CouncilMonitor
194 principal councils 228,996 meetings since 2000 2.8 million official papers archived Straight from each council's own publication system
Tonbridge and Malling Borough Council
Audit Committee, Monday 27 July 2020 at 7.30pm

Risk Management Update

Noted Finance 3 papers

Audit Committee noted this item on Monday 27 July 2020. Below is the council's own wording, with the papers it was decided on.

ItemAU 20/16

Resolved

RESOLVED : That the escalation of a number of key risks to RED (summarised above and set out in paragraph 1.3.4) as a consequence of the coronavirus pandemic be noted and acknowledged.
Word for word from the decision Tonbridge and Malling published for this meeting. Source: democracy.tmbc.gov.uk

Follow this further

Built from Tonbridge and Malling's papers

What the report saysPro

Report to Audit Committee

Risk management

An update on the risk management process and the Strategic Risk Register.

1.1Introduction

1.1.1 The Risk Management Strategy sets out the Council’s risk management objectives and details the roles and responsibilities of officers, Members and the Council’s partners in the identification, evaluation and cost-effective control of risks.

1.1.2 The Council’s risk management arrangements are designed to ensure that risks are reduced to an acceptable level or, where reasonable, eliminated thereby safeguarding the Council’s assets, employees and customers and the delivery of services to the local community. Examples of risk include budget deficit, cyber/data loss, environmental and reputational.

1.1.3 The current Risk Management Strategy was recommended by this Committee in January and subsequently adopted by Full Council on 18 February 2020.

1.2Risk Management Escalation Process

1.2.1 Effectively risks are assessed/scored in terms of their likelihood/impact.

1.2.2 Any risk evaluated as ‘High Risk’ (score of 15 or above) will be deemed by the Council to be beyond ‘risk tolerance’ and to have exceeded its ‘risk appetite’ and will be escalated immediately. Such risks should be added to the service’s risk register and discussed at the earliest opportunity within the Service Management Team (SMT) to inform a decision as to whether this should be escalated to Management Team by the respective Service Director. Management Team should then consider whether the risk is significant enough for inclusion in the Strategic Risk Register and action this if relevant. A record should be maintained of risks discussed at both SMTs and Management Team and the outcome of those discussions.

Audit - Part 1 Public 27 July 2020 2

1.2.3 Similarly risks identified as “Medium Risk” may be escalated to the appropriate SMT for advice and to ensure they are kept fully aware of the current risks being faced. Risks determined as “Low Risk” should be managed within the service team. It is recommended that SMTs consider periodic review or moderation processes for Service Risk Registers to ensure they are happy with the scores risks have been given and confirm whether there are ‘Medium’ or ‘Low’ risks they wish to consider further.

1.3Strategic Risk Register

1.3.1 The Strategic Risk Register (SRR) is considered to be a ‘live’ document and is updated, as often as is required, by the Management Team. An update of the current strategic risks and how they are being managed as at the time of writing is appended at [Annex 1].

1.3.2 As you would expect the Covid-19 outbreak and its ongoing impact across the Council’s service areas, businesses and the wider community has been added to the SRR. Members are asked to note both the addition and updates since the last iteration of the Register.

1.3.3 To give Members some reassurance as to the effectiveness of the regime outcomes from the risk management escalation process are reported to the meetings of this Committee unless that is there is something that needs to be brought to Members’ attention in the interim. Members have been kept updated with regard to the Covid-19 emergency via the Council’s website and reports.

1.3.4 Not surprisingly, the number of risks that have been re-categorised as RED, for the time being at least, has increased. These are now:

1) Financial position/budget deficit

2) Brexit Impact and Economic uncertainty (Impacted by Coronavirus Pandemic)

3) Corporate Strategy and Savings and Transformation Strategy

4) Waste Services (this was previously categorised as RED, so no change)

1.3.5 Given the significance of the chances as a result of the pandemic, a report on the SRR was also presented to Cabinet at its meeting on 3 June 2020. As we begin to develop plans in response to the pandemic, it is hoped that the risk level can be reviewed again.

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
Strategic Risk Register 20/16Appendix 1 151 KB Download
PDF
Service Risks Identified Jul 2020 20/16Appendix 2 225 KB Download
PDF
Risk Management UpdateReport 120 KB DownloadRead as text

At this meeting

Whole meeting

Who was there

7 of 18 attended
VB
Councillor Vivian BransonChairman, present
MA
Councillor Mrs Ann KempVice-Chair, present
TB
Councillor Timothy BishopCommittee Member, present
NF
Councillor Nick Foyle MCIPD ACIBCommittee Member, present
PH
Councillor Paul HickmottCommittee Member, apologies
SH
Councillor Sarah HudsonCommittee Member, apologies
JL
Councillor James LarkCommittee Member, present
LO
Councillor Lee O'TooleCommittee Member, present
KT
Councillor Kim TannerCommittee Member, present
MJ
Councillor Mrs Jill AndersonOther Member, in attendance
MB
Councillor Matt BoughtonOther Member, in attendance
NH
Councillor Nicolas Heslop BA (Hons)Other Member, in attendance

All 18 on the meeting page

On this subject at Tonbridge and Malling

Search all
  1. Risk Management UpdateThis decision
  2. Risk ManagementNoted
  3. Risk ManagementNoted
  4. Risk ManagementNoted
  5. Risk ManagementApproved
  6. Risk ManagementNoted

More from Tonbridge and Malling Audit Committee

All decisions
MeetingDecisionOutcome
20 Jul 2026 MinutesThat the of the meeting of the Audit Committee held on 13 April 2026 be approved as a correct record and signed by th... Approved Open
20 Jul 2026 Annual Governance Statement 2025/26That the Annual Governance Statement for the year ended 31 March 2026, be endorsed. Decided Open
20 Jul 2026 Draft Statement of Accounts 2025/26That (1) the enclosed unaudited set of Accounts for 2025/26, be noted and endorsed; and (2) the Statement provided by... Noted Open
20 Jul 2026 Review of the Effectiveness of Internal Audit 2025/26That on the basis of the findings of the review, the opinion that the effectiveness of the Internal Audit function fo... Decided Open
20 Jul 2026 External Quality Assessment OutcomeThat the outcomes of the External Quality Assessment (EQA) of the Internal Audit Function, be noted; and the action p... Noted Open

We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies