Decision Notice D170052MEM The report updated progress on a number of key projects contained in the Borough Council’s Capital Plan. In addition, three Post Implementation Reviews were brought forward for consideration and approval. Particular reference was made to measures to increase parking provision at Leybourne Lakes Country Park. It was noted that this project was currently on List A. In addition, temporary measures were in place to increase car parking at Haysden Country Park. These measures would be monitored over the coming months and the findings reflected in the Capital Plan Evaluation to be considered by Members at a future meeting of the Finance, Innovation and Property Advisory Board. Finally, local Members referred to the recent improvements made to the play equipment at Larkfield recreation ground, which had been positively received and was a well-used facility. RECOMMENDED: That (1) the updates on the current Capital Plan, as set out in Annex 1 of the report, be noted; (2) the Post Implementation Review for Larkfield Recreation Ground Play Improvements, as set out in Annex 2 of the report, be approved; (3) the Post Implementation Review for Tonbridge Racecourse Sportsground Bridge Renewal/Repair, as set out in Annex 3 of the report, be approved; and (4) the Post Implementation Review for DDA Audit Recommendations – Phase 3, as set out in Annex 4 of the report, be approved.
Word for word from the decision Tonbridge and Malling published for this meeting.Source: democracy.tmbc.gov.uk
Report of the Director of Street Scene, Leisure & Technical Services Part 1- Public
Matters for Recommendation to Cabinet - Non-Key Decision (Decision may be taken by the Cabinet Member)
1 CAPITAL PLAN PROJECTS
Summary This report advises Members of progress with key projects contained in the Council’s Capital Plan and brings forward three Post Implementation Reviews for consideration and approval.
1.1Introduction
1.1.1 It is important that progress on the Council’s Capital Plan programme is kept under regular review and a number of key projects have been updated below. In addition, a full update reflecting the current List A schemes relevant to this Board is attached at [Annex 1] for information.
1.1.2 Capital Plan schemes are also subject to Post Implementation Reviews after completion to assess their success against identified targets. In accordance with the Capital Strategy relevant Post Implementation Reviews will be submitted to this Board for approval and presented in accordance with the approved template. Three Post Implementation Reviews has been brought forward for Member consideration and are detailed at [Annexes 2-4].
1.2Leybourne Lakes Country Park – Additional Car Parking
1.2.1 Currently on List A, the project aims to increase parking provision within the main car park by increasing the number of bays (approximately 30) within the current overflow car park. Initial works have taken place to transplant trees that will be affected and quotes are currently being sought for the creation of the new bays.
1.2.2 The total project cost is estimated at £17,000 with £9,700 being funded from receipts from South East Water, secured in relation to a recent Easement Agreement connected to the Park. The works are due to be completed prior to the school summer holiday period.
Communities&HousingAB-NKD-Part 1 Public 24 July 2017 2
1.3Haysden Country Park – Additional Car Parking
1.3.1 Currently within the Council’s Capital Plan for evaluation, this project looks to review current parking provision on site with the potential to increase parking capacity in response to increasing visitor numbers.
1.3.2 It has recently become apparent that at peak times the current main car park cannot accommodate visitor demand to the Country Park, with cars parking along the main driveway or not being able to park at all. In response to this, temporary measures have recently been put in place that have included the removal of the raised beds in the car park and clearance to the end of the existing overflow car park to create approximately 10 additional spaces. Additional temporary parking has also been created within Tile Barn Field that lies beyond the end of the existing overflow cark park; this has created approximately 60 additional temporary parking spaces.
1.3.3 It is the intention to monitor parking provision over the coming months and reflect these findings in the Capital Plan Evaluation that will be considered by Members of the Finance, Innovation and Property Advisory Board in January 2018. Consideration will need to be given to the requirement for further parking and/or the formalisation of current temporary arrangements.
1.4Tonbridge Racecourse Revetment Works
1.4.1 Currently on List A of the Capital Plan the project aims to address erosion and existing collapsing revetment on identified sections of the river bank. Tenders have been sought for the project and it is anticipated that works will commence in early autumn. Works will be dependent on tenders received, Environment Agency Consents and Contractors lead-in requirements. The total project cost is estimated at £120,000 with external funding of £28,000 already secured.
1.5PIR – Larkfield Recreation Ground Play Improvements
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
Follow Communities and Housing Advisory Board at Tonbridge and Malling and we tell you when its next papers are published, before the meeting rather than after it.
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.