AI summaryThurrock Cabinet approved demolition of three Blackshots tower blocks and garages, funded by £2.67m of HRA reserves, and a competitive tender to procure a contractor.
Written from the decision and the officer reportPDF Pro
OutcomeAgreedMorrisson House, Bevan House and Keir Hardie House
Money£2.67m from HRA reservesAround 4.5% of total HRA reserves of about £60m
What happens nextCompetitive tender for demolition contractorAward delegated to Executive Director of Place, Property and Development
Who it affectsBlackshots Estate and HRA financesFuture options report due to Cabinet in Autumn 2026
What was decided
Cabinet agreed to demolish Morrisson House, Bevan House and Keir Hardie House on the Blackshots Estate, with demolition funded by a one-off application of HRA reserves. Report P8
Cabinet approved starting a competitive tender process for a demolition contractor and delegated authority to award the contract to the Executive Director of Place, Property and Development, in consultation with the relevant Cabinet member and S151 Officer.
Cabinet noted the cleared site will be secured and maintained, with any temporary use agreed by the Executive Director where it cuts costs or supports local benefits, and that a further Cabinet report on future redevelopment options will come in Autumn 2026.
Why
A December 2022 Cabinet report found the blocks have serious structural and safety problems, including damp and mould, non-compliant external wall systems, and components at the end of their service life, with independent assessments ruling out refurbishment as a fully compliant long-term solution. Report 5.3
Retaining the empty blocks would keep adding costs for security, maintenance, fly-tipping clearance, building safety compliance and Council Tax on empty homes, and would continue to be a concern for local residents. Report 5.1, P8
Officers said demolition removes safety risks, avoids escalating revenue costs and prepares the site for future redevelopment, while buying the Council time before committing to a redevelopment scheme. Report 5.6, P8
What happens next
A competitive tender will be run to appoint a suitably qualified demolition contractor for the three blocks and associated garages. Report 5.6
A further Cabinet report on future options for the Blackshots site will follow completion of an options appraisal, expected in Autumn 2026.
The cleared site will be secured and maintained, with any temporary use agreed by the Executive Director of Place, Property and Development in consultation with the Cabinet member for Regeneration and Environment.
The money
£2.67m Proposed use of HRA reserves to fund the demolition works Report P8
approximately £60m Current total HRA reserves Report P8
4.5% Share of total HRA reserves represented by the £2.67m Report P8
£254,000 per annum Estimated Council Tax payable by the HRA at current 2026 rates if blocks retained Report P8
approximately £508,000 per annum Estimated Council Tax payable once the empty homes premium applies Report P8
£508,000 Estimated annual HRA saving in 2027/28 from removing the liability Report P8
£508,000 Estimated annual HRA saving in 2028/29 and subsequent years Report P8
Options considered
Rejected: Retain the tower blocks in their current condition. Significant ongoing financial burden, safety risks and resident concerns; not considered viable Report 5.1
Rejected: Bundle demolition into a future design-and-build redevelopment contract. Uncertain redevelopment timings made bundling demolition into an uncertain future contract impractical Report 5.4
Rejected: Partial demolition or soft-strip only. Would not resolve safety and security issues, would still leave Council Tax liabilities, and delivered limited benefits for the investment Report 5.5
Chosen: Full demolition via open competitive tender. Clearest route to removing safety risks, avoiding escalating revenue costs, reducing reputational harm, securing best value through competition and not being held up by redevelopment timelines Report 5.6, P6
Implications
Financial: HRA will use £2.67m of reserves, around 4.5% of its total reserves, avoiding premature borrowing and ongoing financing charges; ongoing Council Tax savings of about £508,000 a year from 2027/28. Report P8
Risk: Identified risks include delays in demobilising telecoms masts, rising demolition costs from inflation, higher interest rates, continued safety and security risk if demolition is delayed, and expiry of planning permission in August 2030. Report P9, P10
Legal: The Council relies on the general power of competence in s.1 of the Localism Act 2011, and the procurement must comply with the Procurement Act 2023 and the Council's Contract Procedure Rules; no secure tenants remain, so no demolition notices under Schedule 5A Housing Act 1985 are required. Report 9.1, P13, P14
Equalities: Consultation with neighbouring residents showed a strong preference for demolition and redevelopment, and the Community Equality Impact Assessment expects a positive impact on residents' health and wellbeing; the contractor will be required to meet Equality Act 2010 and Public Sector Equality Duty duties. Report 10.1, P17, P18, P19, P20
Other: Contracts will include social value measures to be delivered in line with the council's social value framework. Report P19
Who and where
Residents of the Blackshots Estate and neighbouring properties Report P7, 10.1, P15
Thurrock Council General Fund, through a corresponding reduction in Council Tax income from the empty blocks Report P8
Telecommunications providers with masts on the blocks, who will need to demobilise before demolition Report P9
The Housing Service Tenants Panel, which has been consulted and is supportive Report P7
Timeline
December 2022: Previous Cabinet report agreed the Blackshots tower blocks have serious structural and safety issues
2026 (current 2026 rates): Estimated Council Tax on the empty blocks is about £254,000 a year, rising to about £508,000 with the empty homes premium Report P8
2027/28: Estimated annual HRA saving of £508,000 from removing the Council Tax liability on the demolished blocks Report P8
2028/29 and subsequent years: Estimated annual HRA saving of £508,000 continues Report P8
August 2030: Current planning permission for demolition expires if work is delayed Report P9
Autumn 2026: Further Cabinet report to follow on future options for the redevelopment of Blackshots
Plain English for the jargon
HRA: Housing Revenue Account, the ring-fenced account councils use for income and spending on council housing
S151 Officer: The council officer with statutory responsibility for the proper administration of its financial affairs
CEIA: Community Equality Impact Assessment, the council's assessment of equalities effects of a proposal
Soft-strip: Removing internal fixtures, fittings and non-structural components from a building before demolition or refurbishment
Empty homes premium: An additional Council Tax charge on homes that have been empty for an extended period
What was decided, why, and what happens next
Pro reads every officer report for you and explains each decision in plain English: the money, the options, the risks, the timeline, each with the paragraph it came from.
