Affordable Housing Delivery - Land to the rear of 69 High Street, Godalming
ApprovedExecutive1 paper
AI summaryWaverley Executive recommends Council approve £7,532,229 from the Housing Revenue Account to build 13 new affordable homes on land behind 69 High Street, Godalming, with the Full Council vote set for 25 February 2026.
Written from the decision and the officer reportPDF Pro
OutcomeApprovedEndorse report and recommend 13 affordable homes
Money£7,532,229 from Housing Revenue AccountIncludes £3.6m borrowing, 47 year payback
What happens nextFull Council decision 25 February 2026Planning application expected June 2026
Who it affectsHouseholds on housing register13 studio, one and two bed flats in Godalming
What was decided
The Executive resolved to recommend to Full Council on 25 February 2026 the allocation of £7,532,229 from the Housing Revenue Account to deliver 13 new affordable, sustainable homes on land to the rear of 69 High Street, Godalming. Report P4, P5
Subject to Council approval, the Executive delegated authority to the Strategic Director of Planning, Economy and Place to commence the tender, enter a JCT Contract with a preferred contractor, and progress related agreements, in consultation with the Portfolio Holder for Housing Delivery. Report P6, P7, P8
Authority was delegated to senior finance and legal directors, with relevant Portfolio Holders, to accept any grant allocation from the Homes England Social and Affordable Homes Programme 2026-2032, provided there is no negative net revenue impact on the scheme business plan. Report P6, P8
Why
The scheme supports the Corporate Strategy 2024-2028 priority to deliver decent and affordable homes that meet local housing need, and the Build More, Build Better, Build for Life Affordable Homes Delivery Strategy 2025-2028. Report 3.1, 3.2, 7.1, 7.2
It contributes to the town centre regeneration goal by adding residential footfall alongside commercial uses, with a nearby approved scheme at 61-65 High Street cited as a precedent. Report 1.1, 3.3
The 13 unit flatted scheme was chosen over alternatives because a 10 unit scheme was financially unviable, and selling the land would likely deliver no affordable housing and risk a capital loss. Report 11.2, 11.3, 11.4, P69
What happens next
Full Council will consider the funding recommendation on 25 February 2026; if approved, officers will submit a planning application in June 2026 and start a two-stage design and build tender. Report P18
Officers will bid for Homes England Social and Affordable Homes Programme 2026-2032 grant; if unsuccessful, Housing Revenue Account reserves will be used. Report P72
Public consultation will be carried out as part of the planning application submission process in early 2026, and Overview and Scrutiny feedback will follow as a supplementary paper after its 9 January 2026 meeting. Report 9.1, 14.1
The money
£7,532,229 Allocation from the Housing Revenue Account to deliver 13 affordable homes Report P5
£3.6m Borrowing within the scheme funding, assessed against Treasury Management limits Report P72
around 15% Contingencies on build and fee costs within the budget proposal Report P73
Options considered
Rejected: Option 1: Do nothing, retain site post-demolition. Ongoing safety costs, future construction cost rises, and failure to deliver a viable scheme Report 11.1
Chosen: Option 2: Deliver 13 unit flatted scheme with rents at 70%. Supported in pre-application advice and delivers council affordable housing in the town centre Report 11.2, P64
Rejected: Option 3: Reduce to 10 unit scheme (8 flats and 2 houses). Financial appraisal deemed it unviable with more significant capital loss Report 11.3
Rejected: Option 4: Secure planning consent for 13 units then sell the land. Unlikely to deliver affordable homes, risk of capital loss and unknown sales timeline Report 11.4, P68, P69
Implications
Financial: Payback period of 47 years, reducing to 44 years if Homes England grant is secured; HRA business plan, NPV and payback all assessed. Report P71, P72
Legal: The Council is responsible as a local housing authority for providing social and affordable housing; legal risks to be kept under review through the development cycle. Report P78, P79
Equalities: Equalities Impact Assessment indicates no disproportionately adverse impact; delivery of affordable housing actively promotes equality and supports women and BAME households more likely to access such homes in Waverley. Report P85
Climate: Homes designed to contribute to the Council's Net Zero-Carbon Council by 2030 aim, with air source heat pumps, enhanced insulation, PV solar panels, and a waste recycling strategy. Report 6.8, P41, P88, P89
Risk: Key risks include contractor insolvency, cost overruns against business plan, Right to Buy sale, sub-contractor payment failure, delays in enabling works, and reputational damage if the scheme does not proceed. Report 10.3, 10.4, 10.5, 10.6, 10.7, 10.8
Staffing: Housing Development Manager and Development Officer in place, supported by Employers Agent, Clerk of Works and CDM; Finance, Legal and Housing Services require no additional resource. Report P86
Other: Local Government Reorganisation implications are limited: the 13 new homes will transfer to the asset register of the new West Surrey unitary authority. Report 8.2
Who and where
Households on the Council's housing register in need of affordable rented homes Report 7.3
Town centre economy in Godalming through added residential footfall Report 1.1, P40
Future tenants of the 13 new studio, one and two bed flats on a town centre brownfield site Report 6.8, P39
Ward members and the Portfolio Holder for Housing informally consulted Report 9.2
Timeline
February 2022: Full Council approved acquisition of 69 High Street for affordable housing under the HRA and commercial use under the General Fund Report 6.2, P28
May 2022: Purchase of 69 High Street completed Report 6.3
August 2023: Business Case approved to split the project into commercial and residential phases, with residential development paused Report 6.5
September 2024 to June 2025: Design team appointed to develop the affordable housing residential scheme using the HRA pre-development budget Report 6.7
22 October 2025: Full Council considered the commercial scheme and chose to appoint the contractor and progress the residential scheme Report 3.4, P15
January 2026: Commercial build contract expected to be signed Report 6.6
9 January 2026: Overview and Scrutiny Committee considered this report Report 14.1
10 February 2026: Executive considered the affordable housing recommendation Report P18
25 February 2026: Full Council to consider the £7,532,229 funding recommendation Report P18
June 2026: Planning application for the residential scheme to be submitted Report P18
2026 to 2032: Window for the Homes England Social and Affordable Homes Programme being bid into Report P6, P8
Plain English for the jargon
Housing Revenue Account (HRA): The ringfenced account local housing authorities use for income and spending on council housing.
