Decision Notice D150048MEM The report of the Director of Street Scene and Leisure gave details of progress with key projects in the Council’s Capital Plan. It was noted that relevant post implementation reviews would be submitted to the Advisory Board twelve months after the schemes’ completion to assess their success against identified targets. RECOMMENDED: That progress on Capital Plan schemes be noted and relevant future Post Implementation Reviews be brought forward to the Advisory Board for consideration.
Word for word from the decision Tonbridge and Malling published for this meeting.Source: democracy.tmbc.gov.uk
Report of the Director of Street Scene and Leisure Part 1- Public
Matters for Recommendation to Cabinet - Non-Key Decision (Decision may be taken by the Cabinet Member)
1 CAPITAL PLAN PROGRESS REPORT
Summary This report advises Members of progress with key projects contained in the Council’s Capital Plan.
1.1Introduction
1.1.1 It is important that progress on the Council’s Capital Plan programme is kept under regular review and a number of key projects have been updated below. In addition a full update reflecting the current List A schemes relevant to this Board is attached at [Annex 1] for information.
1.1.2 Capital Plan schemes are also subject to Post Implementation Reviews twelve months after completion to assess their success against identified targets. In accordance with the Capital Strategy relevant Post Implementation Reviews will be submitted to this Board for approval and presented in accordance with the template agreed by the Finance, Innovation and Property Advisory Board. No reviews have been brought forward for consideration at this meeting.
1.2Larkfield Leisure Centre – Health Suite
1.2.1 Members may be aware of the current Capital Plan Scheme for the refurbishment of the Health Suite at Larkfield Leisure Centre. The Health Suite is currently in a poor condition and, in liaison with the Tonbridge and Malling Leisure Trust, the project allows for a full refurbishment of the suite, including the provision of a new Spa bath, Sauna, Stream Room, Showers and ventilation system. The designs are currently being finalised with the consultant architect, with the intention to go out to tender in early June. Works are expected to take place in the Summer/Autumn subject to contractor lead-in times.
1.2.2 The total project cost is estimated at £300,000 and following agreement with the Leisure Trust, the Council will achieve an annual revenue saving of £15,000 once the new facilities open to the public.
CommAB-NKD-Part 1 Public 10 June 2015 2
1.3Larkfield Leisure Centre – Ultra Violet Dosing and Auto Backwashing Plant
1.3.1 A new scheme has been approved to enhance the existing plant that provides disinfection of the pools with Ultra Violet dosing and auto backwashing plant. Ultra Violet dosing has previously been installed at Tonbridge Swimming Pool and takes advantage of newer, cleaner technology. The new plant will improve reliability and efficiency.
1.3.2 The works have been tendered and awarded to Sterling Hydrotech for £137,018, slightly below the pre-tender estimate of £140,000. The installation may be undertaken whilst the pool is open but will require careful phasing and the potential of a one/two day closure to each pool. The Council is currently in liaison with the Leisure Trust to establish the most appropriate time for the works to take place, though it is hoped that the works will be complete prior to the summer school holidays.
1.4Tonbridge Town Lock
1.4.1 In partnership with the Environment Agency (EA), the Council has brought forward proposals to enhance the section of riverside at Town Lock, Tonbridge. The works will include provision of a new flood wall, enhancement of the open space, the provision of CCTV and new boater facilities.
1.4.2 Final designs have been approved and tendered and the successful contractor, Interserve, has been appointed. It is envisaged that the works will commence on the 1 June 2015 with a 34 week programme. This is a significant scheme costing a total £1.89m. It is anticipated that the Council’s final financial contribution will be £400,000 with the remainder met by the EA (£700,000) and developer contributions.
1.5Tonbridge River Revetment
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
Follow Communities Advisory Board at Tonbridge and Malling and we tell you when its next papers are published, before the meeting rather than after it.
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.