Decision Notice D150068MEM Members were advised of progress with key projects contained in the Borough Council’s Capital Plan. In addition, a Post Implementation Review related to the pipework surrounding the outdoor pool at Tonbridge Swimming Pool was brought forward for approval. The details were set out in Annex 2 of the report. The current position regarding the refurbishment of the health suite and ultra violet disinfection at Larkfield Leisure Centre, potential improvements to facilities at Leybourne Lakes Country Park, the Tonbridge Town Lock project and proposals for design works for Wouldham river wall were outlined and noted by Members. With regard to Tonbridge Town Lock Members were assured that regular liaison and discussion with the Environment Agency was ongoing and the project was fully compliant with their recommendations. Members also indicated that any further delays to the project timetable should be avoided where possible. RECOMMENDED : That (1) the Post Implementation Review for Tonbridge Outdoor Pool, as shown at Annex 2 of the report, be approved; and (2) a detailed design for works to Wouldham River Wall be progressed and costed and reported to the January 2016 meeting of the Finance, Innovation and Property Advisory Board.
Word for word from the decision Tonbridge and Malling published for this meeting.Source: democracy.tmbc.gov.uk
Report of the Director of Street Scene, Leisure & Technical Services Part 1- Public
Matters for Recommendation to Cabinet - Non-Key Decision (Decision may be taken by the Cabinet Member)
1 CAPITAL PLAN PROJECTS
Summary This report advises Members of progress with key projects contained in the Council’s Capital Plan and brings forward a Post Implementation Review for approval.
1.1Introduction
1.1.1 It is important that progress on the Council’s Capital Plan programme is kept under regular review and a number of key projects have been updated below. In addition a full update reflecting the current List A schemes relevant to this Board is attached at [Annex 1] for information.
1.1.2 Capital Plan schemes are also subject to Post Implementation Reviews after completion to assess their success against identified targets. In accordance with the Capital Strategy relevant Post Implementation Reviews will be submitted to this Board for approval and presented in accordance with the approved template.
1.2Post Implementation Reviews
1.2.1 One Post Implementation Review has been brought forward for Member consideration and approval and is shown at [Annex 2]. The scheme relates to pipework surrounding the outdoor pool at Tonbridge Swimming Pool.
1.2.2 The project was completed on timescale with a small overspend of £4,000.
1.3Larkfield Leisure Centre – Refurbishment of Health Suite
1.3.1 The Health Suite at Larkfield Leisure Centre is currently in a poor condition and the project allows for a full refurbishment of the suite, including the provision of a new Spa bath, Sauna, Stream Room, Showers and ventilation system.
1.3.2 The works have recently been tendered and, following a detailed tender evaluation, a contractor has been selected. The tender price was above the pre- tender estimate and the financial shortfall has been met by a financial contribution
CommunitiesAB-NKD-Part 1 Public 16 September 2015 2
from the Leisure Trust and virements from other existing schemes within the Capital Plan. In order to enable the scheme to be progressed in accordance with the existing timescale, approval of the funding has been granted under Section 4, Paragraph 14.2 of the Financial Procedure Rules by the Leader, Chairman of the Overview and Scrutiny Committee, the Group Leader of the Opposition, the Cabinet Members for Finance and Communities, the Chief Executive, the Director of Finance and Transformation and the Director of Central Services and Monitoring Officer. A detailed report on the tender evaluation and financing of the project is being considered by the Overview and Scrutiny Committee on 15 September 2015. It is the intention that works will commence on site in September with completion in early December 2015.
1.4Larkfield Leisure Centre – Ultra Violet Dosing and Auto Backwashing Plant
1.4.1 This scheme was brought forward to enhance the existing plant that provides disinfection of the pools with Ultra Violet dosing and auto backwashing plant. Ultra Violet dosing has previously been installed at Tonbridge Swimming Pool and takes advantage of newer, cleaner technology. The new plant will improve reliability and efficiency.
1.4.2 I am pleased to advise Members that the works have been completed and a Post Implementation Review will be brought forward to a future meeting of this Board for Member consideration.
1.5Leybourne Lakes Country Park
1.5.1 A List C project for evaluation is currently in the Council’s Capital Plan for improved facility provision at Leybourne Lakes Country Park. The scheme identifies the potential improvements to include the provision of an education room/facility and general improvements to the water sports facilities/area.
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
Follow Communities Advisory Board at Tonbridge and Malling and we tell you when its next papers are published, before the meeting rather than after it.
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.