General Fund (GF): The main council account for non-housing services, used here to acquire the property and bring the commercial unit back into use.
JCT Contract: A standard form of construction contract issued by the Joint Contracts Tribunal, used here for the build contract with a preferred contractor.
RIBA Stage 3: The Royal Institute of British Architects' third design stage, involving developed design and coordinated information.
Net Present Value (NPV): A financial measure comparing the value of future cash flows to today's money, used in the scheme viability assessment.
Net Zero-Carbon Council: The Council's stated aim, declared through a 2019 Climate Emergency, to be carbon-neutral as an organisation by 2030.
What was decided, why, and what happens next
Pro reads every officer report for you and explains each decision in plain English: the money, the options, the risks, the timeline, each with the paragraph it came from.
Written by AI from the council's published papers. AI can get things wrong: the council's own wording below is the record.Report a problem
ItemEXE 26/25
Resolved
RESOLVED that: the following recommendations be presented to Council, to be read at the meeting of Council on the 25 February 2026: approve the allocation of £7,532,229 from the Housing Revenue Account to deliver 13 new affordable, sustainable homes to meet local housing need to be funded as set out ... EXE 26/25
Word for word from the decision Waverley published for this meeting.Source: modgov.waverley.gov.uk
1.1The purpose of this report is to brief members on the proposed new build affordable housing scheme on land to the rear of 69 High Street, Godalming, to meet the Council's priorities within its Corporate Strategy to deliver Decent and Affordable Homes that meet local housing need.
1.2The report seeks feedback from the Overview and Scrutiny Committee on the Options presented and the recommended way forward, as outlined in the business case attached at Exempt Appendix 1.
Recommendations
2.1That the Executive resolves to:
2.1.1 Endorse the content of this report and recommend to the full Council meeting on 25 February 2026 that it resolves to:
a. approve the allocation of £7,532,229 from the Housing Revenue Account to deliver 13 new affordable, sustainable homes to meet local housing need to be funded as set out in Exempt Appendix 1 of this report. b. delegate to the Executive approval of the final budget once tender returns for the construction of the contract have been received. 2.1.2 That, strictly subject to Full Council approving the allocation of the required budget, the Executive resolves to:
a. delegate to the Joint Strategic Director of Finance, and Joint Strategic Director of Democracy, Law and People, in conjunction with the Portfolio Holders for Finance, Assets and Property and Organisational Development and Governance the authority to accept grant allocation from Homes England Social and Affordable Homes Programme 2026- 2032 and enter into any related legal agreement (provided there is not a negative net revenue impact to the business plan for the scheme.) b. delegate authority to the Strategic Director of Planning, Economy and Place to: i. approve the commencement of a tender process for the construction contracts ii. approve the entering into any pre-contract services agreement and JCT Contract with a preferred contractor, in consultation with the Portfolio Holder for Housing (Delivery)
2 Affordable Housing Delivery – Land to the rear of 69 High Street, Godalming
iii. and any related contractual documentation iv. approve entering into any agreements with any utility or related provider to ensure the connection, moving and management of any services, to facilitate or deliver the project provided they are within the approved budget. v. approve acceptance of and entering into an agreement with Homes England should grant funding be secured from the Social and Affordable Homes Programme (provided there is not a negative impact to the business plan for the scheme.)
3. Reason(s) for recommendation
3.1The Waverley Corporate Strategy 2024-2028 sets out the Vision and Strategic Priorities for the Council. One of the strategic priorities is to ‘deliver more high-quality social homes that meet the Decent Homes Standard for those that need them’.
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.