Resolved
That the updates to the Strategic Risk Register since the last iteration with particular emphasis on those risks categorised as ‘RED’ be noted.
Audit Committee noted this item on Monday 4 April 2022. Below is the council's own wording, with the papers it was decided on.
Resolved
That the updates to the Strategic Risk Register since the last iteration with particular emphasis on those risks categorised as ‘RED’ be noted.
An update on the risk management process and the Strategic Risk Register.
1.1Introduction
1.1.1 The Risk Management Strategy sets out the Council’s risk management objectives and details the roles and responsibilities of officers, Members and the Council’s partners in the identification, evaluation and cost-effective control of risks.
1.1.2 The Council’s risk management arrangements are designed to ensure that risks are reduced to an acceptable level or, where reasonable, eliminated thereby safeguarding the Council’s assets, employees and customers and the delivery of services to the local community. Examples of risk include budget deficit, cyber/data loss, environmental and reputational.
1.1.3 The Council endeavours to pursue a forward-looking and dynamic approach to delivering services to the local community and will not be averse to taking a degree of commercial risk. However, it will always exercise a prudent approach to risk taking and decisions will be made within the parameters of the Council’s internal control arrangements, i.e. Constitution, Procedural Rules, etc. These arrangements will serve to ensure that the Council does not expose itself to risks above an acceptable level.
1.1.4 The current Risk Management Strategy was recommended by this Committee in January and subsequently adopted by Full Council on 22 February 2022.
1.2Risk Management Escalation Process
1.2.1 Effectively risks are assessed/scored in terms of their likelihood/impact.
1.2.2 Any risk evaluated as ‘High Risk’ (score of 15 or above) will be deemed by the Council to be beyond ‘risk tolerance’ and to have exceeded its ‘risk appetite’ and will be escalated immediately. Such risks should be added to the service’s risk
Audit - Part 1 Public 04 April 2022 2
register and discussed at the earliest opportunity within the Service Management Team (SMT) to inform a decision as to whether this should be escalated to Management Team by the respective Service Director. Management Team should then consider whether the risk is significant enough for inclusion in the Strategic Risk Register and action this if relevant. A record should be maintained of risks discussed at both SMTs and Management Team and the outcome of those discussions.
1.2.3 Similarly risks identified as “Medium Risk” may be escalated to the appropriate SMT for advice and to ensure they are kept fully aware of the current risks being faced. Risks determined as “Low Risk” should be managed within the service team. It is recommended that SMTs consider periodic review or moderation processes for Service Risk Registers to ensure they are happy with the scores risks have been given and confirm whether there are ‘Medium’ or ‘Low’ risks they wish to consider further.
1.3Strategic Risk Register
1.3.1 The Strategic Risk Register (SRR) is considered to be a ‘live’ document and is updated, as often as is required, by the Management Team. An update of the current strategic risks and how they are being managed as at the time of writing is appended at [Annex 1].
1.3.2 As reported to earlier meetings the Covid-19 pandemic and measures taken in response resulted in a number of risks on the Strategic Risk Register being re- categorised as RED.
1.3.3 For completeness the risks categorised as RED at the time of the January meeting is given below and remains the case.
1) Financial position/budget deficit
2) EU Transition and Economic Uncertainty (severely impacted by Coronavirus Pandemic)
3) Corporate Strategy and Savings and Transformation Strategy
4) Waste Services
5) Local Plan
1.3.4 Members are asked to note the updates in red font since the last iteration of the Register.
1.4Ongoing Risks and Risks Identified by Service Management Teams and Management Team
1.4.1 To give Members some reassurance as to the effectiveness of risk management outcomes from the risk management escalation process are reported to the
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
PDF |
Strategic Risk Register Current 22/16Appendix 1 | 172 KB | Download |
PDF |
Service Risks Identified 22/16Appendix 2 | 113 KB | Download |
PDF |
Risk ManagementReport | 121 KB | DownloadRead as text |
Follow Audit Committee at Tonbridge and Malling and we tell you when its next papers are published, before the meeting rather than after it.
| Meeting | Decision | Outcome | |
|---|---|---|---|
| 20 Jul 2026 | MinutesThat the of the meeting of the Audit Committee held on 13 April 2026 be approved as a correct record and signed by th... | Approved | Open |
| 20 Jul 2026 | Annual Governance Statement 2025/26That the Annual Governance Statement for the year ended 31 March 2026, be endorsed. | Decided | Open |
| 20 Jul 2026 | Draft Statement of Accounts 2025/26That (1) the enclosed unaudited set of Accounts for 2025/26, be noted and endorsed; and (2) the Statement provided by... | Noted | Open |
| 20 Jul 2026 | Review of the Effectiveness of Internal Audit 2025/26That on the basis of the findings of the review, the opinion that the effectiveness of the Internal Audit function fo... | Decided | Open |
| 20 Jul 2026 | External Quality Assessment OutcomeThat the outcomes of the External Quality Assessment (EQA) of the Internal Audit Function, be noted; and the action p... | Noted | Open |
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Keeps you signed in and runs your free-paper allowance. Always on.
Counts visits and which pages are used. First-party only, no advertising, never shared.