Resolved
RESOLVED to note the reports on the planned maintenance programmes.
Corporate Overview and Scrutiny Housing Improvement Sub-Committee noted this item on Wednesday 16 September 2015. Below is the council's own wording, with the papers it was decided on.
Resolved
RESOLVED to note the reports on the planned maintenance programmes.
As at end December 2014 there was an overall provision in the 2014-15 capital programme of £6.89m for decent homes and planned works.
The Decent Homes Standard was introduced by the Government in 2000 and set a ‘decency’ standard to which all social rented housing should be improved and, in some cases, allocated funding to enable that improvement.
1. This report provides a summary of progress to date for the following key areas of decent homes and planned works:-
Boiler/Heating Upgrades Kitchen & Bathroom Upgrades Roofing Works Electrical Testing/Upgrades External Wall Finishes Sheltered Scheme Lighting Windows & Doors Communal Heating
Boiler & Heating System Upgrades
2. Central Heating Services Ltd (CHS) upgraded 304 boiler and heating system installations to Council dwellings during 2014-15 against a target figure of 290. 3. 32 of the 63 priority open flue boilers were replaced in 2014-15. The remaining appliances will be replaced as part of the service programme using a planned approach. This will ensure that any vulnerable residents are given support during the course of the works appropriate to their needs.
External Wall Finishes
4. The External Wall Finishes programme proved to be quite small for 2014-15 and affected just 5 properties from the 35 initially identified at desk-top level. Mears successfully completed this work stream with no problems of note recorded.
Roofing Works
5. Roofing works were undertaken by Mears and although started later in the year, good progress was made with a competent sub-contactor delivering this work stream on their behalf. Mears were able to complete roofing works at 44 properties during 2013-14 against a target of 50. The outstanding roofs will be completed early in 2015-16.
Kitchen & Bathroom Replacements
6. The original Kitchen and Bathroom programme was reduced for this year. This was due to a combination of a later start to allow for an improved method of delivery and in Mears recruiting sufficiently experienced operatives to install them.
7. Mears delivered 288 kitchens against a reduced target of 284 during 2014-15. They significantly exceeded their bathroom target and delivered 214 Bathrooms against a reduced target of 174.
Electrical Testing & Upgrade Programme
8. T Brown was the contractor responsible for rewires and electrical upgrades to Council dwellings. They were able to make good progress, completing rewiring and upgrades to 335 properties to bring them up to modern standards. 12 refusals were noted. We have strengthened our no access process and will take court action if necessary.
Windows & Doors
9. Reduced unit costs for this year enabled our contractor to deliver 119 window and door replacements against a target of 105
Sheltered Scheme Lighting
10. Tenders have been received and works are planned to start on site at the end of June 2015.
Communal Heating Systems
11. Urgent works that could be undertaken during the heating season have been completed as planned. 12. Subject to budget approval, the major upgrades will be carried out during the summer when the boilers can be shut-down without disruption.
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
PDF |
Planned maintenance programme 2014/15 outturn and 2015/16 planReport | 75 KB | DownloadRead as text |
Follow Corporate Overview and Scrutiny Housing Improvement Sub-Committee at Waverley and we tell you when its next papers are published, before the meeting rather than after it.
| Meeting | Decision | Outcome | |
|---|---|---|---|
| 9 Jan 2017 | Committee Work ProgrammeIt was agreed to move this report to later in the year, when it would be considered by the new Housing OS Committee. ... | Agreed | Open |
| 7 Nov 2016 | Tenant Involvement - Mid-year progress reportRESOLVED to note the good progress being made on tenant involvement, and were pleased with the energy and innovation ... | Noted | Open |
| 7 Nov 2016 | New Anti-Social Behaviour Powers for Housing Operations - consultation responses and updated PolicyRESOLVED to endorse the Policy subject to the incorporation of amendments to reflect the suggestions about presentati... | Decided | Open |
| 7 Nov 2016 | Exclusion of press and publicRESOLVED that pursuant to Procedure Rule 20, and in accordance with Section 100A (4) of the Local Government Act 1972... | Decided | Open |
| 4 Jul 2016 | Exclusion of press and publicRESOLVED that, pursuant to Procedure Rule 20, and in accordance with Section 100A(4) of the Local Government Act 1972... | Decided | Open |
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Keeps you signed in and runs your free-paper allowance. Always on.
Counts visits and which pages are used. First-party only, no advertising, never shared.