Three month extension of current repairs and maintenance contract for the council's housing stock with Mears Ltd
AgreedExecutive2 papers
AI summaryThurrock Cabinet approves a three month extension of the Mears housing repairs contract, from 1 August to 31 October 2026, worth an estimated £3,200,000, to bridge the gap until the new contract starts on 1 November 2026.
Written from the decision and the officer reportPDF Pro
OutcomeAgreedMears Ltd, 1 August to 31 October 2026
Money£3,200,000 estimated valueRevenue £2,700,000, capital £500,000
What happens nextNew contract starts 1 November 2026Officer authority delegated to implement
Who it affectsCouncil housing tenants and leaseholdersResponsive repairs and voids service
What was decided
Cabinet approved a three month extension of the Mears responsive repairs and maintenance contract from 1 August 2026 to 31 October 2026, with an estimated value of £3,200,000, comprising £2,700,000 for responsive repairs and voids and £500,000 for capital expenditure. Report P1, 4.10
Cabinet delegated authority to the Executive Director Place, in consultation with the Lead Cabinet Member, to finalise, execute and implement all contractual, legal, procurement and governance documentation needed for the extension. Report P1, 4.6
Why
The original procurement timetable slipped because bidders needed to resubmit after the Council issued proposed contract amendments and the Essex Pension Fund actuarial assessment in early 2026, pushing the new contract start from 1 July 2026 to 1 November 2026. Report 4.1
The extension is needed to avoid a gap in statutory repairs and maintenance services between 31 July 2026, when the current contract expires, and 1 November 2026, when the new contract begins, and to protect continuity for tenants and leaseholders. Report 4.2, 4.5, 4.20
Officers say the existing Mears contract has performed strongly and the extension supports compliance with landlord obligations, the Social Housing consumer standards and tenant safety during the transition. Report 4.3, 4.8, 8.3
What happens next
Officers will complete a Deed of Extension and the internal contract modification, and update the cumulative whole life value of the contract to include the extension. Report 4.9, 4.14
Mears will continue delivering responsive repairs and voids services, and will carry out £500,000 of capital and compliance work during August, September and October 2026, funded from the existing repairs and maintenance budget. Report 4.10, 4.12, 4.13, P33
The newly procured housing repairs contract, also awarded to Mears, is scheduled to commence on 1 November 2026 following mobilisation. Report 4.2, 4.8, 5.3
The money
£3,200,000 Estimated total value of the three month extension Report P1, 4.10
£2,700,000 Revenue element for responsive repairs and voids, pro-rata from £10.8 million annual budget Report P1, 4.11
£500,000 Capital expenditure for compliance and essential works during the extension Report P1, 4.12
£10.8 million Annual Mears contract budget for responsive repairs and voids Report 4.11
£900,000 Monthly pro-rata figure used to calculate the £2,700,000 revenue element Report 4.11
Options considered
Rejected: Do not extend the existing contract and let it lapse. Would create a material risk of a gap in statutory repairs and maintenance services, risking non-compliance with landlord obligations and the Regulator of Social Housing's Safety and Quality Standard Report 5.1, P27
Rejected: Seek a stop-gap arrangement with an alternate supplier. Too little time for a lawful interim procurement and would create two transitions in quick succession, increasing disruption and accountability risks Report 5.2, P29
Rejected: Start the new contract on an earlier date. The new contract contains revised requirements that need a mobilisation period; an earlier start would increase operational and service delivery risks Report 5.3, P31
Implications
Financial: The £3,200,000 extension is funded from the existing repairs and maintenance budget provision for the period, not from additional budget provision. Report 4.13, P33
Legal: The extension will be implemented under Regulation 72(1)(e) of the Public Contract Regulations 2015 and is not considered a substantial modification; risk of procurement challenge is assessed as low. Report 10.3, 10.4
Risk: Without the extension the Council faces immediate operational, legal, regulatory and reputational risk, including deterioration in stock condition and inability to meet statutory repairing obligations. Report 8.1, 8.2, 8.3, P41, P43
Equalities: Officers conclude the extension does not in itself create direct equality impacts for protected groups, and no Customer Impact Assessment is needed. Report 11.1, P62
Governance: The decision is being taken under the urgency general exception process because 28 days' notice could not be given; the Chair of Overview and Scrutiny has been notified. Report 10.6, 4.16, 4.17
Who and where
