AI summaryCabinet named Muse Places as preferred partner for Purfleet-on-Thames regeneration and approved up to £450k from the Freeport Counterfactual Reserve for negotiation costs. Officers will now negotiate a development agreement and report back to a future cabinet.
Written from the decision and the officer reportPDF Pro
OutcomeNotedCabinet to negotiate development agreement
MoneyUp to £450kFrom Freeport Counterfactual Reserve for council costs
What happens nextFuture cabinet decisionOn final development agreement
Who it affectsPurfleet-on-Thames areaLocal residents and community groups
What was decided
Cabinet named Muse Places as the preferred partner for delivering the regeneration of Purfleet-on-Thames.
Officers will begin negotiations on a development agreement with Muse Places, covering funding, planning and legal considerations, with both sides working at their own cost and risk. Report 6.1
Cabinet allocated up to £450k from the Freeport Counterfactual Reserve to cover council-only costs of the negotiation and due diligence, including external specialist support.
Why
Regeneration at Purfleet-on-Thames has stalled and needs an experienced partner; the ECF Board has approved the proposed route. Report P15, 7.1
A focused procurement through a framework is faster, cheaper and gives access to pre-assessed partners compared with an open tender. Report 7.2, 7.3
A direct award under the Pagabo Framework is considered compliant with the Council's Contract Procedure Rules and procurement law. Report 8.2, 8.4
What happens next
Officers will negotiate heads of terms and carry out due diligence on funding, planning and legal issues. Report 8.1
Any proposed Development Agreement will be brought back to a future cabinet meeting for decision. Report 8.1
A project board will be set up to oversee the process, with cost control resting with the Chief Finance Officer (s151). Report P15
The money
£450k Allocated from Freeport Counterfactual Reserve to fund council-only costs of negotiations and due diligence
£8.4m Current balance of the Freeport Counterfactual Reserve
Options considered
Chosen: Name Muse Places as preferred partner and negotiate a development agreement. ECF Board approved the proposal; direct award under Pagabo framework is compliant and faster than open tender Report P15, 7.3
Rejected: Run an open procurement process for a development partner. Likely to be lengthy and expensive with no guarantee that experienced developers will bid Report 7.2
Rejected: Do not progress the regeneration. Risk that Homes England claws back earlier funding and the council may have to sell assets to repay Report P13
Implications
Legal: A subsidy control assessment is likely to be required if land is transferred for nil value for regeneration. Report 8.6, P21
Legal: The Pagabo framework is due to expire on 18 April 2026 and is in the process of being extended to 18 October 2026; if not extended, an alternative procurement route would be needed in line with the Procurement Act 2023.
Risk: If the regeneration does not progress, Homes England could claw back earlier funding, potentially requiring the council to sell assets to repay. Report P13
Risk: Major regeneration projects carry significant and ongoing risks from macro-economic and socio-political factors throughout the project lifecycle. Report 7.1, 7.4, P14
Risk: The procurement process could cost more than the £450k allocated, requiring further funding. Report P15
Risk: Third parties could challenge the procurement route, potentially requiring an alternative approach. Report P15
Financial: The council's current high-level financial plan is on a cash-flat basis and not yet sufficient to support a legally binding development agreement; a robust appraisal is needed. Report 6.2
Equalities: There are no equality and diversity implications from this report. Report P24, P25
Who and where
Purfleet-on-Thames Community Forum and local residents Report 5.2, P13
Muse Places (proposed development partner) Report 6.1
Timeline
March 2025: ECF team made a presentation to the Purfleet-on-Thames Community Forum Report 5.2
3 March 2026: Risk implications verified by Janki Patel Report P12
6 March 2026: Financial implications verified by Dawn Calvert; legal implications verified by Helen Nicol Report P7, P23
18 April 2026: Pagabo framework is due to expire
18 October 2026: Possible extended expiry date for the Pagabo framework
Future cabinet meeting (date not set): Any proposed Development Agreement to be brought back to cabinet for decision
Plain English for the jargon
Pagabo Framework: A purchasing framework offering construction and development project support, accessible to most public sector organisations including local authorities.
