Thurrock Council
Cabinet, Wednesday 26 August 2026 at 7.00pm

Purfleet-On-Thames Regeneration Update

Noted Executive 1 paper

AI summaryThurrock Cabinet notes progress on Purfleet-on-Thames regeneration due diligence and authorises the Executive Director to appoint consultants to support negotiating a Development Agreement, with the council's £450,000 costs funded from its Freeport reserve.

AI summaryIn plain English

Written from the decision and the officer reportPDF Pro
OutcomeNoted
Money£450k from Freeport Counterfactual Reserve
What happens nextNot stated
Who it affectsPurfleet-on-Thames ward

What was decided

Cabinet noted the ongoing progress on due diligence required before entering into a Development Agreement for the delivery of Purfleet-on-Thames regeneration. Report P7

Cabinet agreed that the Executive Director of Place, Property & Development has authority, in consultation with the Chief Financial Officer and Executive Director of Corporate Services and Monitoring Officer, to progress the appointment of appropriate consultants to complete remaining due diligence and support negotiation of a Development Agreement, at each party's own cost and risk. Report P7

Cabinet noted that any proposed Development Agreement will be brought back to a future cabinet meeting for decision. Report P7

Why

A previous development agreement with Purfleet Centre Regeneration Limited was terminated in March 2024 because PCRL was not in a position to bring forward sufficient funding, and the council decided it needed to lead the complex project itself. Report P9, 4.7

Officers recommend Muse Places as preferred delivery partner, a subsidiary of Morgan Sindall Group, which is a partner in the English Cities Fund alongside Homes England and Legal and General; commissioners require full commercial, property, legal and financial due diligence before any agreement is signed. Report P9, 4.7, P8

KPMG Legal has advised that a direct award to Muse under the existing Pagabo Developer Led Framework is arguable because Muse and the Morgan Sindall Consortium are part of the same economic operator, but the framework expires on 19th October 2026 and a new framework ITT closed on 3rd July with Morgan Sindall and Muse having submitted a bid. Report P11, 5.1

What happens next

Officers will appoint external specialist advisers using the new Pagabo framework once it is announced, expected before the 19th October 2026 start date, to complete commercial, property, legal and financial due diligence and negotiate a Development Agreement with Muse Places. Report P11, P15

The adviser will review the business plan, supporting financial information, draft Heads of Terms and emerging Development Agreement, distinguishing matters that must be resolved before signing from those to be addressed through conditions or future phase gateways. Report P15

Any proposed Development Agreement will be brought back to a future cabinet meeting for decision, and the Purfleet-on-Thames Community Forum will continue to be engaged ahead of that formal decision. Report P7, P14

The money

  • £450k Allocated from the Freeport Counterfactual Reserve to fund council only costs of external specialist support for the Development Agreement negotiation Report 4.7, P15

Options considered

  • Chosen: Note progress and authorise the Executive Director to appoint consultants to support Development Agreement negotiations. Preferred route to progress due diligence required by commissioners while working at each party's own cost and risk Report P7, 4.7
  • Rejected: Consider alternative options at this stage. Alternative options were considered in the March 2026 Cabinet report and no additional alternatives have been considered for this update Report P13

Implications

  • Financial: The Freeport Counterfactual Reserve is confirmed as sufficient to cover the maximum £450k of council only costs for external specialist support, with each party to the Development Agreement negotiation bearing its own cost and risk. Report P7, P15
  • Legal: KPMG Legal has advised there is a good argument for a direct award to Muse under the existing Pagabo Framework, but the framework expires on 19th October 2026 and the council intends to award under the new framework, with a compliant alternative route to be investigated if Morgan Sindall and Muse are not confirmed on it. Report P11, 5.1, P17
  • Risk: The report states there are no substantive new risk implications for this update, and any request to award a Development Agreement will be returned to Cabinet with full risk implications. Report P16
  • Equalities: There are no additional equality and diversity implications arising from this update. Report P17

