Draft Revenue Budget 2026/27 and Draft Medium Term Financial Strategy 2026/27 to 2028/29
ApprovedExecutive6 papers
AI summaryThurrock Cabinet approved the draft 2026/27 revenue budget and Medium Term Financial Strategy to 2028/29, with £13.9m of savings identified against a £13.65m target, subject to consultation before final approval by Full Council in February 2026.
Written from the decision and the officer reportPDF Pro
OutcomeApprovedSubject to final Cabinet and Council decision in February 2026
Money£13.9m savings vs £13.65m targetPlus planned 2.99% core and 2% ASC precept rises
What happens nextScrutiny on 20 January 2026Final Cabinet and Council approval in February 2026
Who it affectsCouncil tax payers and schoolsThurrock residents, schools, and service users
What was decided
Cabinet approved the draft 2026/27 budget and MTFS 2026/27 to 2028/29 as a starting point, noting that the budget will be updated after the Indicative Local Government Finance Settlement and reconsidered with consultation responses and the equality impact assessment before referral to Council in February. Report 2.1
Cabinet noted the planning assumption to increase core Council Tax by 2.99% and the Adult Social Care Precept by 2% in 2026/27, and agreed to continue mirroring the national schools funding formula as decided since 2020/21. Report 2.1, 8.6
Cabinet noted that draft savings proposals of £13.9m have been identified against a target of £13.65m, with one-off implementation costs of £897k to be funded from the Council Transformation Infrastructure Funding Reserve. Report 2.1, 6.2
Why
The Council requires Exceptional Financial Support through a Capitalisation Direction to set a balanced budget, with total EFS estimated at £691m for 2022/23 to 2028/29, and ongoing financial uncertainty linked to the unconfirmed local impact of the new fair funding formula and multi-year settlement. Report 3.1, 4.1, 4.3
The draft budget responds to the Autumn Budget 2025 announced on 26 November 2025, which confirmed the Fair Funding Review 2.0 will be implemented from 2026/27, with detailed funding impact to follow the Indicative Finance Settlement in mid-December 2025. Report 5.1, 5.2, 5.5, 5.7
What happens next
The report is referred to the Corporate Overview and Scrutiny Committee on 20 January 2026 for further consideration, with public consultation on the draft budget to follow. Report 2.1, 10.1
The final budget and MTFS will be updated in February 2026 to reflect council tax, business rates, the local government financial settlement, and updated treasury costs, with the five financial strategies and overarching Capitalisation Directive Model finalised at that point. Report 4.4, 7.5
Full Council will be asked to set the budget before 11 March 2026 under section 30(6) of the Local Government Finance Act 1992, with the Chief Finance Officer required to report on the robustness of estimates and adequacy of reserves.
£72.1m EFS through Capitalisation Direction for 2025/26, 30% of net revenue budget Report 4.1, 7.1
£691m Total estimated EFS for 2022/23 to 2028/29 (£57m operating, £634m treasury) Report 4.1
£280m Capitalisation Direction requirement for 2026/27 to 2028/29 Report 7.2
73.491 Estimated Capitalisation Requirement for 2026/27 (£m) Report P29, 7.1
73.310 Exceptional Financial Support 2026/27 in current MTFS (£m) Report 7.1
£57.137m National Non-Domestic Rates assumed across the MTFS period Report P26, P29
Options considered
Chosen: Approve draft 2026/27 budget and MTFS for consultation. Sets out the Council's financial position and savings proposals pending final settlement details, while allowing further scrutiny and consultation. Report 2.1, 3.4
Implications
Financial: The Council continues to rely on Exceptional Financial Support through a Capitalisation Direction, with any net gain from Fair Funding Review 2.0 to be applied as a direct reduction in EFS rather than funding new expenditure. Report 5.7
Risk: Risks identified include: dependence on the Indicative Finance Settlement, uncertainty over Devolution and Local Government Reform (£2m contingency earmarked), external inflationary volatility (£1.75m contingency), delays to existing 2025/26 savings, and inability to deliver the approved MTFS. Report 12.2, P55, P56, P57
Legal: Setting the budget is reserved to Full Council and must happen before 11 March each year under section 30(6) of the Local Government Finance Act 1992; the Chief Finance Officer must report on robustness of estimates and adequacy of reserves under section 25 of the Local Government Act 2003.
Equalities: No direct diversity implications arise from the report; Community and Equality Impact Assessments (CEIAs) have been undertaken for specific savings proposals.
Staffing: A pay award of 3.2% is budgeted for across the plan, revised from 2.5% in the previous MTFS, reflecting the local government pay settlement for 2025/26 and subject to revision pending the final 2026/27 pay agreement. Report P29, 7.12
Other: The schools funding formula for 2026/27 will continue to mirror the National Funding Formula including Area Cost Adjustment, with Basic Entitlement reduced where needed to stay within available funding, consistent with Cabinet decisions since 2020/21. Report 8.6, 8.7
Who and where
Thurrock Council tax payers, facing a planning assumption of a 2.99% core Council Tax increase and 2% Adult Social Care Precept increase in 2026/27 Report 2.1, P29
Mainstream schools (maintained and academies) in Thurrock, whose 2026/27 funding will be determined by the local formula mirroring the NFF Report 8.6
Service users across adult social care, children's services, homelessness and SEND, where national funding pressures remain largely unaddressed by the Fair Funding Review Report 5.4
The Council workforce, with a 3.2% pay award assumption built into the MTFS Report P29, 7.12
Timeline
13 November 2025: Draft saving proposals presented to the Corporate Overview and Scrutiny Committee Report 6.3
26 November 2025: Autumn Budget 2025 announced, confirming Fair Funding Review 2.0 implementation from 2026/27 Report 5.1, 5.5
4 August: Department for Education released summary policy document on schools NFF structure for 2026/27
27 November 2025: Schools Forum discussed the funding formula principles Report 8.6
Week commencing 15 December 2025: Indicative Local Government Finance Settlement expected, providing clarity on funding impact for Thurrock Report 5.7
17 December 2025: Cabinet considered and approved the draft 2026/27 budget and MTFS Report 2.1
20 January 2026: Report to be considered by the Corporate Overview and Scrutiny Committee Report 2.1, 10.1
February 2026: Final budget and MTFS to be presented to Cabinet and then Council for approval, incorporating updated settlement, council tax, business rates, and treasury costs Report 4.4, 7.5
Before 11 March 2026: Statutory deadline for Full Council to set the budget under section 30(6) LGFA 1992
1 April 2026: Start of the 2026/27 financial year, including full reset of the Business Rates Retention System Report 7.11
Plain English for the jargon
MTFS: Medium Term Financial Strategy, the Council's multi-year financial planning document covering 2026/27 to 2028/29 in this report.
EFS: Exceptional Financial Support, central government funding provided through a Capitalisation Direction that allows the Council to borrow from the Public Works Loans Board to support revenue expenditure.
Capitalisation Direction: Approval permitting the Council to treat certain revenue costs as capital, enabling borrowing to fund them; Thurrock's estimated total is £691m for 2022/23 to 2028/29.
NFF: National Funding Formula, the Department for Education's formula for distributing school funding; Thurrock's local formula mirrors it.
CEIA: Community and Equality Impact Assessment, undertaken for specific savings proposals to ensure fair and proportionate delivery.
NNDR: National Non-Domestic Rates, the business rates retained locally; assumed at £57.137m across the MTFS period.
What was decided, why, and what happens next
Pro reads every officer report for you and explains each decision in plain English: the money, the options, the risks, the timeline, each with the paragraph it came from.
