RESOLVED : That (1) the updates to the Strategic Risk Register since the last iteration, with particular emphasis on those risks categorised as RED (set out below) be noted; · Achievement of Savings and Transformation Strategy · Failure to agree a Local Plan · Managed exit from Agile System (2) the service risks identified in Annex 2 of the report be noted; and (3) the responsibilities of the Member Risk Champion as detailed in Annex 3 of the report be noted.
Word for word from the decision Tonbridge and Malling published for this meeting.Source: democracy.tmbc.gov.uk
1.1The report of the Management Team provides an update on the risk management process and the Strategic Risk Register. An update is also provided in respect of the work being undertaken within the Council to champion risk management.
2 Corporate Strategy Priority Area
2.1Efficient services for all our residents, maintaining an effective council.
2.2The identification, evaluation, and cost-effective control of risks is essential in safeguarding the Council’s assets, employees and customers and the delivery of services to the local community.
2.3The Council endeavours to pursue a forward-looking and dynamic approach to delivering services to the local community and will not be averse to taking a degree of commercial risk. However, it will always exercise a prudent approach to risk taking and decisions will be made within the parameters of the Council’s internal control arrangements
Recommendations
3.1Members are asked to:
1) NOTE the updates to the Strategic Risk Register since the last iteration with particular emphasis on those risks categorised as RED as shown in Annexes 1 and 1a;
AC - RTCab P1-Public 14 April 2025 2
2) NOTE the service risks identified in Annex 2;
3) NOTE the responsibilities of the Member Risk Champion as detailed in Annex 3.
4 Introduction and Background
4.1The Risk Management Strategy sets out the Council's risk management objectives and details the roles and responsibilities of officers, Members and the Council's partners in the identification, evaluation and cost-effective control of risks.
4.2The Council's risk management arrangements are designed to ensure that risks are reduced to an acceptable level or, where reasonable, eliminated thereby safeguarding the Council's assets, employees and customers and the delivery of services to the local community. Examples of risk include budget deficit, cyber/data loss, environmental and reputational.
4.3The Council endeavours to pursue a forward-looking and dynamic approach to delivering services to the local community and will not be averse to taking a degree of commercial risk. However, it will always exercise a prudent approach to risk taking and decisions will be made within the parameters of the Council's internal control arrangements, i.e. Constitution, Procedural Rules, etc. These arrangements will serve to ensure that the Council does not expose itself to risks above an acceptable level.
4.4The current Risk Management Strategy was endorsed by this Committee in January and subsequently adopted by Full Council on 20 February 2024. At the last meeting of this Committee in January 2025, due to ongoing work to review and update risk management processes within the Council, Members agreed that the next update of the Strategy would be in September 2025.
5 Risk Management Escalation Process
5.1Effectively risks are assessed/scored in terms of their likelihood/impact.
5.2Any risk evaluated as ‘High Risk’ (score of 15 or above) will be deemed by the Council to be beyond ‘risk tolerance’ and to have exceeded its ‘risk appetite’ and will be escalated immediately. Such risks should be added to the service’s risk register and discussed at the earliest opportunity within the Service Management Team (SMT) to inform a decision as to whether this should be escalated to Management Team by the respective Service Director. Management Team should then consider whether the risk is significant enough for inclusion in the Strategic Risk Register and action this if relevant. A record should be maintained of risks discussed at both SMTs and Management Team and the outcome of those discussions.
AC - RTCab P1-Public 14 April 2025 3
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
Budgetary Control 2026/27 to July 2026RESOLVED : That (1) the net favourable variance of circa £66,093 as at the end of July 2026, when compared to the pro...
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.