Communities and Housing Advisory Board approved this item on Monday 12 November 2018. Below is the council's own wording, with the papers it was decided on.
Decision Notice D180069MEM The report of the Director of Street Scene, Leisure and Technical Services gave details of progress with key projects included in the Council’s Capital Plan and brought forward four post implementation reviews for consideration and approval. RECOMMENDED: That (1) the updates on the current schemes within the Capital Plan, as shown at Annex 1 to the report, be noted; (2) the post implementation review for Haysden Country Park Extension Play Area, as shown at Annex 2 to the report, be approved; (3) the post implementation review for Haysden Country Park Site Improvements, as shown at Annex 3 to the report, be approved; (4) the post implementation review for Larkfield Leisure Centre Pool Disinfection, as shown at Annex 4 to the report, be approved; and (5) the post implementation review for Public Open Space Site Improvements, as shown at Annex 5 to the report, be approved.
Word for word from the decision Tonbridge and Malling published for this meeting.Source: democracy.tmbc.gov.uk
Report of the Director of Street Scene, Leisure & Technical Services Part 1- Public
Matters for Recommendation to Cabinet - Non-Key Decision (Decision may be taken by the Cabinet Member)
1 CAPITAL PLAN PROJECTS
Summary This report advises Members of progress with key projects included in the Council’s Capital Plan and brings forward four Post Implementation Reviews for consideration and approval.
1.1Introduction
1.1.1 It is important that progress on the Council’s Capital Plan programme is kept under regular review and a number of key projects have been updated below. In addition, a full update reflecting all current List A schemes relevant to this Board is attached at [Annex 1] for information.
1.1.2 Capital Plan schemes are also subject to Post Implementation Reviews (PIR) after completion to assess their success against identified targets. In accordance with the Capital Strategy relevant PIR’s will be submitted to this Board for approval and presented in accordance with the approved template. Four PIRs have been brought forward for Member consideration and are detailed at [Annexes 2-5].
1.2PIR - Haysden Country Park – Extension of Play Area
1.2.1 The scheme looked to extend the existing play area at the Country Park providing an enhanced range of facilities for visitors. The scheme was delivered in-line with budget and achieved the identified targets. The scheme was fully funded through external funding including a successful application of £50,000 from SITA. A full copy of the PIR can be found at [Annex 2]
1.3PIR - Haysden Country Park – Site Improvements
1.3.1 The scheme delivered a number of improvements to the western end of Barden Lake. Works included revetment, marginal planting and the provision of new paths and picnic benches. The works have transformed the visual quality of this area of the Park and were delivered in partnership with local volunteers. The total project cost was £54,576 with an external funding contribution of £43,563 from the Cory
Communities&HousingAB-NKD-Part 1 Public 12 November 2018 2
Trust and developer contributions. A full copy of the PIR can be found at [Annex 3]
1.4PIR – Larkfield Leisure Centre Pool Disinfection
1.4.1 The scheme was designed to enhance the existing plant that provides disinfection of the pools with Ultra Violet dosing and auto backwashing. The project aimed to improve reliability and efficiency and these objectives have been met. A full copy of the PIR can be found at [Annex 4]
1.5PIR – Public Open Space – Site Improvements
1.5.1 The scheme has seen improvements made to a number of Public Open Spaces across the borough including Scotchers Field, Tonbridge and Leybourne Lakes Country Park. The scheme was delivered within budget and met the targets set. The total project cost was £97,474 and was fully funded through developer contributions. A full copy of the PIR can be found at [Annex 5]
1.6Leybourne Lakes Country Park – Development Opportunities
1.6.1 Members will be aware that the Council is investigating the potential outsourcing of the management of Leybourne Lakes Country Park. As previously reported to Members of this Board in July it is the intention to go out to tender prior to Christmas and Officers have been in the process of developing the tender documents. It is then the intention to report the outcome of the procurement exercise back to this Board in either February or May 2019 for Member consideration.
1.6.2 Prior to any potential transfer, the Council is intending to undertake necessary path refurbishment works to priority areas within the Park. These works are estimated at £6,000, are fully funded through developer contributions and are due to take place before the end of the calendar year.
1.7Wouldham River Wall
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
Follow Communities and Housing Advisory Board at Tonbridge and Malling and we tell you when its next papers are published, before the meeting rather than after it.
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.