CouncilMonitor
194 principal councils 228,996 meetings since 2000 2.8 million official papers archived Straight from each council's own publication system
Thurrock Council
Cabinet, Wednesday 15 July 2026 at 6.00pm

Procurement of Processing of Dry Mixed Recyclables Contract

Approved Executive 1 paper

AI summaryThurrock Cabinet approves procurement of a new Dry Mixed Recyclables processing contract, starting 1 April 2027 for an initial three years with two one-year extensions.

AI summaryIn plain English

Written from the decision and the officer reportPDF Pro
OutcomeApprovedInitial three years plus two one-year extensions
Money£3,750,000.00 (existing four-year contract)New contract expected within current budget envelope
What happens nextITT by 7 September 2026; award by 25 November 2026Service starts 1 April 2027
Who it affectsAll wards in ThurrockResidents and commercial waste customers

What was decided

Cabinet approved procuring a new contract for the Processing of Dry Mixed Recyclables, running from 1 April 2027 for an initial three years, with two optional one-year extensions. Report P9, P35

Authority was delegated to the Executive Director of Place, Property and Development, in consultation with the Chief Finance Officer (S151) and the Cabinet Member for Regeneration and Environment, to start the procurement and award the contract to the highest-scoring bidder within budget. Report 2.2

The new contract replaces the existing arrangement with Biffa Municipal Limited, which expires on 31 March 2027, and the contractor's Material Recovery Facility should be within about 40 miles of the Council's waste transfer site. Report 4.2, 1.5

Why

The Council has a statutory duty under the Environmental Protection Act 1990 to collect waste and separately collect recycling, and the current contract ends on 31 March 2027. Report P8, 4.2

Running an open competitive tender is expected to achieve better value for money, share the value of recyclates with the re-processor, and meet Simpler Recycling and future Government requirements. Report P11, 1.6, 4.4

A 3+1+1 term is intended to align with Local Government Reorganisation and avoid forcing a new unitary authority from April 2028 to re-procure immediately, while the contract will include a novation clause. Report P35, 6.5

What happens next

Invitations to tender are intended to be issued by 7 September 2026 and the contract awarded by 25 November 2026, with monthly contract management meetings and KPIs on tonnages, rebates, contamination and onward destinations. Report 1.12, 1.11, 1.4

A Communities and Equality Impact Assessment will be completed before award, and contract changes must follow standing orders and the Procurement Act 2023, with LGR clauses built in. Report 7.1, 3.2, 6.3

Savings or pressures from pEPR, PLA09 behaviour change and the Deposit Return Scheme will be tracked monthly through tonnage, composition and rebate data, and managed within the Waste service revenue budget and Medium Term Financial Strategy. Report 1.1, 1.3, P46, P47

The money

  • £3,750,000.00 Total value of the existing four-year DMR processing contract (exclusive of VAT) Report 1.7, P30

Options considered

  • Rejected: Do nothing at the end of the current contract. Council is required to provide a recycling service and the current contract expires 31 March 2027
  • Rejected: Deliver recycling in-house. Council has no Materials Recovery Facility and building one would require significant capital investment before expiry Report 2.2
  • Rejected: Use another council's contractual arrangements. Locations likely outside the borough and LGR impacts make this unworkable Report 2.3
  • Rejected: Call off from an existing framework. No suitable frameworks currently exist Report 2.4

Implications

  • Legal: Procurement must comply with the Procurement Act 2023 and the Council's Contract Procedure Rules; the Environmental Protection Act 1990 statutory duties drive the requirement. Report 6.3
  • Financial: New contract is expected to stay within the current Waste service revenue budget; any savings from pEPR, PLA09 or DRS will be used first to offset statutory waste costs, then support the Medium Term Financial Strategy. Report 4.3, 4.4, P46, P47
  • Risk: Main financial risk is volatility in recyclates tonnage and market price; mitigations include transparent contract management, monthly KPIs and opening the opportunity to competition. Report P11, P49, P50
  • Equalities: A Communities and Equality Impact Assessment will be completed before award, and Social Value considerations are embedded in the procurement. Report 7.1
  • Other: Contract must include an option to novate to any successor unitary authority under Local Government Reorganisation, and a right to terminate for convenience on reasonable notice. Report 6.5

