That Cabinet: 1. Approved the Grays Town Fund Programme and Budget allocations as set in Table 1 of the report. 2. Delegated authority to the Corporate Director of Resources and Place Delivery and the Director of Public Realm, in consultation with the Portfolio Holder for Regeneration and External Affairs, and Assistant Director Legal Services to: a. Approve the Business Case Summaries; b. Submission of planning application for the projects within Grays Town Fund Programme; c. Approve the operation of procurement processes through to the awarding of contracts to commission consultants and contractors to undertake services and works to deliver the Grays Town Fund programme, subject to tendered sums being within the anticipated budget; d. Negotiate and enter into necessary agreements to facilitate delivery of Grays Town Fund programme including access agreements and licences, leases and design and construction contracts. Reason for decision: as outlined in the report This decision is subject to call-in
Word for word from the decision Thurrock published for this meeting.Source: democracy.thurrock.gov.uk
The development of the Grays Town Fund Programme is progressing in preparation for the submission of the Business Case summaries to the Department of Levelling Up, Homes and Communities (DLUHC) by 5 October 2022. This report sets out the development of the programme to date following the consideration of the initial programme in the Cabinet Report dated 7 July 2021. It also reports the recommendations made by the Grays Town Board with regards to a revised programme of projects and delivery strategy in response to stakeholder project feedback and unprecedented cost inflation issues.
The report highlights key contractual and financial implications for the Council associated with progressing with the recommended project programme, budget and delivery strategy. The report then seeks approval of the Grays Town Fund Programme and budget allocation and to a range of recommendations which will enable the Council to continue to develop and deliver the recommended programme within the programme timetable. It is proposed that, when required, further reports on individual projects will be brought back to the Cabinet for consideration and approval.
1. Recommendation(s)
That Cabinet:
1.1Approve the Grays Town Fund Programme and Budget allocations as set in Table 1 of this report. 1.2 Delegates authority to the Corporate Director of Resources and Place Delivery and the Director of Public Realm, in consultation with the Portfolio Holder for Regeneration and External Affairs, and Assistant Director of Legal Services to:
a. approve the Business Case Summaries, b. submission of planning application for the projects within Grays Towns Fund Programme, c. approve the operation of procurement processes through to the awarding of contracts to commission consultants and contractors to undertake services and works to deliver the Grays Town Fund programme, subject to tendered sums being within the anticipated budget. d. negotiate and enter into necessary agreements to facilitate delivery of Grays Town Fund programme including access agreements and licences, leases and design and construction contracts.
2. Introduction and Background
2.1On the 15 July 2021, DLUHC announced a conditional Town Deal offer of up to £19.9 million for Grays, following submission of Grays Town Investment Plan with a Town Deal ask of £24.9 million to the Ministry for Housing, Communities and Local Government (now DLUHC) in February 2021.
2.2Heads of Terms for Grays Town Deal were accepted on the 5 August 2021 and a list of projects to be delivered under the Town Deal was submitted to DLUHC on the 5 October 2021.
2.3To secure this Town Deal, the Full Business Cases will need to be developed for each of the shortlisted projects and the associated Towns Fund Business Case Summaries will need to be submitted to DLUHC by the 5 October 2022.
2.4The Town Deal projects were shortlisted from Grays Town Investment Plan by Grays Town Board based on their ability to drive Grays’ regeneration agenda and the available grant funding. The Grays Town Investment Plan projects and their respective aims are set below:
Project 1: Station Gateway - £2.64m The project seeks to deliver two buildings on the south side of the rail line to complete the public realm around the underpass and support continuation of the High Street to other Town Fund Projects at the riverfront. This was to include a 350 sq.m cultural facility and 225sq.m of business start-up space, retail and food and drink and provide an arts, culture and event venue attracting 5000 visitors per year.
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
Thurrock Transport Strategy Adoption2.1 Cabinet approved the Thurrock Transport Strategy given in Appendix 1 to be progressed to Full Council for adoptio...
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies