Housing Delivery Local Authority Housing Fund Round 4
ApprovedExecutive3 papers
AI summaryWaverley Executive backs £1,527,344 government grant to buy six homes for Afghan resettled families and homeless households, subject to Council approval.
Written from the decision and the officer reportPDF Pro
OutcomeApprovedRecommend to Full Council on 21 April 2026
Money£1,527,344 grant, £3,335,600 schemeBalance £1,816,000 from borrowing
What happens nextCouncil approval 21 April 2026MOU signing, first funding July 2026
Who it affectsSix homes, Afghan and homeless familiesFive for ARP, one for temporary accommodation
What was decided
Accept £1,527,344 of LAHF Round 4 grant and forward finance the purchase of six properties. Report P10
Approve delivery of the scheme on the terms in the report and Exempt Appendix 1. Report P11
Delegate authority to the Joint Assistant Director of Housing, in consultation with the Co-Portfolio Holder and the Joint Assistant Director of Finance, to purchase each property and agree MOU changes. Report P12, P13
Why
The scheme meets the Waverley Corporate Strategy 2024 to 2028 by providing decent, affordable homes and reducing reliance on costly B&Bs and hotels. Report 3.1, 1.2, P53
It supports the Afghan Resettlement Programme and households owed a homelessness duty, while reducing pressure on the Housing Revenue Account and borrowing. Report 3.3, 6.5, P38, P39
An independent viability appraisal shows a positive net revenue position over a 60 year asset life, with payback within 35 years for the Council's own investment. Report 3.4, P78
What happens next
Full Council to consider the budget recommendation of £3,335,600 on 21 April 2026. Report 4.1, P16
Sign the Memorandum of Understanding with MHCLG, with the first tranche of grant released in July 2026. Report 4.2, 1.5
A LAHF Round 4 Project Group will manage delivery, with interim specialist consultant support funded by the revenue element. Report 6.13, P88
The money
£1,527,344 LAHF Round 4 grant funding to be accepted Report P10
£1,519,600 Capital allocation from MHCLG for Round 4 Report 1.3, P69
£7,744 Revenue allocation from MHCLG for Round 4 Report 1.3, P69
£3,335,600 Total scheme cost to be added to capital programme Report P16, P69
£1,816,000 Borrowing to fund the balance of the scheme Report P77
£470,800 Year 1 capital allocation (2026 to 2027) Report P72
£1,048,800 Year 3 capital allocation (2028 to 2029) Report P74
£2,039,531 Previous LAHF Round 1 allocation for 11 homes Report 6.2
£779,161 Previous LAHF Round 3 allocation for 3 homes Report 6.2
Options considered
Rejected: Option 1: Do not accept LAHF Round 4 funding allocation. Would lose the opportunity to leverage subsidy for six additional homes during 2026 to 2030 Report 11.1, P65
Chosen: Option 2: Accept LAHF Round 4 funding allocation (Recommended). Provides value for money, reduces impact on HRA reserves, borrowing and capital receipts that could be used elsewhere Report 11.2, P67, P68
Implications
Financial: Total scheme cost of £3,335,600 with £1,816,000 from borrowing; payback within 35 years for Council investment, 48 years including the LAHF grant. Report P77, P78
Financial: Borrowing assumed at 4% for years 1 to 2, 3% for years 3 to 4 and 2% from year 5; internal borrowing used until external rates reach 2%. Report P79
Legal: Council can purchase properties under Section 9(1)(b) Housing Act 1985 and determine housing allocations under Part VI of the Housing Act 1996. Report P83, P84
Equalities: Equalities Comprehensive Impact Assessment finds no disproportionately adverse impact; five homes restricted to ARP families and one to temporary accommodation, so the Housing Allocations Scheme will be amended. Report P94, P95, P96, P101, P102
Climate: Energy efficiency improvements will be prioritised when acquiring properties to improve EPC ratings where possible. Report P112, P113
Risk: If the Council fails to deliver within the MOU timeframes, the funding must be returned to MHCLG. Report 10.2, P82
Staffing: Interim specialist consultant resource needed to identify and acquire six homes; cost met by the £7,744 revenue allocation. Report 10.2, P88
Who and where
Families on the Afghan Resettlement Programme (ARP) who are homeless, at risk of homelessness or in UK transitional accommodation Report P100, P104
Households owed a homelessness duty by Waverley, mainly families needing two bedroom or larger temporary accommodation Report P99
Wider local housing applicants who may access the resettlement homes after ARP needs are addressed Report 6.9, P110
Timeline
November 2025: MHCLG announces LAHF Round 4 and invites councils not initially allocated to submit an Expression of Interest Report 6.1, 6.3
19 December 2025: Council submits Expression of Interest for LAHF Round 4 funding Report 6.4