Who and where

  • All Thurrock wards (residents and commercial waste customers) Report P5, 4.3
  • Council waste service (waste collection, transfer and disposal operations) Report 1.5, 4.3
  • Future unitary authority/authorities created by Local Government Reorganisation from April 2028 Report 6.5, P35

Timeline

  • 7 September 2026: Intended date for invitations to tender to be issued Report 1.12
  • 25 November 2026: Intended date for contract award to the successful bidder Report 1.12
  • 31 March 2027: Expiry of the current DMR processing contract with Biffa Municipal Limited Report 4.2
  • 1 April 2027: Start date of the new DMR processing contract Report P9, 1.12
  • April 2028: Anticipated creation of a new unitary authority under Local Government Reorganisation Report P35
  • 31 March 2030: End of the initial three-year term (before any extensions) Report 6.5

Plain English for the jargon

  • DMR: Dry Mixed Recyclables, the mixed paper, card, plastics, metals and glass collected at the kerbside for recycling.
  • MRF: Material Recovery Facility, the contractor's plant where DMR is sorted into individual recyclates.
  • pEPR: Packaging Extended Producer Responsibility, a UK policy that moves the cost of household packaging waste from councils and taxpayers to packaging producers.
  • DRS: Deposit Return Scheme, a planned scheme adding a refundable deposit to single-use drinks containers, expected to reduce PET, aluminium and steel in DMR.
  • PLA09: A behaviour change programme funded by pEPR aimed at moving recyclable material out of residual waste into recycling, food waste, textile and other routes.
  • Simpler Recycling: Government reforms (part of the Environment Act 2020 Regulations 2024) introducing consistent recyclable waste collections.
  • LGR: Local Government Reorganisation, the planned restructuring of councils expected to create new unitary authorities.
  • KPI: Key Performance Indicator, a measurable target used to judge contract performance such as tonnages, rebates and contamination levels.
  • CEIA: Communities and Equality Impact Assessment, used to identify and mitigate impacts on protected groups before contract award.
What was decided, why, and what happens next

Pro reads every officer report for you and explains each decision in plain English: the money, the options, the risks, the timeline, each with the paragraph it came from.

Written by AI from the council's published papers. AI can get things wrong: the council's own wording below is the record.Report a problem
Item366

Resolved

2.1 Approve the procurement of a contract for the Processing of Dry Mixed Recyclables, for an initial term of three years to run from 1 st April 2027, with two optional one-year extensions (3 +1 +1). 2.2 Delegate authority to the Executive Director of Place, Property & Development, in consultation with the Chief Finance Officer S151 and the Cabinet Member for Regeneration and Environment, to: 2.2.1 Approve the commencement of the procurement process. 2.2.2 Provided the bids received are within budget, to award the contract to the successful bidder who achieves the highest score.
Word for word from the decision Thurrock published for this meeting. Source: democracy.thurrock.gov.uk

Follow this further

Built from Thurrock's papers

What the report saysPro

Report to Cabinet

Report to Cabinet Report Title Procurement of Processing of Dry Mixed Recyclables Contract Date of Meeting Wednesday, 15 July 2026

Report Author Paul Crick, Director for Operations, Transport and Assets – Place Corporate Director Claire Demmel, Executive Director - Place, Property & Development Lead Cabinet Member(s) Cabinet Member for Regeneration & Environment

Why is this a key decision? 1. Expenditure over £500K yes

2. Significant impact on 2 or more wards yes

Wards Affected (All Wards);

Is report Urgent? No

Appendices (if any) N/A

1. Executive Summary 1.1 This report seeks Cabinet approval to procure an external provider for the provision of Processing of Dry Mixed Recyclables, replacing the existing contract that is currently due to expire on 31st March 2027. The proposal is for this contract to be procured by running an open competitive procurement exercise by going out to market.

2. Recommendations For the reasons set out in this report, the Cabinet is recommended to: 2.1 Approve the procurement of a contract for the Processing of Dry Mixed Recyclables, for an initial term of three years to run from 1st April 2027, with two optional one-year extensions (3 +1 +1).

