Resolved
RESOLVED to note the progress on the planned works programme, and that the issue of ‘no access’ needed to be investigated further.
Corporate Overview and Scrutiny Housing Improvement Sub-Committee noted this item on Tuesday 10 March 2015. Below is the council's own wording, with the papers it was decided on.
Resolved
RESOLVED to note the progress on the planned works programme, and that the issue of ‘no access’ needed to be investigated further.
As at end December 2014 there is an overall provision in the 2014/15 capital programme of £6.89m for decent homes and planned works.
There are no legal implications.
Introduction
1. This report provides a summary of progress to date for the following key areas of decent homes and planned works:
Boiler/Heating Upgrades Kitchen & Bathroom Upgrades Roofing Works Electrical Testing/Upgrades External Wall Finishes Sheltered Scheme Lighting Windows & Doors Communal Heating
Boiler & Heating System Upgrades
2. Central Heating Services Ltd (CHS) has upgraded 168 installations from the planned programme. There have also been an additional 35 critical replacements as an emergency response to failing appliances. The overall programme is 71% complete at the end of January. The remaining 29% of the programme has been delayed by access issues. These are being followed up with tenants. 3. Twelve of the high risk open flue boilers have been replaced. The remaining appliances will be replaced as part of the service programme using a planned approach. This will ensure that any vulnerable residents are given support during the course of the works appropriate to their needs. Tenant satisfaction rates remain high with a low number complaints received to date.
External Wall Finishes
4. Works have been completed to a number of properties in the last quarter. A full programme will not be achievable this year however, as our contractor, Mears have faced recruitment problems with obtaining skilled operatives. They have recently recruited additional staff however and although this will have little impact on the current programme, it will allow for an accelerated start next year. It is proposed that part of this year’s funding will be rolled over to 2015/16 and part used to fund urgent works elsewhere.
Roofing Works
5. The roofing programme is running well and completion of work is predicted to all properties on this year’s programme list. It is predicted that any underspend is carried forward to enable a full programme in 2015/16.
Kitchen & Bathroom Replacements
6. The original Kitchen and Bathroom programme was reduced for this year. This was due to a combination of a later start to allow for an improved method of delivery and in Mears recruiting sufficiently experienced operatives to install them. Current performance and customer satisfaction is good.
7. We have received a high number of tenant refusals, but in order to maintain programme numbers we have provided Mears with additional properties and a revised programme. We currently plan to deliver a full budget spend across these activities.
8. Together with Mears we are currently investigating ways of improving the level of tenant refusals and tailoring our approach to ensure maximum take up.
Electrical Testing & Upgrade Programme
9. T Brown has carried out electrical testing to 475 homes which includes properties that were flagged as failing the Decent Homes Standard. Of these 310 properties required upgrading to the electrical installations in order to bring them up to current standards. There are a further 26 addresses which potentially fail the Decent Homes Standard and subject to access, these will be tested and upgraded as necessary before the end of March 2015. 10. The 2015/16 testing and upgrade programme will be based on a 10 year testing cycle in accordance with our Electrical Safety Policy. This will mean a future rolling testing programme of around 450 homes per year.
Windows & Doors
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
PDF |
PLANNED MAINTENANCE PROGRAMME 2014/15 UPDATEReport | 141 KB | DownloadRead as text |
Follow Corporate Overview and Scrutiny Housing Improvement Sub-Committee at Waverley and we tell you when its next papers are published, before the meeting rather than after it.
| Meeting | Decision | Outcome | |
|---|---|---|---|
| 9 Jan 2017 | Committee Work ProgrammeIt was agreed to move this report to later in the year, when it would be considered by the new Housing OS Committee. ... | Agreed | Open |
| 7 Nov 2016 | Tenant Involvement - Mid-year progress reportRESOLVED to note the good progress being made on tenant involvement, and were pleased with the energy and innovation ... | Noted | Open |
| 7 Nov 2016 | New Anti-Social Behaviour Powers for Housing Operations - consultation responses and updated PolicyRESOLVED to endorse the Policy subject to the incorporation of amendments to reflect the suggestions about presentati... | Decided | Open |
| 7 Nov 2016 | Exclusion of press and publicRESOLVED that pursuant to Procedure Rule 20, and in accordance with Section 100A (4) of the Local Government Act 1972... | Decided | Open |
| 4 Jul 2016 | Exclusion of press and publicRESOLVED that, pursuant to Procedure Rule 20, and in accordance with Section 100A(4) of the Local Government Act 1972... | Decided | Open |
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Keeps you signed in and runs your free-paper allowance. Always on.
Counts visits and which pages are used. First-party only, no advertising, never shared.