Grays Town Fund - Grays Riverfront Public Realm & Flood Defence: Design & Build Contract Award, and External Funding
ApprovedExecutive3 papers
AI summaryThurrock Cabinet approves Stage 1 of two-stage Design & Build contract for Grays Riverfront public realm and flood defence scheme, and backs bids to Sport England and the Environment Agency to close a funding gap on the £9m Town Deal project.
Written from the decision and the officer reportPDF Pro
OutcomeApprovedPreferred bidder appointed for pre-construction services only
Money£0.65m Stage 1, £9.0m project budgetStage 1 from Town Fund; tenders exceeded the budget
What happens nextSubmit grant bids, run PCSAFurther Cabinet decision needed to proceed to construction
Who it affectsGrays Riverside and Grays Thurrock wardsRiverside public realm and flood defence
What was decided
Cabinet approved appointing the preferred bidder under a two-stage Design & Build contract and entering Stage 1, a Pre-Construction Services Agreement covering technical design, surveys, statutory consents including river works licences, and value engineering. Report P12, P16
Cabinet approved submitting bids to Sport England's Place Expansion Capital Grant programme and to the Environment Agency's Flood Defence Grant-in-Aid programme, and delegated authority to the Executive Director of Place, in consultation with the section 151 officer and the Portfolio Holder for Good Growth, to finalise and submit them. Report P12, P16
Why
The £9.0m Town Deal allocation for the riverfront scheme is within a wider £19.9m Grays Town Deal grant confirmed in March 2023, and the project responds to obligations under the Thames Estuary 2100 plan while delivering regeneration, public realm and flood defence benefits. Report P11, P14, P17
Both compliant tender bids received through the procurement exceeded the approved funding envelope, so a staged approach was chosen to allow value engineering, statutory consents and cost certainty before any commitment to construction. Report P15, P16, P19
Public engagement in August 2024 showed 83.7% support for the scheme among those giving feedback, and the Grays Town Board approved the approach on 23 October 2025. Report P18
What happens next
Appoint the preferred bidder to the Pre-Construction Services Agreement at an estimated cost of around £0.65m from the Towns Fund, and progress the planning application, statutory consents, surveys and value engineering. Report P16
Prepare and submit bids to the Environment Agency's Flood Defence Grant-in-Aid programme and to Sport England's Place Expansion Capital Grant programme alongside Stage 1. Report P16, P19
Return to Cabinet for a further decision on whether to proceed to Stage 2 construction, and on any future formal maintenance or legal arrangements with the Environment Agency. Report P16, P19, P23
The money
£9.0m Town Deal allocation to the Grays Riverfront Public Realm & Flood Defence project Report P11, P19
£19.9m Total Grays Town Deal grant confirmed in March 2023 Report P14
£10.9m Town Deal allocation to the Grays Beach Riverside Park & Kilverts Field project Report P14
£1.058m Amount already committed on the riverfront project as of December 2025 Report P19
£7.942m Remaining budget after committed expenditure Report P19
£0.65m Estimated cost of Stage 1 PCSA, funded from the Towns Fund Report P16
£1.75m Council revenue contingency that could be called on if Stage 1 costs are written off Report P19
Options considered
Rejected: Option 1: Do Nothing. Would risk Town Deal commitments, statutory flood defence obligations, reputational damage and potential abortive costs, so not recommended. Report P18
Rejected: Option 2: Single-stage Design & Build without PCSA. Would require retendering, reduce pre-construction development, limit value engineering and raise the risk of cost overruns, so not recommended. Report P18
Rejected: Option 3: Do Something Else (replace the project). Would weaken strategic coherence, add delivery risk and still leave TE2100 obligations, with greater risk of abortive costs and reputational damage, so not recommended. Report P18
Chosen: Option 4: Two-stage Design & Build (preferred). Balances financial deliverability, risk management and programme delivery by allowing design, statutory consents and value engineering to be completed before committing to construction. Report P18, P12
Implications