Written by AI from the council's published papers. AI can get things wrong: the council's own wording below is the record.Report a problem
Item371
Resolved
Cabinet agreed: 2.1to the demolition of Morrisson House, Bevan House and Keir Hardie House at the Blackshots Estate. A location plan is at Appendix A. 2.2 Noted that the costs of the demolition will be funded through a one?off application of HRA reserves, reflecting the non?recurring nature of the expenditure and the need to address immediate safety, security and financial risks associated with retaining vacant high?rise buildings 2.3 Approved the commencement of a competitive tendering process to procure a suitably qualified demolition contractor for the three tower blocks and associated garage structures 2.4 to delegate authority to the Executive Director of Place, Property and Development in consultation with the Cabinet member for Regeneration and Environment, and S151 Officer to award the demolition contract following completion of the procurement process. 2.5 that the cleared site be secured and maintained following demolition, with any temporary use of the cleared site to be agreed by the Executive Director of Place, Property and Development in consultation with the Cabinet Member for Regeneration and Environment where this would reduce costs and support local benefits. 2.6 Noted that a further report to Cabinet on future options for the redevelopment of Blackshots is to be brought to Cabinet in Autumn 2026 following completion of an options appraisal.
Word for word from the decision Thurrock published for this meeting.Source: democracy.thurrock.gov.uk
Report to Cabinet Report Title Blackshots Towers and Garages Demolition
Date of Meeting Wednesday 15th July 2026
Report Author Keith Andrews – Head of Housing Development
Corporate Director Claire Demmel - Executive Director of Place, Property and Development Lead Cabinet Member(s) Cllr Tom Kelly – Portfolio Holder for Regeneration & Environment
Why is this a key 1. Expenditure over £500K yes decision? 2. Significant impact on 2 or more wards No
Wards Affected Little Thurrock Blackshots
Identify exempt 3 - Information relating to the financial or business information and affairs of any particular person (including the exemption category authority holding that information) and includes contemplated, as well as past or current activities.
This report is public but Appendix 2 is exempt for the reason above.
Is report Urgent? No
Reasons for urgency N/A (only where applicable)
Appendices (if any) 1. Site Location Plan – Blackshots Estate
2. Exempt Appendix 1. Executive Summary This report seeks Cabinet approval to demolish the three vacant tower blocks and associated garage structures at Blackshots, commence a tender exercise and appoint a selected contractor for their demolition. The blocks have been fully vacated of residents in anticipation of redevelopment and demolition is now considered necessary. Not demolishing the blocks would lead to continuing rising security and maintenance costs. The development of the site would be brought back to Cabinet for consideration. 2. Recommendations For the reasons set out in this report, the Cabinet is recommended to: 2.1 Agree to the demolition of Morrisson House, Bevan House and Keir Hardie House at the Blackshots Estate. A location plan is at Appendix A.
2.2Note that the costs of the demolition will be funded through a one‑off application of HRA reserves, reflecting the non‑recurring nature of the expenditure and the need to address immediate safety, security and financial risks associated with retaining vacant high‑rise buildings
2.3Approve the commencement of a competitive tendering process to procure a suitably qualified demolition contractor for the three tower blocks and associated garage structures
2.4Agree to delegate authority to the Executive Director of Place, Property and Development in consultation with the Cabinet member for Regeneration and Environment, and S151 Officer to award the demolition contract following completion of the procurement process.
2.5Agree that the cleared site be secured and maintained following demolition, with any temporary use of the cleared site to be agreed by the Executive Director of Place, Property and Development in consultation with the Cabinet Member for Regeneration and Environment where this would reduce costs and support local benefits.
2.6Note that a further report to Cabinet on future options for the redevelopment of Blackshots is to be brought to Cabinet in Autumn 2026 following completion of an options appraisal.
3. Commissioner’s Comments Isolating demolition from an integrated demolition, design and build (D&B) contract allows for early site clearance and some specific risk reduction. However, it can also fracture single-point responsibility and introduce cost, scheduling with separate tender processes, and liability risks for the site redevelopment. With separate contracts the Council lose the leverage of having a single contractor absorb unforeseen below-ground anomalies within a fixed overall project budget.
If the Council must keep the contracts separate, a clearly costed option including the variables above to demonstrate best value should be outlined in this report.
In progressing the procurement, a scoped interface between the demolition contractor’s work and the D&B contractor’s scope is recommended to prevent unforeseen below-ground obstructions or foundation anomalies creating a future issue.
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
Thurrock Transport Strategy Adoption2.1 Cabinet approved the Thurrock Transport Strategy given in Appendix 1 to be progressed to Full Council for adoptio...
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.