What was decided, why, and what happens next
Pro reads every officer report for you and explains each decision in plain English: the money, the options, the risks, the timeline, each with the paragraph it came from.
Written by AI from the council's published papers. AI can get things wrong: the council's own wording below is the record.Report a problem
Item344
Resolved
2.1 Cabinet noted that Muse Places are the preferred partner for delivery of the regeneration of Purfleet-on- Thames; 2.2 Cabinet agreed that officers begin negotiations on the terms of a development agreement with Muse Places and undertake due diligence on the issues still to be resolved as set out in this report (to include, but not limited to funding, planning and legal considerations) with the Council and Muse Places working at their own cost and risk during this process; 2.3 Cabinet noted that any proposed Development Agreement will be brought back to a future cabinet meeting for decision. 2.4 Cabinet noted that the Council is allocating £450k from its Freeport Counterfactual Reserve to fund Council only costs incurred to deliver recommendation 2.2 above, including sourcing external specialist support and advice
Word for word from the decision Thurrock published for this meeting.Source: democracy.thurrock.gov.uk
Report to Cabinet Report Title Purfleet-On-Thames Regeneration
Date of Meeting Wednesday, 18th March 2026
Report Author Mark Bradbury
Corporate Director Executive Director of Place
Lead Cabinet Member(s) Cabinet Member for Good Growth
Why is this a key 1. Expenditure over £500K no decision? 2. Significant impact on 2 or more wards no
Wards Affected West Thurrock & South Stifford
Identify exempt information Appendices 1 and 2 are exempt and not for and exemption category publication pursuant to paragraph 3 Schedule 12A Local Government Act 1972 as information in the appendices contains “information relating to the financial or business affairs of any particular person (including the authority holding that information)”. It is in the public interest for the information in the appendices to be exempt at this stage due to the necessity of not prejudicing ongoing negotiations regarding progressing the scheme.
Is report Urgent? No
Reasons for urgency N/A (only where applicable)
Appendices (if any) • Purfleet on Thames Regeneration Business Plan (exempt) • KPMG Review (exempt) 1. Executive Summary 1.1 The regeneration of Purfleet-on-Thames is a priority for the Council. The project has the potential to deliver around 2,850 new homes, across a range of tenures, including affordable, focussed around a new a town centre with supporting enabling and community infrastructure, including a bridge over the railway to allow the closure of the level crossing, a redeveloped station, a primary school and medical facilities, along with new employment space
1.2This report updates cabinet on the work to develop a Business Plan for the delivery of the project and seek agreement that Muse Places, supported by the English Cities Fund, are the Council’s preferred Master Developer for the regeneration of Purfleet-on-Thames. Subject to approval of the recommendation officers will finalise the terms of a Development Agreement prior to bringing this back to Cabinet for final approval. £450,000 will be allocated from the Freeport Counterfactual Reserve to meet the costs of further advice including, but not limited to, planning, legal and financial advice required to finalise the Agreement.
2. Recommendations 2.1 Note that Muse Places are the preferred partner for delivery of the regeneration of Purfleet-on-Thames;
2.2Agree that officers begin negotiations on the terms of a development agreement with Muse Places and undertake due diligence on the issues still to be resolved as set out in this report (to include, but not limited to funding, planning and legal considerations) with the Council and Muse Places working at their own cost and risk during this process;
2.3Note that any proposed Development Agreement will be brought back to a future cabinet meeting for decision.
2.4Note that the Council is allocating £450k from its Freeport Counterfactual Reserve to fund Council only costs incurred to deliver recommendation 2.2 above, including sourcing external specialist support and advice
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
Thurrock Transport Strategy Adoption2.1 Cabinet approved the Thurrock Transport Strategy given in Appendix 1 to be progressed to Full Council for adoptio...
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.