Financial: Tender returns exceeded the £9m Town Deal allocation, creating a material funding gap that Stage 1 value engineering and external bids (Environment Agency and Sport England) are intended to close. Stage 1 costs and the £1.058m already committed would be abortive if Stage 2 does not proceed, with no specific revenue budget to absorb them. Report P15, P19, P21
Legal: The Council relies on the General Power of Competence under section 1 of the Localism Act 2011 and section 111 of the Local Government Act 1972, with the procurement run compliantly under the Public Contracts Regulations 2015. The PCSA must include termination rights, full intellectual property ownership, insurance, liability caps and step-in rights. Report P23
Risk: Principal risks are a budget shortfall, abortive Stage 1 costs, market and inflationary pressures, delays to planning and river works licences, and long-term maintenance of flood defence sections integrated within the public realm amphitheatre, which the Environment Agency will not maintain. Report P21, P23
Equalities: The scheme is expected to improve accessibility and inclusion of public spaces; an initial Equalities Impact Assessment exists for the Grays Riverside Masterplan and individual Community Equality Impact Assessments will follow. No adverse equality implications are identified. Report P25
Climate: The scheme delivers upgraded flood defences in line with the Thames Estuary 2100 plan, supporting climate resilience and protecting homes, infrastructure and public spaces. Report P11, P14, P17
Other: The project is time-constrained: Town Deal grant must be defrayed by March 2028, and continuing without it would risk loss of funding or reliance on alternative sources such as external borrowing. Report P16, P19
Who and where
Residents and businesses in Grays Riverside Ward and Grays Thurrock Ward Report P7
Users of the riverside public realm, including visitors, cyclists and pedestrians Report P11, P17
Riparian communities protected by the upgraded flood defences under the TE2100 plan Report P14, P17
Council as riparian landowner and accountable body for the Town Deal grant Report P14, P19, P23
Environment Agency as statutory lead flood risk authority for main rivers Report P14, P23
Preferred Design & Build contractor and their supply chain Report P16, P21
Sport England as potential funder of cycle circuit, pavilion and skatepark enhancements Report P11, P19
Future Council teams responsible for maintaining any integrated flood defence elements in the public realm Report P19, P23
Timeline
March 2023: Grays Town Deal grant of £19.9m confirmed Report P14
5-28 August 2024: Public engagement period: 113 residents at drop-ins, over 2,000 online visits, 92 feedback forms, 83.7% support Report P18
October 2024: Planning application for the riverfront scheme submitted Report P15
15 October 2025: Place Executive Director Management Team reviewed proposals Report P18
23 October 2025: Grays Town Board approved the proposed approach Report P18
As of December 2025: £1.058m committed on the project, leaving £7.942m remaining Report P19
18 February 2026: Cabinet decision: Stage 1 PCSA and external funding bids approved Report P2, P12
March 2028: Deadline by which Town Deal grant must be defrayed Report P16, P19
Plain English for the jargon
PCSA: Pre-Construction Services Agreement, the Stage 1 contract covering design development, surveys, consents and value engineering before any commitment to build.
D&B: Design & Build, a procurement model where a single contractor is responsible for both designing and constructing the works.
Town Deal: UK government funding programme (here delivered via MHCLG) providing grant to selected towns for regeneration projects.
TE2100: Thames Estuary 2100 Plan, the Environment Agency's long-term strategy for managing flood risk in the Thames estuary through to 2100.
RIBA Stage 2+: Concept design stage of the Royal Institute of British Architects' plan of work, after which planning applications can be submitted.
Riparian owner: Owner of land alongside a watercourse, who holds certain legal responsibilities for that watercourse and its defences.
What was decided, why, and what happens next
Pro reads every officer report for you and explains each decision in plain English: the money, the options, the risks, the timeline, each with the paragraph it came from.
Written by AI from the council's published papers. AI can get things wrong: the council's own wording below is the record.Report a problem
Item323
Resolved
2.1 Design & Build Contract and Funding 2.2 Cabinet approved the appointment of the preferred bidder under a two-stage Design & Build contract and enter into Stage 1 Pre-Construction Services Agreement (PCSA): Technical design development, surveys, statutory consents (including river works licences), and value engineering to produce a fully costed proposal. 2.3 Cabinet approved submission of a bid to Sport England’s Place Expansion Capital Grant programme. 2.4 Cabinet approved submission of a bid to the Environment Agency’s Flood Defence Grant-in-Aid (FDGiA) programme 2.5 Cabinet delegated authority to the Executive Director of Place, in consultation with the section 151 officer and Portfolio Holder for Good Growth to finalise and submit the grant bids referred in paragraphs 2.3 and 2.4.
Word for word from the decision Thurrock published for this meeting.Source: democracy.thurrock.gov.uk
Report to Cabinet Report Title Grays Town Fund - Grays Riverfront Public Realm & Flood Defence: Design & Build Contract Award, and External Funding.
Date of Meeting Wednesday 18 February 2026
Report Author George McCullough, Head of Regeneration
Corporate Director Claire Demmel, Executive Director of Place
Lead Cabinet Member(s) Cllr Lee Watson, Cabinet Member for Good Growth
Why is this a key 1. Expenditure over £500K yes / no decision? 2. Significant impact on 2 or more wards yes /no
Wards Affected Grays Riverside Ward and Grays Thurrock Ward
Identify exempt 3 - Information relating to the financial or business information and affairs of any particular person (including the exemption category authority holding that information) and includes contemplated, as well as past or current activities. The report and Appendix 1 and 3 are public. Appendix 2 is exempt for the reason set out above. Is report Urgent? No
Reasons for urgency Not Applicable (only where applicable)
Appendices (if any) 1. Tonkin Liu Flood Defence Sections Drawings (566 111 P.A to 566 117 P.A). 2. Financial Implication - Exempt. 3. Key Procurement and Design Terms Explained
1. Executive Summary 1.1 The Grays Riverfront Public Realm & Flood Defence scheme is a core component of the Grays Town Deal programme, supported by £9.0m from the Ministry of Housing, Communities and Local Government (MHCLG) Town Deal. 1.2 The scheme will deliver significant public realm improvements alongside flood defence upgrades in line with the Thames Estuary 2100 (TE2100) Plan and is a key intervention in the regeneration of Grays Riverside. 1.3 The project has reached RIBA Stage 2+, a planning application has been submitted, and a two-stage Design & Build procurement process has been undertaken to manage risk, improve cost certainty and support delivery within Town Deal timescales. 1.4 Tender returns received through the procurement process exceed the approved funding allocation. Cabinet approval is therefore sought to appoint the preferred bidder under a two-stage Design & Build contract, committing initially only to Stage 1 (Pre-Construction Services Agreement). This stage will allow the detailed technical design to be progressed, statutory consents to be secured, surveys to be completed and value engineering to be undertaken before any decision is taken on construction. 1.5 The Stage 1 process will enable the contractor and project team to refine the design, explore opportunities to reduce costs through simplification of materials and scope, and confirm whether the scheme can be delivered within the approved funding envelope. Some potential opportunities to reduce costs have been identified which can be explored further during Stage 1, providing a structured process for testing affordability before any commitment is made to construction. 1.6 Cabinet approval is also sought to submit bids for external funding, including the Environment Agency’s Flood Defence Grant-in-Aid and Sport England’s Place Expansion Capital Grant, to help address the funding gap and enhance project outcomes. 1.7 The project includes flood defence elements that are structurally integrated within the public realm. Ongoing discussions are taking place with the Environment Agency regarding future maintenance responsibilities for these elements. While a formal joint maintenance agreement is not required at this stage, clarity on future responsibilities will continue to be progressed alongside the planning and design process and, where necessary, will be subject to appropriate future governance. 1.8 Further detail on the background to the scheme, procurement approach, funding position, risks and implications is set out in Sections 4 to 15 of this report.
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
Thurrock Transport Strategy Adoption2.1 Cabinet approved the Thurrock Transport Strategy given in Appendix 1 to be progressed to Full Council for adoptio...
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.