Council housing tenants and leaseholders receiving the responsive repairs and voids service Report 4.5, 4.8, 8.2
Mears Ltd, the current and newly appointed repairs contractor Report 4.2, 4.3, 5.3
The Council's Housing service and the Executive Director Place Report P1
Timeline
2015: Current Mears contract originally procured on a 5+5 year basis to 2025 Report 4.3
January 2024: Prior procurement exercise for a new contract initiated Report 4.4
December 2025: Bidders submitted tender proposals to the Council Report 4.1
January 2026: Council issued proposed contract amendments Report 4.1
Early May 2026: Contract award decision made on the new housing repairs contract Report 4.16
27 May 2026: New Leader and Cabinet appointed following local elections Report 4.17
30 June 2026: Original expiry of the current responsive repairs contract Report 4.2
15 July 2026: Cabinet decision to approve the further three month extension Report 4.15
1 to 31 July 2026: One month extension to the current contract approved by the Leader under special urgency Report 4.2
1 August 2026 to 31 October 2026: Period covered by the approved three month extension Report P1
1 November 2026: Planned commencement of the newly procured housing repairs contract Report 4.2, 4.8, 5.3
Plain English for the jargon
Deed of Extension: A legal document used to vary and continue the existing contract for the additional three month period.
Responsive repairs and voids: Day to day repairs reported by tenants and work to empty council homes between tenancies.
Public Contract Regulations 2015: The procurement rules in force when the original contract was awarded, under which Regulation 72(1)(e) allows certain contract modifications.
Urgency general exception: A governance route for key decisions where the usual 28 days' Forward Plan notice cannot be given.
What was decided, why, and what happens next
Pro reads every officer report for you and explains each decision in plain English: the money, the options, the risks, the timeline, each with the paragraph it came from.
Written by AI from the council's published papers. AI can get things wrong: the council's own wording below is the record.Report a problem
Item372
Resolved
Cabinet agreed to: 2.1 Approve the extension of the Council’s current responsive repairs and maintenance contract with Mears for the period 1 August 2026 to 31 October 2026, at an estimated value of £3,200,000, comprising £2,700,000 for responsive repairs and voids, calculated on a three-month pro-rata basis from the annual £10.8 million budget allocated to the Mears contract for responsive repairs and voids, and £500,000 for capital expenditure during the three-month extension period to progress key priorities, including compliance work. 2.2 Delegate authority to the Executive Director Place, in consultation with the Lead Cabinet Member, to finalise, execute and implement all necessary contractual, legal, procurement and governance documentation required to give effect to the recommended three-month extension.
Word for word from the decision Thurrock published for this meeting.Source: democracy.thurrock.gov.uk
For the reasons set out in this report, the Cabinet is recommended to: 2.1 Approve the extension of the Council’s current responsive repairs and maintenance contract with Mears for the period 1 August 2026 to 31 October 2026, at an estimated value of £3,200,000, comprising £2,700,000 for responsive repairs and voids, calculated on a three-month pro-rata basis from the annual £10.8 million budget allocated to the Mears contract for responsive repairs and voids, and £500,000 for capital expenditure during the three-month extension period to progress key priorities, including compliance work. 2.4 Delegate authority to the Executive Director Place, in consultation with the Lead Cabinet Member, to finalise, execute and implement all necessary contractual, legal, procurement and governance documentation required to give effect to the recommended three-month extension.
3. Commissioner’s Comments
3.1The Council needs to ensure that more effective procedures and forward planning is in place, that reflects the complexity of a large re-procurement project. Contract extensions should be agreed early in the process to ensure that mobilisation of the new contract is not rushed, the best possible outcome is achieved for the life of the new contract and best value is achieved in contract negotiations.
3.2The commissioners note the key decision proposed is being treated as a matter of urgency and timescale now permitting can be justified. Noting the points above for future consideration, commissioners are content for this report to be considered. 4. Proposals – the rationale and evidence for the recommendations
Background
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
Thurrock Transport Strategy Adoption2.1 Cabinet approved the Thurrock Transport Strategy given in Appendix 1 to be progressed to Full Council for adoptio...
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.