Risk Management

Noted Executive 5 papers

AI summaryTonbridge and Malling Cabinet noted updates to the Strategic Risk Register, keeping three risks at RED: failure to adopt a Local Plan, local government reorganisation in Kent, and development management decisions.

AI summaryIn plain English

Written from the decision and the officer reportPDF Pro
OutcomeNotedCabinet noted Strategic Risk Register and service risks
MoneyNot stated
What happens nextFurther MTFS updates due in 2026/27Two financial risks may return if position changes
Who it affectsCouncil services and assetsRisks cover planning, staffing, reorganisation and finance

What was decided

Cabinet noted updates to the Strategic Risk Register since the last review, with particular emphasis on RED-rated risks in Annexes 1 and 1(a). Report P8

Cabinet noted the service risks identified in Annex 2. Report P9

Why

The report supports the corporate strategy priority of efficient services and maintaining an effective council through identification and control of risks. Report 2.1, 2.2

Sound risk management is required to safeguard the Council's assets, employees, customers and service delivery. Report 4.2, 10.1, 10.2

What happens next

Management Team will consider removing the financial position and savings and transformation risks from the Strategic Risk Register at the next presentation. Report 6.5, P33, P34

Further updates to the Medium Term Financial Strategy will take place in 2026/27. Report P35

Risk management remains a standing item on Management Team and Service Management Team agendas. Report 9.2

Options considered

  • Rejected: Remove 'Financial position/budget deficit' from Strategic Risk Register. Nil funding gap over 10 year MTFS period; risk considered low for next 12 to 18 months Report 6.5, P33
  • Rejected: Remove 'Achievement of Savings and Transformation Strategy' from Strategic Risk Register. No savings and transformation strategy needed for 2026/27 following budget setting Report P34
  • Chosen: Add new risk on Development Management Decisions to Strategic Risk Register. Issues with South East Water infrastructure assumptions may lead to refund of planning fees and legal costs Report 6.8

Implications

  • Legal: Accounts and Audit Regulations require accounting control systems to manage risk, and Health and Safety law requires effective risk management. Report 10.1, 10.2
  • Financial: Development Management Decisions risk may lead to refund of planning fees, legal costs, and a new saving target affecting MTFS reserve balances. Report 6.8, 6.9
  • Risk: Three risks remain at RED: failure to adopt a Local Plan, local government reorganisation in Kent, and development management decisions. Report 6.10, P42, P43, P44
  • Staffing: Recruitment and Retention of Staff risk reduced from RED to high amber following the recently agreed pay award. Report 6.7
  • Equalities: Decisions recommended have a remote or low relevance to the Equality Act with no perceived impact on end users.

Who and where

  • Council assets, employees, customers and residents receiving services Report 2.2, 4.2
  • Members and officers responsible for risk identification and control Report 4.1

Timeline

  • September 2025: Risk Management Strategy endorsed by Cabinet Report 4.4
  • 28 October 2025: Risk Management Strategy adopted by Full Council Report 4.4
  • January 2026: Previous report on risk management to this Committee Report 6.4, 7.2
  • February 2026: Budget set; nil funding gap recognised over 10 year MTFS period Report P33
  • 13 April 2026: Audit Committee considered risk management Report P10, P22, P37
  • 2026/27: Further updates to the Medium Term Financial Strategy to take place Report P35

Plain English for the jargon

  • SRR: Strategic Risk Register, a live document updated by the Management Team
  • MTFS: Medium Term Financial Strategy covering the Council's financial planning period
  • RED risk: Risk scoring between 15 and 25 on the 5 by 5 likelihood/impact matrix, considered for escalation to the Strategic Risk Register
What was decided, why, and what happens next

Pro reads every officer report for you and explains each decision in plain English: the money, the options, the risks, the timeline, each with the paragraph it came from.

Written by AI from the council's published papers. AI can get things wrong: the council's own wording below is the record.Report a problem
ItemCB 26/58

Resolved

RESOLVED : That (1) the updates to the Strategic Risk Register since the last iteration be noted, with particular emphasis on those risks categorised as RED as shown in Annexes 1 and 1(a) and summarised above; and (2) the service risks identified in Annex 2 be noted.
Word for word from the decision Tonbridge and Malling published for this meeting. Source: democracy.tmbc.gov.uk

Follow this further

Built from Tonbridge and Malling's papers

What the report saysPro

Report to Cabinet

Risk management

1 Summary and Purpose of Report

1.1The report of the Management Team provides an update on the risk management process and the Strategic Risk Register.

2 Corporate Strategy Priority Area

2.1Efficient services for all our residents, maintaining an effective council.

2.2The identification, evaluation, and cost-effective control of risks is essential in safeguarding the Council's assets, employees and customers and the delivery of services to the local community.