6 March 2026: MHCLG confirms allocation of £1,519,600 capital and £7,744 revenue to Waverley Report 1.3, 6.4
10 April 2026: Original MHCLG deadline to return the signed MOU, extended to align with Council approval Report 1.5
14 April 2026: Executive considers the scheme
21 April 2026: Full Council to consider the £3,335,600 capital programme addition Report 4.1, P23
July 2026: First tranche of LAHF grant funding released by MHCLG Report 4.2
2026 to 2030: Four year funding programme with further tranches released in line with the MOU Report 4.2
Plain English for the jargon
LAHF: Local Authority Housing Fund, a government programme run by MHCLG to expand temporary and resettlement housing
MHCLG: Ministry of Housing, Communities and Local Government
ARP: Afghan Resettlement Programme, supporting Afghan families resettled in the UK
MOU: Memorandum of Understanding, the agreement between the Council and MHCLG setting out funding and delivery terms
HRA: Housing Revenue Account, the ringfenced account for council housing income and spending
EPC: Energy Performance Certificate, a rating of a property's energy efficiency
S151 Officer: The Council's statutory chief finance officer
TA element: Temporary accommodation element of the LAHF scheme, providing homes for homeless households
What was decided, why, and what happens next
Pro reads every officer report for you and explains each decision in plain English: the money, the options, the risks, the timeline, each with the paragraph it came from.
Written by AI from the council's published papers. AI can get things wrong: the council's own wording below is the record.Report a problem
ItemEXE 72/25
Resolved
RESOLVED that: 1. The £1,527,344 of LAHF Round 4 grant funding and forward financing the acquisition of six properties under this scheme, be accepted. 2. The delivery of the scheme in the terms set out in this report and Exempt Appendix 1 – Financial Appraisal, be approved. 3. The Joint ... EXE 72/25
Word for word from the decision Waverley published for this meeting.Source: modgov.waverley.gov.uk
1.1The delivery of decent and affordable homes is one of the Council’s Corporate Priorities. This report provides detail of the funding allocation that the Council has been allocated by the Ministry of Housing, Communities and Local Government (MHCLG) via the Local Authority Housing Fund (LAHF) Round 4.
1.2The LAHF Round 4 is a £950 million government programme aimed at expanding high – quality temporary accommodation and supporting housing for Afghan resettlement families whilst reducing the reliance on costly B&B’s and hotels.
1.3On 6 March 2026 the MHCLG confirmed the allocation of further funding from the LAHF Round 4 comprising of a capital allocation of £1,519,600 and revenue allocation of £7,744.
1.4The Council have previously received a funding allocation from the (MHCLG) through the Local Authority Housing Fund (LAHF) Round 1 and Round 3.
1.5As with the previous rounds, the LAHF Round 4 requires the Council to enter a separate Memorandum of Understanding (MOU) with the MHCLG. MHCLG has requested that the MOU be signed and returned to them by 10 April 2026, but we have requested an extension to align with the proposed approval timetable for this matter which they have agreed to.
1.6The Council must also commit to providing match funding to deliver the scheme outputs. The LAHF funding allocation is on a contribution of 40% or 50% (dependent on property type) of the property acquisition cost based on the median property price within the Council area.
1.7An independent LAHF Funding Appraisal Review has been undertaken and is attached as Exempt Appendix 2 to this report. This document assesses the financial viability appraisals completed by Council officers and includes observations, best practice guidance on Housing Delivery – Local Authority Housing Fund Round 4
the delivery of the scheme and purchase price of the six homes to delivered.
Recommendations
2.1That the Executive resolves, subject to full Council approving the required budget, to:
2.1.1 Accept £1,527,344 of LAHF Round 4 grant funding and forward financing the acquisition of six properties under this scheme.
2.1.2 Approve the delivery of the scheme in the terms set out in this report and Exempt Appendix 1 – Financial Appraisal.
2.1.3 Delegate authority to the Joint Assistant Director of Housing in consultation with the Co-Portfolio Holder for Housing (Operations and Services) and the Joint Assistant Director of Finance to make the key decisions required to purchase each of the individual properties needed to meet the LAHF Round 4 funding requirements as set out in the MOU at Appendix 3.
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.