2.2Delegate authority to the Executive Director of Place, Property & Development, in consultation with the Chief Finance Officer S151 and the Cabinet Member for Regeneration and Environment, to: 2.2.1 Approve the commencement of the procurement process. 2.2.2 Provided the bids received are within budget, to award the contract to the successful bidder who achieves the highest score.

3. Commissioner’s Comments 3.1 The procurement of a contract for the processing of dry mixed recycling will ensure that statutory duty to provide waste collections and to separately collect recycling is met. The recycling markets are volatile, and the contract will also share the value of the material collected with the re-processor. The main financial risk from this procurement lies in the tonnage and variability of the market for the price of recyclates collected. Specific contract management will need to be in place, with appropriate and transparent contract management provisions included in the Contract.

3.2Contract modifications must be authorised in accordance with standing orders and public procurement law and as far as possible should be pre-empted within this process. It will be necessary to ensure that the new procurement both drives value and effective service delivery for its duration and is designed for consolidation with simple LGR clauses that requires the contractor to provide support, information requested and engage with any documents required to give effect to LGR at no additional cost to the Council.

3.3The Commissioners are content with this report being considered.

4. Proposals – the rationale and evidence for the recommendations 4.1 In 2020 Cabinet gave delegated authority to the then Corporate Director of Finance, Governance and Property and the Director of Environment, Highways and Counter Fraud in consultation with the Portfolio Holder for Environment, Sports and Leisure for the procurement of the following contract: Processing of Dry Mixed Recycling (DMR)

4.2The contract was awarded for an initial two years to Biffa Municipal Limited, with the option to extend for a further two years. The contract option to extend was exercised and the current term expires on the 31st March 2027.

4.3The current contract provides the ability for the contractor, on behalf of the Council, to recover essential recyclates from the DMR collections from both residents and businesses who use the Councils Commercial Waste service. These recyclates are then sold on the commodities market at competitive rates procured by the incumbents’ traders and contribute to the reduction of fees for the processing costs.

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
Procurement of Processing of Dry Mixed Recyclables ContractReport 166 KB DownloadRead as text

At this meeting

Whole meeting

Who was there

7 of 16 attended
RB
Councillor Richard BingleyChair, present
AB
Councillor Alan BensonVice-Chair, present
AA
Councillor Alex AndersonCommittee Member, apologies
MB
Councillor Milena BingleyCommittee Member, present
TK
Councillor Tom KellyCommittee Member, present
GM
Councillor George MonkCommittee Member, present
SL
Councillor Sara Lisa PoyntzCommittee Member, present
RP
Councillor Robert Percy WilloughbyCommittee Member, present
DC
Dawn CalvertOfficer, in attendance
CD
Claire DemmelOfficer, in attendance
DF
Daniel FenwickOfficer, in attendance
SM
Sheila MurphyOfficer, in attendance

All 16 on the meeting page

More from Thurrock Cabinet

All decisions
MeetingDecisionOutcome
16 Sep 2026 Corporate and Improvement Plan - 2025/26 Quarter 4 and End of Year Performance Report and Annual Report3.1 Cabinet Noted the quarterly Corporate Performance Report at Appendix 1 and consider which performance issues Cabi... Noted Open
16 Sep 2026 Thurrock Transport Strategy Adoption2.1 Cabinet approved the Thurrock Transport Strategy given in Appendix 1 to be progressed to Full Council for adoptio... Approved Open
16 Sep 2026 Proposed Changes to the Essex Coast Recreational Disturbance Avoidance and Mitigation Strategy (RAMS) and Tariff2.1 Cabinet approved the £476 RAMS tariff, as set out in section 9.1 of the Cabinet report; 2.2 Cabinet agreed to wit... Approved Open
16 Sep 2026 High Priority Housing Policies - Housing Adaptations Policy2.1 Cabinet agreed the Council’s Housing Adaptations Policy in Appendix 1 to commence with effect from 1 October 2026... Agreed Open
16 Sep 2026 Matrix Agency Worker 1 year contract extension2.1 Cabinet agreed to utilise the one-year extension option contained within the current contract and extend the exis... Agreed Open

We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies