RESOLVED : That (1) the review undertaken by Management Team in streamlining the Strategic Risk Register, be noted; and (2) the updates to the Strategic Risk Register since the last iteration with particular emphasis on those risks categorised as ‘RED’, be noted.
Word for word from the decision Tonbridge and Malling published for this meeting.Source: democracy.tmbc.gov.uk
The report provides an update on the risk management process and the Strategic Risk Register.
1.1Introduction
1.1.1 The Risk Management Strategy sets out the Council’s risk management objectives and details the roles and responsibilities of officers, Members and the Council’s partners in the identification, evaluation and cost-effective control of risks.
1.1.2 The Council’s risk management arrangements are designed to ensure that risks are reduced to an acceptable level or, where reasonable, eliminated thereby safeguarding the Council’s assets, employees and customers and the delivery of services to the local community. Examples of risk include budget deficit, cyber/data loss, environmental and reputational.
1.1.3 The Council endeavours to pursue a forward-looking and dynamic approach to delivering services to the local community and will not be averse to taking a degree of commercial risk. However, it will always exercise a prudent approach to risk taking and decisions will be made within the parameters of the Council’s internal control arrangements, i.e. Constitution, Procedural Rules, etc. These arrangements will serve to ensure that the Council does not expose itself to risks above an acceptable level.
1.1.4 The current Risk Management Strategy was endorsed by this Committee in January and subsequently adopted by Full Council on 20 February 2024.
1.2Risk Management Escalation Process
1.2.1 Effectively risks are assessed/scored in terms of their likelihood/impact.
1.2.2 Any risk evaluated as ‘High Risk’ (score of 15 or above) will be deemed by the Council to be beyond ‘risk tolerance’ and to have exceeded its ‘risk appetite’ and will be escalated immediately. Such risks should be added to the service’s risk register and discussed at the earliest opportunity within the Service Management
Audit - Part 1 Public 22 July 2024 2
Team (SMT) to inform a decision as to whether this should be escalated to Management Team by the respective Service Director. Management Team should then consider whether the risk is significant enough for inclusion in the Strategic Risk Register and action this if relevant. A record should be maintained of risks discussed at both SMTs and Management Team and the outcome of those discussions.
1.2.3 Similarly risks identified as “Medium Risk” may be escalated to the appropriate SMT for advice and to ensure they are kept fully aware of the current risks being faced. Risks determined as “Low Risk” should be managed within the service team. It is recommended that SMTs consider periodic review or moderation processes for Service Risk Registers to ensure they are happy with the scores risks have been given and confirm whether there are ‘Medium’ or ‘Low’ risks they wish to consider further.
1.3Strategic Risk Register
1.3.1 The Strategic Risk Register (SRR) is considered to be a ‘live’ document and is updated, as often as is required, by the Management Team. An executive summary of the RED risks has been provided at [Annex 1] and a full update of the current strategic risks and how they are being managed as at the time of writing is appended at [Annex 1a].
1.3.2 As part of the Zurich review Officers have reviewed the scoring on all of the risks identified in order to ensure that the scoring reflects the current position of the risk considered.
1.3.3 For completeness the risks that were categorised as RED at the time of the April meeting is given below.
1) Savings and Transformation Strategy
2) Local Plan
3) Implementation of the Agile software system
4) Procurement
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
Budgetary Control 2026/27 to July 2026RESOLVED : That (1) the net favourable variance of circa £66,093 as at the end of July 2026, when compared to the pro...
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.