Who and where

  • Purfleet-on-Thames ward residents Report P4, P6, P14
  • The council, as the body leading the regeneration and committing £450k of its own costs and future potential liabilities under a Development Agreement Report P7, P15
  • Muse Places and the English Cities Fund, as the preferred delivery partners and likely counterparty to a future Development Agreement Report P9
  • Purfleet-on-Thames Community Forum, which continues to receive updates and will be engaged ahead of any formal Development Agreement decision Report P14

Timeline

  • March 2024: Development agreement with Purfleet Centre Regeneration Limited terminated following an October 2023 Cabinet decision, on the basis PCRL could not bring forward sufficient funding Report P9
  • November 2024: Chief Executive approved entering into a Development Management Services Agreement with Muse Places to deliver a business plan for the regeneration Report P9
  • March 2026: Business Plan presented to Cabinet; Cabinet noted Muse Places as preferred partner and agreed to begin Development Agreement negotiations and due diligence at each party's own cost and risk, with £450k allocated from the Freeport Counterfactual Reserve Report 4.7
  • 12th May 2026: Invitation to Tender for the updated Pagabo Developer Led Framework launched Report P11
  • 3rd July: Pagabo framework ITT closed; bids being assessed Report P11
  • 17th August 2026: Financial and risk implications verified by the Chief Financial Officer and Richard Green Report P15, P16
  • 18th August 2026: Equality and diversity implications verified by Rebecca Lee Report P17
  • 26th August 2026: Cabinet considered this regeneration update report Report P2
  • 19th October 2026: Current Pagabo Developer Led Framework due to expire; new framework expected to be announced before this start date Report P11

Plain English for the jargon

  • Development Agreement: A contract setting out the terms under which a regeneration partner will deliver a development, including funding, planning and legal obligations, used here between the council and Muse Places for Purfleet-on-Thames
  • Purfleet Centre Regeneration Limited (PCRL): The consortium with which the council previously had a development agreement for Purfleet-on-Thames, terminated in March 2024
  • Muse Places: A subsidiary of Morgan Sindall Group and partner in the English Cities Fund, identified as the council's preferred delivery partner for the regeneration
  • English Cities Fund (ECF): A partnership between Homes England, Legal and General and Muse Places that has expressed interest in partnering with the council on the regeneration
  • Pagabo Developer Led Framework: A public procurement framework through which the council may appoint development partners; the current version expires on 19th October 2026 and a successor is being procured
  • Freeport Counterfactual Reserve: A council reserve from which £450k is being allocated to fund the council's own costs of specialist support for the Development Agreement negotiation
  • Development Management Services Agreement (DMSA): An agreement with Muse Places, approved by the Chief Executive in November 2024, to deliver the business plan for the regeneration
What was decided, why, and what happens next

Pro reads every officer report for you and explains each decision in plain English: the money, the options, the risks, the timeline, each with the paragraph it came from.

Written by AI from the council's published papers. AI can get things wrong: the council's own wording below is the record.Report a problem
Item379

Resolved

2.1 Cabinet noted the ongoing progress on the due diligence required ahead of entering into a Development Agreement for the delivery of Purfleet-on-Thames regeneration. 2.2 Cabinet agreed that the Executive Director of Place, Property & Development has authority, in consultation with the Chief Financial Officer and Executive Director – Corporate Services & Monitoring Officer, to progress the appointment of appropriate consultants to complete the remaining due diligence and support the negotiation of a Development Agreement, at each party's own cost and risk. 2.3 Cabinet noted that any proposed Development Agreement will be brought back to a future cabinet meeting for decision.
Word for word from the decision Thurrock published for this meeting. Source: democracy.thurrock.gov.uk

Follow this further

Built from Thurrock's papers

What the report saysPro

Report to Cabinet

Report to Cabinet Report Title Purfleet-on-Thames Regeneration Update

Date of Meeting 26th August 2026

Report Author Mark Bradbury, Director - Strategic Growth Partnerships & Special Projects Corporate Director Claire Demmel, Executive Director of Place, Property & Development Lead Cabinet Member(s) Cabinet Member for Regeneration & Environment Leader of the Council Why is this a key 1. Expenditure over £500K no decision? 2. Significant impact on 2 or more wards no

Wards Affected Purfleet-on-Thames

Identify exempt Choose an item. information and exemption category Not Applicable

1. Executive Summary 1.1 The regeneration of Purfleet-on-Thames is a priority for the Council. The project has the potential to deliver around 2,850 new homes, across a range of tenures, including affordable, focussed around a new a town centre with supporting enabling and community infrastructure, including a bridge over the railway to allow the closure of the level crossing, a redeveloped station, a primary school and medical facilities, along with new employment space. 1.2 This report updates Cabinet on the due diligence being undertaken ahead of a future recommendation to Cabinet to enter into a Development Agreement

2. Recommendations For the reasons set out in this report, the Cabinet is recommended to: 2.1 Note the ongoing progress on the due diligence required ahead of entering into a Development Agreement for the delivery of Purfleet-on-Thames regeneration. 2.2 Agree that the Executive Director of Place, Property & Development has authority, in consultation with the Chief Financial Officer and Executive Director – Corporate Services & Monitoring Officer, to progress the appointment of appropriate consultants to complete the remaining due diligence and support the negotiation of a Development Agreement, at each party's own cost and risk. 2.3 Note that any proposed Development Agreement will be brought back to a future cabinet meeting for decision.

3. Commissioner’s Comments 3.1 Commissioners note the procurement advice received from KPMG Legal and the Council’s intention that an award is made under the new framework. Subject to value verification and the specifications compliance with the established public procurement framework, commissioners are content with this approach and the ongoing progress on the due diligence required ahead of entering into a Development Agreement for the delivery of Purfleet-on- Thames regeneration.

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
Purfleet-On-Thames Regeneration UpdateReport 132 KB DownloadRead as text

At this meeting

Whole meeting
373MinutesOn the agenda
379Purfleet-On-Thames Regeneration UpdateThis decision
380Thurrock Local PlanOn the agenda

Who was there

8 of 12 attended
RB
Councillor Richard BingleyChair, present
AB
Councillor Alan BensonVice-Chair, present
AA
Councillor Alex AndersonCommittee Member, present
MB
Councillor Milena BingleyCommittee Member, present
TK
Councillor Tom KellyCommittee Member, present
GM
Councillor George MonkCommittee Member, present
SL
Councillor Sara Lisa PoyntzCommittee Member, present
RP
Councillor Robert Percy WilloughbyCommittee Member, present
AB
Ashley BaldwinOfficer, in attendance
DF
Daniel FenwickOfficer, in attendance
DS
Dr Dave SmithOfficer, in attendance
RW
Rhiannon WhiteleySecretary, in attendance

On this subject at Thurrock

Search all
  1. Purfleet-On-Thames Regeneration UpdateThis decision
  2. Purfleet-On-Thames RegenerationNoted
  3. Purfleet-On-Thames RegenerationAgreed
  4. Purfleet: Changing name to Purfleet-on-ThamesAgreed

More from Thurrock Cabinet

All decisions
MeetingDecisionOutcome
16 Sep 2026 Corporate and Improvement Plan - 2025/26 Quarter 4 and End of Year Performance Report and Annual Report3.1 Cabinet Noted the quarterly Corporate Performance Report at Appendix 1 and consider which performance issues Cabi... Noted Open
16 Sep 2026 Thurrock Transport Strategy Adoption2.1 Cabinet approved the Thurrock Transport Strategy given in Appendix 1 to be progressed to Full Council for adoptio... Approved Open
16 Sep 2026 Proposed Changes to the Essex Coast Recreational Disturbance Avoidance and Mitigation Strategy (RAMS) and Tariff2.1 Cabinet approved the £476 RAMS tariff, as set out in section 9.1 of the Cabinet report; 2.2 Cabinet agreed to wit... Approved Open
16 Sep 2026 High Priority Housing Policies - Housing Adaptations Policy2.1 Cabinet agreed the Council’s Housing Adaptations Policy in Appendix 1 to commence with effect from 1 October 2026... Agreed Open
16 Sep 2026 Matrix Agency Worker 1 year contract extension2.1 Cabinet agreed to utilise the one-year extension option contained within the current contract and extend the exis... Agreed Open

We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies