AI summaryThurrock Cabinet approves refreshed Capital Programme 2026/27 to 2028/29 worth £167.532m, including £7.6M for Treetops free school expansion and £600k for Thameside Primary.
Written from the decision and the officer reportPDF Pro
OutcomeNotedIncludes new bids, project deletions, and education capital additions
Money£167.532m total programmePlus £7.6M Treetops and £600k Thameside from specific funds
What happens nextProcurement to beginFor designers, project teams, and principal contractors
Who it affectsThurrock Council and residentsEducation and wider infrastructure investment
What was decided
Cabinet approved the deletion of projects in Appendix B and freed up associated resources as part of the capital refresh.
Cabinet approved a £7.6M budget to expand Treetops free school, funded from the SEN Capital budget, and £600k to replace alternative provision at Thameside Primary, funded by a S106 grant.
Cabinet approved the start of procurement processes to appoint designers, project teams and principal contractors for the School Capital Programme, with delegation given to the Director of Children's Services.
Why
Capital funded proposals must be affordable within the Council's revenue budget, and the Council is required under the CIPFA Prudential Code to agree a capital strategy that is both prudent and sustainable. Report P1
The programme delivers investment in Thurrock through maintenance of existing infrastructure and necessary enhancements where they deliver cost avoidance benefits, as well as health and safety compliance. Report P3
No alternative viable options were considered because the Council is required by statute and the Prudential Code to agree a capital programme and associated capital strategy. Report 5.1
What happens next
The Director of Children's Services, in consultation with the relevant Portfolio Holder and the Chief Finance Officer, will enter into appropriate agreements following procurement awards.
Any future budget adjustments including year-end carry forwards will be reported to Cabinet as part of the Revenue and Capital out-turn reports. Report 7.2
The Capital Overview Board will continue monthly reviews and challenge of programme delivery to mitigate slippage and affordability risks. Report P14
The money
£167.532m Proposed total capital programme for 2026/27 to 2028/29 Report P9
£167.097m Net existing project expenditure rolling forward into the updated programme Report P9
£7.6M Budget for expansion of Treetops free school, funded from the SEN Capital budget
£600k Budget to replace alternative provision at Thameside Primary, funded by a S106 grant
Options considered
Chosen: Agree the refreshed Capital Programme and associated capital strategy as required by statute. The Council is required by statute and the CIPFA Prudential Code to agree a capital programme; no viable alternatives were considered. Report 5.1, 9.1
Rejected: Consider alternative approaches to the capital refresh. No alternative options were considered viable as the Council must comply with statutory and CIPFA requirements. Report 5.1
Implications
Financial: The capital programme must remain affordable within the Council's revenue budget and comply with the CIPFA Prudential Code for a prudent and sustainable capital strategy. Report P1, P15
Risk: Major risks include programme slippage, affordability under the improvement and recovery plan, health and safety, maintenance costs, cost of borrowing, and availability of funding, with most rated AMBER. Report P13, P14, P15, P16, P17, P18
Legal: Each scheme will be approved in accordance with the Council's constitution, Contract Procedure Rules and Financial Regulations, and funding conditions must be strictly complied with. Report 9.2, 9.3
Equalities: There are no direct diversity implications, but individual projects will be subject to Community and Equality Impact Assessments. Report 10.1, 10.2
Other: Procurement implications will be considered when approval is sought for particular schemes. Report P30
Who and where
Thurrock residents and service users benefiting from maintained and enhanced infrastructure Report P3
Pupils and families at Treetops free school, with expanded provision funded from the SEN Capital budget
Pupils and families at Thameside Primary, with replacement alternative provision funded by a S106 grant
Council commissioners overseeing the improvement and recovery plan constraints Report P15
Designers, project teams and principal contractors to be appointed through procurement
Timeline
2025-12-17: Cabinet decision taken on the Draft Capital Programme 2026/27 to 2028/29
2026/27 to 2028/29: Period covered by the proposed total capital programme of £167.532m Report P9
2025/26: Year to which the existing agreed capital budgets relate, based on the reported position as at quarter 2 Report 7.2
Plain English for the jargon
CIPFA Prudential Code: The Chartered Institute of Public Finance and Accountancy's code requiring local authorities to agree a capital strategy that is prudent and sustainable.
S106 grant: A financial contribution from a developer towards local infrastructure, agreed under Section 106 of the Town and Country Planning Act.
SEN Capital budget: Capital funding allocated for Special Educational Needs provision.
Virement: The transfer of budget between headings within the Council's approved budget.
Capital refresh: A review and update of the Council's capital programme, including new bids, deletions and revised timelines.
What was decided, why, and what happens next
Pro reads every officer report for you and explains each decision in plain English: the money, the options, the risks, the timeline, each with the paragraph it came from.
Written by AI from the council's published papers. AI can get things wrong: the council's own wording below is the record.Report a problem
Item284
Resolved
3.1 With regard to the refresh of the Capital Programme and for the reasons set out in this report a) Cabinet noted the proposed new capital projects as part of the capital refresh, set out in paragraph 4.2.1; b) Cabinet approved the deletion of the projects in Appendix B as part of the capital refresh and the freeing up of the associated resources; c) Cabinet noted the updated and refreshed Capital Programme summarised in Table 3 with full detail in Appendix E. d) With regard to the 2025/26 Capital Programme and for the reasons set out in this report, Cabinet approved in principle the proposed additions and virements to the Education Capital Programme as set out in para 4.4 (Appendix D); e) Cabinet approved a £7.6M budget for the expansion of Treetops free school to be funded from the SEN Capital budget; f) Cabinet approved a £600k budget, funded by a S106 grant, to replace the alternative provision at Thameside Primary; g) Cabinet approved the commencement of the procurement processes in accordance with Council & UK procurement law to appoint Designers and Project Teams, for the School Capital Programme and appoint the Principal Contractors to take forward construction of the proposed schemes, Treetops and Thameside Primary; h) Cabinet approved the delegation to be given to the Director of Children’s Services, in consultation with the relevant Portfolio Holder and the Chief Finance Officer, to enter into an appropriate form of agreement following the award of the agreements arising from recommendation (g) above in compliance with the Council’s procurement regulations; Councillor J Kent returned to the room at 20.06. Reason for the decision: as outlined in the report This decision is subject to call-in
Word for word from the decision Thurrock published for this meeting.Source: democracy.thurrock.gov.uk
Report to Cabinet Report Title Draft Capital Programme 2026/27 to 2028/29
Date of Meeting 17 December 2025
Report Author John Chance, Chief Accountant
Corporate Director Dawn Calvert, Chief Finance Officer (S151 Officer)
Lead Cabinet Member(s) Cllr Valerie Morris-Cook, Cabinet Member for Resources Why is this a key 1. Expenditure over £500K decision? 2. Significant impact on 2 or more wards
Wards Affected (All Wards);
Identify exempt Choose an item. information and exemption category N/A
Is report Urgent? No
Reasons for urgency (only where applicable)
Appendices (if any) Appendix A – Current Capital Programme and Funding Appendix B – Projects recommended for removal from the Capital Programme Appendix C – Capital Schemes requiring alternative funding from Capital Receipts 2025/26 Appendix D – Schools Capital Programme Virements Appendix E - Proposed 3-year programme and funding 2026/27 to 2028/29
1 1. Executive Summary
1.1This report sets out proposed changes to the Council’s Capital Programme. The Capital Programme is aligned to the medium-term financial plan, acknowledging that the last year, 2028/29, falls within the first year of the unitary arrangements under Local Government Reorganisation, if current timelines are adhered to.
1.2The report also covers additions to the Capital Programme and the funding sources associated with them and highlights a number of changes proposed as a result of the refresh exercise carried out, including financing alterations and project removals.
1.3The Capital Strategy will be included along with the Final Capital Programme to Cabinet on 18 February 2026. The strategy will set out the strategic framework underpinning capital expenditure and the associated financing of the Capital Programme.
1.4During the refresh process additions to the Capital Programme were limited to the following four categories:
• Health and Safety: to enhance safety standards or mitigate potential health and safety risks. • Return on investment proposals linked to MTFS savings. • Essential and non-avoidable maintenance and replacement of assets linked to cost avoidance. • Other additions that demonstrate benefits may be approved on a case- by-case basis.
1.5The following table highlights the changes from the current year, 2025/26, to the final year of the current programme 2028/29 and summarises the changes for the general fund, the details of which are covered within this report:
2 Table 1 Capital Programme with proposed changes 2025/26 - 2028/29 2025/26 2026/27 2027/28 2028/29 £m £m £m £m General Fund 101.401 30.239 10.448 8.395 Housing Revenue Account 60.968 59.663 44.548 14.129 Total 162.37 89.90 55.00 22.52
Proposed Adjustments to the Programme: New projects added 0.435 Removal - projects funded by capital receipts (0.124) (0.225) (0.050) (0.050) Removal - projects funded by external borrowing (0.286) Removal - projects funded by government grants (1.229) Sub-total (1.639) 0.210 (0.050) (0.050)
Revised Draft Capital Programme: General Fund 99.762 30.449 10.398 8.345 Housing Revenue Account 60.968 59.663 44.548 14.129 Total 160.730 90.112 54.946 22.474
2. Background 2.1 The Council is required by statute and as set out in the Prudential Code for Capital Finance in Local Authorities, 2021 Edition, to agree the Capital Programme and the associated Capital Strategy. Local authorities are required to have regard to the current editions of this code by regulations 2 and 24 of the Local Authorities (Capital Finance and Accounting) Regulations.
2.2The Capital Programme has undergone a thorough refresh in recent months in efforts to rationalise the programme. To this end a Capital Overview Board was mobilised in October 2025 to oversee the changes and introduce a further level of governance into the financial stewardship of the Capital Programme. The refresh achieved the following objectives:
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
Thurrock Transport Strategy Adoption2.1 Cabinet approved the Thurrock Transport Strategy given in Appendix 1 to be progressed to Full Council for adoptio...
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.