Written by AI from the council's published papers. AI can get things wrong: the council's own wording below is the record.Report a problem
Item283
Resolved
1.1. a. Cabinet approved the draft budget for 2026/27 and the draft Medium Term Financial Strategy (MTFS) 2026/27 to 2028/29, noting this is subject to further consultation, so that Cabinet may later consider the budget considering the consultation responses and the equality impact assessment before it is referred to Council in February. b. Cabinet noted that the Autumn Budget 2025 confirmed broad plans which will impact on local government for 2026/27 onwards, but that the draft budget will be updated when the detail is announced in the Indicative Financial Settlement which has been received on the 17 December 2025. c. Cabinet noted that, at draft stage, savings proposals totalling £13.9m are identified against a target of £13.65m. d. Cabinet noted the planning assumption to increase core Council Tax by 2.99% and to increase Adult Social Care Precept Council Tax by 2% in 2026/27; and e. Cabinet agreed that the councils 2026/27 schools funding formula be implemented as stated in paragraphs XX. This being consistent with previous cabinet decisions made since 2020/21. f. Cabinet referred this report to the Corporate Overview and Scrutiny Committee on 20 January 2025 for consideration. Reason for the decision: as outlined in the report This decision is subject to call-in
Word for word from the decision Thurrock published for this meeting.Source: democracy.thurrock.gov.uk
Report to Cabinet Report Title Draft Revenue Budget 2026/27 and Draft Medium Term Financial Strategy 2026/27 to 2028/29 Date of Meeting Wednesday, 17 December 2025
Report Author Dawn Calvert, Chief Financial Officer S151
Corporate Director Dawn Calvert, Chief Financial Officer S151
Lead Cabinet Member(s) Councillor Valerie Morris-Cook, Cabinet Member for Resources Why is this a key 1. Expenditure over £500K Yes decision? 2. Significant impact on 2 or more wards Yes
Wards Affected All
Identify exempt N/A information and exemption category
Is report Urgent? No
Reasons for urgency N/A (only where applicable)
Appendices (if any) Appendix 1 - Saving Proposals Appendix 2 - Medium Term Financial Strategy 2024/25 to 2028/29 Appendix 3 - Medium Term Financial Strategy 2025/26 to 2028/29 Appendix 4 – Directorate Growth 2026/27 to 2028/29 Appendix 5 – Operational Cost Pressures 1. Executive Summary
1.1This report sets out the draft revenue budget for 2026/27 and draft Medium-Term Financial Strategy (MTFS) for 2026/27 to 2028/29. It reflects the latest financial factors and incorporates any known changes to assumptions and forecasts since that date. The budget and MTFS will be brought back to Cabinet in February 2026 for final approval and recommendation to Council. 1.2. The Council’s overall financial position remains challenging, as it continues to rely on Exceptional Financial Support (EFS) through Capitalisation Directive (CD) to achieve its legal requirement to set a balanced budget for the forthcoming year. The latest forecast indicates a total requirement of £677m over the period 2022/23 to 2028/29. Wider economic factors also continue to influence the Council’s financial position. The main contributors are nationally recognised pressures in demand service-based areas including Homelessness, Social Care and Special Education Need and Disabilities (SEND), which continue to pose a financial risk. 1.3. In order to secure financial sustainability, the Council must continue to deliver against the financial targets set as part of the intervention plan including agreed savings targets, plans for divestments and asset disposals and maintaining a prudent capital programme to minimise borrowing. The Council is progressing well with these targets. In the current financial year savings of £17.8m are forecast for delivery and an underspend in excess of £11m is forecast which will contribute to debt reduction and support the Council’s transformation journey. £13.9m of service efficiencies and transformation opportunities have been identified for 2026/27. 64% of the asset disposal programme is forecast for delivery by the end of 2025/26 and the divestment programme will be substantially completed with the exception of a small number of tail end divestments. The Capital Programme remains a delivery challenge with a forecast underspend of 39% which will be subject to a further review prior to coming back to Cabinet in February.
1.4The level of EFS is underpinned by six key financial strategies: • Annual budget • Medium Term Financial Strategy • Captial Programme • Asset Disposal Plan • Divestment Plan • Treasury Management Strategy
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
Thurrock Transport Strategy Adoption2.1 Cabinet approved the Thurrock Transport Strategy given in Appendix 1 to be progressed to Full Council for adoptio...
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.