Planning, Transport, Regeneration Overview and Scrutiny Committee agreed this item on Thursday 28 September 2023. Below is the council's own wording, with the papers it was decided on.
That Planning, Transport and Regeneration Overview and Scrutiny Committee notes the written legal opinion, and the financial risk assessment and delegates authority to the Director of Place, in consultation with the Director of Law and Governance and the Portfolio Holder for Regeneration, Strategic Planning and External Relationships and Commissioners (1) to endeavour to negotiate a tripartite exit agreement with Homes England and Purfleet Centre Regeneration Limited and if that is not a viable option to agree a mutual withdrawal, with Homes England, from the Purfleet Housing Grant Determination Agreement which will lead to the determination of the Back to Back GDA with Purfleet Centre Regeneration Limited and (2) to take all steps necessary to terminate the Development Agreement and other associated agreements following the termination of the Grant Determination Agreement and the Back to Back GDA. 2. That Planning, Transport and Regeneration Overview and Scrutiny Committee notes the development option being proposed by PCRL and English Cities Fund and delegates authority to the Director of Place, in consultation with the Director of Law and Governance and the Portfolio Holder for Regeneration, Strategic Planning and External Relationships to negotiate and bring back to Cabinet an alternative development proposal no later than 13 th March 2024 ... view the full minutes text for item 16.
Word for word from the decision Thurrock published for this meeting.Source: democracy.thurrock.gov.uk
Report to Planning, Transport, Regeneration Overview and Scrutiny Committee
Executive summary
In order for Purfleet Centre Regeneration Limited (PCRL) to fulfil its role as lead developer and deliver the planned programme set out in the Development Agreement (DA) they are required to access sufficient additional levels of funding (equity, debt and grant) to bring the project forward and a well-resourced team able to effectively manage all workstreams. PCRL has insufficient equity funding and have sought investment from a number of third parties.
The persistent failure by PCRL to secure additional funding and advance the delivery programme has resulted in a sixth Reservation of Rights letter (RoR) to be issued by Homes England (HE) to Thurrock Council and the Back to Back Agreement with PCRL, in relation to the Grant Determination Agreement (GDA), covering the £75m Housing Infrastructure Fund grant.
The Council is concerned that the there is a material risk that the development milestones as set out in the GDA cannot be achieved. Given the prolonged and continued default position there is a real possibility that Homes England will invoke provisions with the GDA and withdraw the HIF funding and commence legal proceeding against the Council to clawback grant expenditure to date. Officers have assessed, with external legal support, all legal remedies available to the Council to address this default situation and minimise any financial exposure to the Council. Following this assessment it is recommended that the Council agree to mutually withdrawal, with Homes England, from the GDA. This effectively terminates the Purfleet HIF Grant Determination Agreement with Homes England and the Back to Back HIF Grant Determination Agreement with PCRL. Homes England have confirmed in writing that it will not demand or seek repayment of any funding in connection with the Funding Agreement. This is subject to the Council agreeing to the mutual withdrawal and entering into the appropriate deed to enact this.
PCRL have continued to attempt to address the funding situation and the Council is mindful to examine alternative funding options; the latest being a proposal involving the English Cities Fund, a consortium of Homes England, Legal & General and Muse. Whilst encouraging, the response from PCRL to the current RoR letter does not contain sufficient detail for the Council to realistically conclude that the scheme can be delivered within the terms or timeframe of the current Grant Determination Agreement. However, following early engagement with PCRL and representatives of the English Cities Fund, officers believe there is merit in examining further the current proposal. Officers are therefore recommending that that the Council work with PCRL and ECF, over a period of up to 3 months, to establish whether there are firm proposals that could be taken back to cabinet with a recommendation to proceed. Any proposal would need to be developed and delivered outside of the terms of the current GDA and within the terms of the current Development Agreement.
Recommendation
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
Follow Planning, Transport, Regeneration Overview and Scrutiny Committee at Thurrock and we tell you when its next papers are published, before the meeting rather than after it.
Regeneration Projects Update - to follow1.1 That the committee notes the proposed changes to the original programmes and the progress on delivering the Regen...
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.