Thurrock Cabinet approved demolishing three Blackshots tower blocks and 17 South Ockendon garages to build 11 affordable council homes, and extended the Mears housing repairs contract by three months at an estimated £3.2m. It noted the 2025/26 outturn, transferring £9.587m to reserves as Exceptional Financial Support fell from £72.128m to £59.070m.
What the committee will consider, in order, with every paper attached to its item. Q4 Financial Outturn 2025/26 is the main business.
To approve as a correct record the minutes of Cabinet held on 23 June 2026.
Decision: Cabinet agreed the following nominations to outside bodies. Anglian (Eastern) Regional Flood & Coastal Committee Cllr R Willoughby Mid and South Essex NHS Foundation Trust Council of Governors Cllr R Willoughby Essex Partnership for Flood Management Cllr D Dennis Essex County Traveller Unit Cllr E Stringer High House Production Park Cllr G Monk Decision page
Decision: Cabinet agreed: 2.1 the key decision threshold as set out in Appendix 1 ; 2.2 All key decisions will be reserved to Cabinet subject to the exceptions set out in paragraph 4.7 below ; 2.3 to delegate all non-key decisions to officers in accordance with the table in Appendix 2; 2.4 all changes will apply to council decisions made on or after 1 October 2026 2.5 to refer these decisions to Full Council to adopt as part of the Council’s Constitution. Decision page
Decision: 2.1 Cabinet agreed the approach (as set out in sections 5 and 6 of this report) to ensure the Pride in Place Impact Fund benefits Thurrock communities with a range of projects informed by local engagement and data and insight, that meet the Government requirements by the end of March 2027 deadline. Cabinet agreed that decisions about individual projects are delegated to the lead Director in consultation with their Executive Director, S151 officer and Cabinet Member for Deregulation, Civic Pride... Decision page
Decision: 2.1 Approve the procurement of a contract for the Processing of Dry Mixed Recyclables, for an initial term of three years to run from 1 st April 2027, with two optional one-year extensions (3 +1 +1). 2.2 Delegate authority to the Executive Director of Place, Property & Development, in consultation with the Chief Finance Officer S151 and the Cabinet Member for Regeneration and Environment, to: 2.2.1 Approve the commencement of the procurement process. 2.2.2 Provided the bids received are within... Decision page
Decision: 2.1 Cabinet approved the prudential indicators for 2025/26 and treasury indicators included in the report (at paragraphs 8.6, 9.2, 10.3 and 11.1). 2.2 Cabinet approved the approach for the separation of the external debt pool into HRA and non-HRA with effect from 1 April 2026 (as set out in Section 14). 2.3 Cabinet noted the Annual Treasury Management Report for 2025/26 and the progress towards the service objectives. Decision page
Decision: 2.1 Cabinet Noted: The annual pipeline of procurement activities with a value exceeding £25,000 for 2026/27 financial year (as identified in Appendix 2). The summary of all contracts awarded over £25,000 during the 2025–2026 financial year. The requirements for procurement activity are subject to council departments confirmation of the continued requirement for the service, goods or works, identification of approved budget source and any additional approvals required. A separate standalone... Decision page
Decision: a) Cabinet noted the 2025/26 revenue and capital outturn position. b) Cabinet approved the transfer of £9.587m to reserves to meet known future liabilities and support the Council’s ongoing financial sustainability. c) Cabinet noted the reduction in the Exceptional Financial Support requirement from £72.128m to £59.070m and to note that the exceptional financial support requirement for 2025/26 is indicative at this stage and will be subject to the completion of the external audit of the... Decision page
Decision: Cabinet Agreed: - 2.1 The proposed site area for the redevelopment of 7 homes on the land to the rear of 20 – 52 Anton Road (Anton South) shown at Appendix A; 2.2 The proposed site area for the redevelopment of 4 homes on the land to the rear of 86-124 Anton Road (Anton North) shown at Appendix B; 2.3 The model for delivery of these projects is self-delivery by the council within the HRA; 2.4 That the purposes for which Anton South and North have, to date, been held is no longer required; 2.5... Decision page
Decision: Cabinet agreed: 2.1to the demolition of Morrisson House, Bevan House and Keir Hardie House at the Blackshots Estate. A location plan is at Appendix A. 2.2 Noted that the costs of the demolition will be funded through a one?off application of HRA reserves, reflecting the non?recurring nature of the expenditure and the need to address immediate safety, security and financial risks associated with retaining vacant high?rise buildings 2.3 Approved the commencement of a competitive tendering process... Decision page
Decision: Cabinet agreed to: 2.1 Approve the extension of the Council’s current responsive repairs and maintenance contract with Mears for the period 1 August 2026 to 31 October 2026, at an estimated value of £3,200,000, comprising £2,700,000 for responsive repairs and voids, calculated on a three-month pro-rata basis from the annual £10.8 million budget allocated to the Mears contract for responsive repairs and voids, and £500,000 for capital expenditure during the three-month extension period to... Decision page
Item 369 is where most of this meeting's papers sit: 7 papers, about 3.6 MB.
This committee has dealt with the subject before.
Get the decision the day it is recorded, and anything that comes back to the committee on this subject.
All 27 papers in one list, with the item each belongs to, its size, and our copy of it. Download any paper from our archive once signed in; read and search it here with Pro.
The committee last met on 23 June 2026. None of its items return this time; 10 items are new. Point at any item to follow a thread. Procedural items are left out.
Appointment to Outside Bodies, Statutory and Other Panels, Floating Support Service - Mental Health & Learning Disabilities, Procurement of Statutory Out of School Tuition Services for Children & Young People, New Lease Agreements for Council Properties do not return this time.
See the 23 June meetingEvery Cabinet meeting we have read, the dates it has set for the future, and each time those dates have changed.
Choose what you want to hear about. The preview is built from this committee's real papers and changes, so you can see what would have reached you.
Thurrock, Cabinet
One alert, sent weekly, on titles and decisions.
Unlimited alerts the same day, searching every page.
Your team, with every match pushed into your own tools.
Every council's records in your own products and research.
Papers, decisions and date changes for the Cabinet, and every other committee you follow, the day they appear.
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Keeps you signed in and runs your free-paper allowance. Always on.
Counts visits and which pages are used. First-party only, no advertising, never shared.