Planned maintenance programme 2015/16 - Mid year review
NotedScrutiny1 paper
Corporate Overview and Scrutiny Housing Improvement Sub-Committee noted this item on Monday 9 November 2015. Below is the council's own wording, with the papers it was decided on.
RESOLVED to note the progress against the planned maintenance programme at 30 September 2015. Whilst the Sub-Committee was pleased to hear that work was progressing well, they found it difficult to establish this from the report, as only the volume of work completed had been provided without indicating the scale of the planned programme for each work stream. Officers were asked to include a table in the next report showing the number of planned jobs, and number completed, for each work stream.
Word for word from the decision Waverley published for this meeting.Source: modgov.waverley.gov.uk
Report to Corporate Overview and Scrutiny Housing Improvement Sub-Committee
Financial implications
There is a provision in the 2015-16 capital programme for decent homes and planned works. It is anticipated that all work will be completed within the existing budget.
Legal implications
The Decent Homes Standard was introduced by the Government in 2000 and set a ‘decency’ standard to which all social rented housing should be improved and, in some cases, allocated funding to enable that improvement.
Background
1. This report provides a summary of progress to date for the following key areas of decent homes and planned works:-
2. 102 out of a total of 229 properties have now received their heating upgrade. The programme has been profiled for delivery by November. External Wall Finishes
3. Surveys have been completed and instructions issued to Mears to carry out repointing work to 53 properties across the borough. Work is on site and Mears plan to increase resources to accelerate the programme.
Roofing Works
4. Mears have completed 9 pitched roofs to date. Leasehold consultation is progressing on a number of blocks with both flat and pitched roofs and planned completion is by the end of February.
Kitchen & Bathroom Replacements
5. A total of 95 kitchens have been completed as at end of September 2015, with a further 64 in in progress. We have completed installations to 88 bathrooms, with a further 35 in in progress.
6. We are experiencing a high number of refusals for kitchen and bathroom replacements and are using an additional resource to investigate reasons for refusal.
Electrical Testing & Upgrade Programme
7. A total of 300 properties from the list of 562 properties on the programme have been tested to date. Works have been scheduled and are being approved on a rolling programme. The testing programme has been profiled to be delivered by mid- November, allowing all works due for the 2015/16 financial year to be costed up.
Windows & Doors
8. Procurement is currently underway for a new contract and a Framework has been agreed. Properties have been identified and works are planned start in mid-February 2016.
Sheltered Scheme Lighting
9. The project is progressing well with 6 of the 7 emergency lighting systems upgrades being on site. There has been a minor issue with supplies however this is being resolved with the supplier. The programme is expected to be completed on target.
Communal Heating Systems
10. The 3 communal heating systems requiring upgrade have been completed. There have been some minor issues with the way they are operating due to airlocks, but this is being addressed.
Summary
11. Overall the programme has progressed well during Quarter 2 of 2015/16. The table below shows the budgetary information for these workstreams 2015- Planned Maintenance Financial Monitoring - Qtr 2 Total Spend Approved and Budget committed Project £ £ Heating Upgrades 928,000 249,283 Wall Finishes 153,000 76,823 Rooofing 450,525 279,526 Kitchens 1,645,138 1,185,533 Bathrooms 749,760 634,732 Electrical Upgrades 260,000 59,142 Rewiring 321,500 38,188 Doors 30,000 14,188 Windows 270,000 0 Sheltered Lighting 550,000 475,018 Totals £5,728,323 £3,280,271
Recommendation
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
Follow Corporate Overview and Scrutiny Housing Improvement Sub-Committee at Waverley and we tell you when its next papers are published, before the meeting rather than after it.
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.