Resolved
The Executive has endorsed the work carried out by the Housing Delivery Board in 2014/15. [CORPORATE OVERVIEW AND SCRUTINY COMMITTEE] [Reason: to summarise the work undertaken by the Housing Delivery Board over the last year].
Executive decided this item on Tuesday 7 July 2015. Below is the council's own wording, with the papers it was decided on.
Resolved
The Executive has endorsed the work carried out by the Housing Delivery Board in 2014/15. [CORPORATE OVERVIEW AND SCRUTINY COMMITTEE] [Reason: to summarise the work undertaken by the Housing Delivery Board over the last year].
WAVERLEY BOROUGH COUNCIL
EXECUTIVE – 7 JULY 2015
Title: HOUSING DELIVERY BOARD ANNUAL REPORT 2014/15
[Portfolio Holder: Cllr Carole King]
1. INTRODUCTION
1.1This report summarises the work undertaken by the Housing Delivery Board in 2014/15. The Terms of Reference require that an annual report be presented to the Executive every year.
1.2The Housing Delivery Board met on the second Monday of every month. The membership was as follows:- Portfolio Holder for Housing Delivery (KW/SS) Portfolio Holder for Finance (JP) Portfolio Holder for Planning (BA) Portfolio Holder for Housing Operations (CK) - Optional Director of Operations (DR) – Chairman Executive Director (PW) Director of Finance and Resources (GC) Head of Housing Strategy and Delivery (JA) Head of Housing Operations (HW) - Optional Head of Planning (ME) Housing Development Officer (LB) Principal Accountant (GP) Legal – (ST/JG) Estates and Valuation Manager (GS) Democratic Services Manager (EMcQ)
1.3The purpose of the Housing Delivery Board is to oversee the delivery of new Council homes, as set out in the Affordable Homes Delivery Plan approved by Full Council on 17 July 2012, and provide a strategic lead to officers.
1.4The functions of the Housing Delivery Board are set out in the Terms of Reference which are reviewed annually: To oversee and contribute to the delivery of the affordable housing programme To receive progress reports on sites in the delivery plan To produce an annual report To engage with Ward Councillors as necessary in relation to particular sites for development or disposal in their wards To monitor the budget for the affordable housing programme To monitor the remodelling of existing housing stock To identify priority sites for each delivery year To deliver the process for the use of consultants To appoint contractors where a tender process has been carried out, including for example establishing a list of professionals. To consider opportunities to deliver additional affordable housing through conversions or remodelling of existing stock holdings To progress items through the Executive and Council, if necessary.
2. REVIEW OF ACHIEVEMENTS IN 2014/15
2.1At each meeting the Housing Delivery Board receives an update on the progress that is being made on committed and proposed development sites. The Housing Delivery Board is briefed on these sites by the designated Lead Officer. The Board considers the recommended actions and provides a strategic steer as required.
2.2Committed spend on new build programme
A capital budget of £7,345,636 from the HRA was committed in 2014/15 to fund the New Affordable Homes programme.
2.3Progress on committed development sites
(a) Station Road, Godalming W. Stirland Limited were appointed as the build contractor to deliver 14 affordable homes at Station Road and building works started in September 2014. The requirement for further archeological excavation works to be carried out by the Surrey County Archaeological Unit beyond the redevelopment area have delayed construction. . The new homes are due to be completed in January 2016.
(b) Sites in Binscombe: Badgers Close, Warren Road and Perrior Road Walkers Construction were appointed as the build contractor and started on site in July 2014. Three new two-bedroom affordable homes were completed at the corner of Warren Road and Perrior Road in March 2015. The properties have been allocated and the tenants moved into their new homes on 19th April 2015. Four 2 bedroom homes at Badgers Close are expected to be completed and handed over by Walker Construction in May 2015.
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
PDF |
Housing Delivery Board Annual Report 2014/2015Report | 85 KB | DownloadRead as text |
Follow Executive at Waverley and we tell you when its next papers are published, before the meeting rather than after it.
| Meeting | Decision | Outcome | |
|---|---|---|---|
| 1 Sep 2026 | Lease Renewal on Unit 3, Enterprise Centre, Farnhamthat 1) Delegated authority be given to the Director of Assets and Property for the granting of the lease of Unit 3, ... | Agreed | Open |
| 1 Sep 2026 | New Contract for Communal Block Cleaning Servicesthat 1) Delegated authority be given to the Director of Housing Service to enter into the Block Cleaning Services con... | Decided | Open |
| 1 Sep 2026 | Acquisition of Land off Hale Road, Adjacent to Farnham Park, Farnhamthat 1) The Executive request consent from West Surrey Shadow Authority to enter into a Conditional Purchase Agreemen... | Agreed | Open |
| 1 Sep 2026 | Waverley Fire Loss - Underinsurance at 13 & 14 Springwood, Station Lane, MilfordRECOMMENDED that Council RESOLVE to: 1) Approve a supplementary estimate increase of £106,269.98 for FY26/27 to be fu... | Approved | Open |
| 1 Sep 2026 | Recycling and Waste Collection and Street Cleansing Services Contracts Arrangements from 1 November 2027that 1) An 8-year extension to the current Waste Collection and Street Cleansing Contract with an option of a contrac... | Approved | Open |
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Keeps you signed in and runs your free-paper allowance. Always on.
Counts visits and which pages are used. First-party only, no advertising, never shared.