments, and milestones and metrics monitor progress on equality objectives. Report 12.1
Other: Good progress on activity with 83.3% of 72 milestones on track, but 29% of 36 metrics off target, with pressure in EHCPs, homelessness, agency staff spend and smoking. Report 1.3, 5.3, 5.6
Who and where
Residents in demand-led services such as Children's Services and homelessness support Report 1.3
Children and families needing Education, Health and Care Plans
Children Looked After needing placements within 20 miles of home
Council staff affected by agency spend pressures
Local residents in Chadwell St Mary and Tilbury under the localities transformation programme
Future residents of 48 new affordable council homes at Teviot Avenue
Timeline
22 October 2025: Full Council adopted the Corporate and Improvement Plan 2025 to 2029 Report 1.1, P67
24 October 2025: Risk implications verified by the Risk Manager Report P54
27 October 2025: Financial implications verified by the Assistant Director Financial Management and Procurement Report P50
30 October 2025: Legal and Governance implications verified Report P60
December 2025: Transformation Roadmap business cases considered at Cabinet
December 2025: Newly recruited educational psychologist due to start
4 December 2025: Report considered by Corporate Overview and Scrutiny Committee Report 8.2
Q1 2025/26 (April, May and June): First quarter reporting period Report 1.1
Q2 2025/26 (July, August and September): Second quarter reporting period covered Report 1.1
January 2026: Workshop planned with Health and Wellbeing Board; engagement on new People Strategy to commence
End of March 2026: Target date for delivery of milestones for 2025/26
March 2026: Draft Local Plan scheduled for consideration at Cabinet
March 2027: Extended deadline for the Grays Beach Park projects
Plain English for the jargon
EHCP: Education, Health and Care Plan, a formal plan for children and young people with special educational needs and disabilities.
PMAF: Performance Management and Assurance Framework, the council's agreed policy for setting and reporting on performance.
RAG: Red, Amber, Green rating used to indicate performance against targets.
SLT: Senior Leadership Team of the council.
Best Value Duty: Duty under the Local Government Act 1999 for councils to secure continuous improvement in how their functions are exercised.
EFS: Exceptional Financial Support, additional funding provided to councils facing severe financial pressure.
What was decided, why, and what happens next
Pro reads every officer report for you and explains each decision in plain English: the money, the options, the risks, the timeline, each with the paragraph it came from.
Written by AI from the council's published papers. AI can get things wrong: the council's own wording below is the record.Report a problem
Item280
Resolved
1.1 Cabinet agreed the Corporate and Improvement Plan milestones and metrics included in the Corporate Performance Report at Appendix 1. 1.2 Cabinet noted the quarterly Corporate Performance Report and progress made up to the end of the second quarter of 2025/26 in delivering the Corporate and Improvement Plan. 1.3 Cabinet considered recommending any areas of concern within the remits of the Overview and Scrutiny Committees to the chairs of those respective committees. Reason for the decision: as outlined in the report This decision is subject to call-in
Word for word from the decision Thurrock published for this meeting.Source: democracy.thurrock.gov.uk
1.1Following the adoption of the Corporate and Improvement Plan 2025-2029 by Full Council on 22 October 2025, Cabinet is presented with the corporate performance report for the first quarter (April, May and June) and the second quarter (July, August and September) for 2025/26. This report sets out the council’s progress towards delivering the Plan by monitoring performance against a set of associated milestones and metrics.
1.2The milestones and metrics have been developed with services and Cabinet members. They have been chosen because they best enable the council to assess its performance against the Plan’s priorities. Or in the case of underperformance, when and where additional action needs to be taken.
1.3The detailed Corporate Performance Report is presented at Appendix 1. In summary, this reporting period shows that good progress has been made in delivering activity (milestones) aligned to the corporate deliverables, as well as maintaining performance in the key services (metrics). However, challenges remain in many demand-led areas such as Education, Health and Care Plans (EHCPs) and homelessness, as well as other areas of pressure such as spend on agency staff and levels of smoking. Each of these is examined in this report and the detailed appendix. 1.4 We have incorporated feedback and lessons learnt from the 2024/25 reporting cycle. This report seeks to further embed the analysis of what the data is telling us (section 6 below) and to simplify its presentation to make it easier to engage with. In addition, the detailed report also highlights the successes of the reporting period, as well as ‘areas to watch’ which are metrics rated Red or Amber with a worsening direction of travel compared to the same period last year. These improvements will be continually monitored and built upon.
Recommendations
For the reasons set out in this report, the Cabinet is recommended to:
2.1Agree the Corporate and Improvement Plan milestones and metrics included in the Corporate Performance Report at Appendix 1.
2.2Note the quarterly Corporate Performance Report and progress made up to the end of the second quarter of 2025/26 in delivering the Corporate and Improvement Plan.
2.3Consider recommending any areas of concern within the remits of the Overview and Scrutiny Committees to the chairs of those respective committees.
3. Commissioner’s Comments
3.1This revised quarterly performance report provides a comprehensive picture of the Council’s performance to date and demonstrates the growing maturity of the organisation around its corporate performance. Commissioners welcome the clear format, recognising the organisation’s successes and outlining key areas for members to monitor closely. The narrative is helpful, outlining actions the Council is tacking to get performance on track and it is important that the organisation continues to track and monitor these actions between quarterly reports, linking back to internal audit and risk registers where appropriate, to ensure that the Council remains focused on achieving its stretching targets and ensuring an organisational-wide focus on continuous improvement.
4. Proposals – the rationale and evidence for the recommendations
The process for agreeing the right Milestones and Metrics
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
Thurrock Transport Strategy Adoption2.1 Cabinet approved the Thurrock Transport Strategy given in Appendix 1 to be progressed to Full Council for adoptio...
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.