2.3The Council endeavours to pursue a forward-looking and dynamic approach to delivering services to the local community and will not be averse to taking a degree of commercial risk. However, it will always exercise a prudent approach to risk taking and decisions will be made within the parameters of the Council's internal control arrangements

Recommendations

3.1Members are asked to:

1) NOTE the updates to the Strategic Risk Register since the last iteration with particular emphasis on those risks categorised as RED as shown in Annexes 1 and 1a; and

2) NOTE the service risks identified in Annex 2.

AC - RTCab P1-Public 13 April 2026 2

4 Introduction and Background

4.1The Risk Management Strategy sets out the Council's risk management objectives and details the roles and responsibilities of officers, Members and the Council's partners in the identification, evaluation and cost-effective control of risks.

4.2The Council's risk management arrangements are designed to ensure that risks are reduced to an acceptable level or, where reasonable, eliminated thereby safeguarding the Council's assets, employees and customers and the delivery of services to the local community. Examples of risk include budget deficit, cyber/data loss, environmental and reputational.

4.3The Council endeavours to pursue a forward-looking and dynamic approach to delivering services to the local community and will not be averse to taking a degree of commercial risk. However, it will always exercise a prudent approach to risk taking and decisions will be made within the parameters of the Council's internal control arrangements, i.e. Constitution, Procedural Rules, etc. These arrangements will serve to ensure that the Council does not expose itself to risks above an acceptable level.

4.4The current Risk Management Strategy was endorsed by this Committee in September 2025 and subsequently adopted by Full Council on 28 October 2025.

5 Risk Management Escalation Process

5.1Effectively risks are assessed/scored in terms of their likelihood/impact.

5.2Following the change to the Strategy in October 2025, the Council has now adopted the nation 5 x 5 risk matrix. This results in the following potential scoring of risks as detailed in the table below;

Score Likelihood 1 2 3 4 5 Reasonably Almost Impact Description Rare Unlikely Likely Possible Certain 1 Low 1 2 3 4 5 2 Moderate 2 4 6 8 10 3 Significant 3 6 9 12 15 4 Severe 4 8 12 16 20 5 Catastrophic 5 10 15 20 25

5.3Amber risks, those scoring between 8 and 12, should be raised at Service Management Team, added to the Service Risks identified list.

5.4Red risks, those scoring 15 to 25, should be considered by Service Management Teams for potential escalation to Corporate Management Team for inclusion onto the Strategic Risk Register (SRR), see the section on escalation later in this

AC - RTCab P1-Public 13 April 2026 3

guidance note. If agreed the Chief Officer raising the concern should add the details required to the SRR.

6 Strategic Risk Register

6.1The Strategic Risk Register (SRR) is considered to be a 'live' document and is updated, as often as is required, by the Management Team.

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
Executive Summary: Strategic Risk Register 26/58Appendix 1 106 KB Download
PDF
Strategic Risk Register 26/58Appendix 1a 135 KB Download
PDF
Service Risks 26/58Appendix 2 492 KB Download
PDF
Report of Management Team 26/58Report 160 KB DownloadRead as text
PDF
Risk ManagementReport 124 KB Download

At this meeting

Whole meeting

Who was there

5 of 9 attended
MB
Councillor Matt BoughtonChair, present
RB
Councillor Robin Betts (Housing, Environment and Economy)Committee Member, present
MC
Councillor Martin Coffin (Finance, Waste and Technical Services)Committee Member, present
DK
Councillor Des Keers (Community Services)Committee Member, present
AM
Councillor Adem Mehmet (Infrastructure and Tonbridge Regeneration)Committee Member, apologies
MT
Councillor Mike Taylor (Planning)Committee Member, present
SC
Councillor Steve CrispOther Member, in attendance
MA
Councillor Mrs Anita Oakley MA BA (Hons)Other Member, in attendance
MR
Councillor Mark RhodesOther Member, in attendance

On this subject at Tonbridge and Malling

Search all
  1. Risk ManagementThis decision
  2. Risk ManagementNoted
  3. Risk ManagementNoted
  4. Risk ManagementApproved
  5. Risk ManagementNoted
  6. Risk ManagementNoted

More from Tonbridge and Malling Cabinet

All decisions
MeetingDecisionOutcome
1 Sep 2026 MinutesThat the of the meeting of the Cabinet held on 30 June 2026 be approved as a correct record and signed by the Chairman. Approved Open
1 Sep 2026 Local Government Reorganisation - Establishment of West Kent Joint CommitteeRESOLVED : That (1) the Secretary of State’s decision to proceed with four unitary councils for Kent and Medway, as s... Noted Open
1 Sep 2026 Budgetary Control 2026/27 to July 2026RESOLVED : That (1) the net favourable variance of circa £66,093 as at the end of July 2026, when compared to the pro... Noted Open
1 Sep 2026 Risk ManagementRESOLVED : That (1) the updates to the Strategic Risk Register since the last iteration, with particular emphasis on ... Noted Open
1 Sep 2026 Artificial Intelligence Governance Framework PolicyRESOLVED : That (1) the , attached at Annex 1, be approved for adoption and implementation; (2) the establishment and... Approved Open