Overview and Scrutiny Committee - Services, Wednesday 24 November 2021 at 7.00pm

CRANLEIGH LEISURE CENTRE NEW BUILD

Decided Scrutiny 1 paper

Overview and Scrutiny Committee - Services decided this item on Wednesday 24 November 2021. Below is the council's own wording, with the papers it was decided on.

Item15

Resolved

RESOLVED to endorse the Executive’s proposed recommendations to Council, but Members had a number of detailed questions and asked that the Portfolio Holder and officers arrange one or more informal briefings for all councillors ahead of the Council meeting on 14 December, to allow time for the proposals to be considered in detail, and clarification provided where required, before councillors made a decision at Council.
Word for word from the decision Waverley published for this meeting. Source: modgov.waverley.gov.uk

Follow this further

Built from Waverley's papers

What the report saysPro

Report to Overview and Scrutiny Committee - Services

Recommendations

It is recommended that the Executive considers the findings of this report and recommends to Council:

2.1that a capital budget of £19.95m be allocated to deliver a low carbon new-build Cranleigh Leisure Centre, to a minimum of Passivhaus standard;

2.2that officers appoint a project manager and specialist energy consultant as part of the professional technical services team, to be supported by an in-house client team and to approve an associated budget of £250,000;

2.3to approve a new-build leisure centre on Village Way car park, subject to planning, (Option 1, to the north of the existing centre) as the preferred location, as set out within Annexe 1 of the report; and

2.4to ask officers to report back to members when final costs, design, preferred contractor, and precise funding arrangements are known.

Reason for the recommendations

Project background

3.1Following Council commitment to a multi-million-pound investment in leisure facilities in Cranleigh, the Sport, Leisure and Culture Consultancy (‘SLC’) were appointed to conduct an Options Appraisal to explore the alternative site options for development of a new leisure facility for Cranleigh.

3.2In March 2020 the Council put all corporate projects on hold due to the Covid-19 pandemic.

3.3In September 2021 a Feasibility Update Report was undertaken by SLC to test the conclusions from the earlier, pre-pandemic Options Appraisal. The report can be found in Exempt Annexe 1.

Leisure centre background

3.4Cranleigh Leisure Centre was built in 1969 with an expected lifespan of 40 years. The Centre was refurbished in 2009 at a total cost of £1.67m. The works did not include any structural work or the replacement of any mechanical and electrical plant or any structural work to the pool tanks.

3.5Cranleigh Leisure Centre is one of five leisure centres within the Waverley contract and runs at an annual deficit with a payment of c£150,000 p.a. paid to the contractor to operate the centre.

3.6Due to the age of the leisure centre (52 years) major maintenance and repair costs, on the mechanical plant and structure, are now unavoidable. There have been several unforeseen closures due to the failure of plant and roofing. A high risk of further issues and plant failure is likely to impose partial facility closure. The longer the delay before further investment is made, the greater the investment required to simply maintain and keep the centre open.

3.7Independent building surveys have concluded that to sustain the current building and facilities as they are (with no improvements) will cost the Council c£6m over the next 5 years. It is important to note that this maintenance work will offer no return on investment and further significant investment would be required to retain provision.

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
CRANLEIGH LEISURE CENTRE NEW BUILDReport 681 KB DownloadRead as text

At this meeting

Whole meeting

Who was there

9 of 15 attended
KD
Councillor Kevin DeanusChair, present
PM
Councillor Peter MarriottVice Chair, present
CC
Councillor Carole CockburnCommittee Member, present
CB
Councillor Christine BakerCommittee Member, apologies
MD
Councillor Martin D'ArcyCommittee Member, present
SD
Councillor Sally DicksonCommittee Member, apologies
JE
Councillor Jenny ElseCommittee Member, present
MF
Councillor Mary ForyszewskiCommittee Member, present
RR
Councillor Ruth ReedCommittee Member, present
PT
Councillor Philip TownsendCommittee Member, present
MW
Councillor Michaela WicksCommittee Member, apologies
JH
Councillor Joan HeaginSubstitute, present as substitute

All 15 on the meeting page

On this subject at Waverley

Search all
  1. CRANLEIGH LEISURE CENTRE NEW BUILDThis decision
  2. Cranleigh Leisure CentreApproved
  3. Cranleigh Leisure CentreApproved
  4. Cranleigh Leisure Centre New BuildApproved
  5. Wa/2024/02091 - waverley borough council cranleigh leisure centre village way cranleigh gu6 8afDecided
  6. Cranleigh Leisure Centre New BuildAgreed

More from Waverley Overview and Scrutiny Committee - Services

All decisions
MeetingDecisionOutcome
15 Sep 2025 Committee Work ProgrammeRESOLVED that the be noted. Noted Open
15 Sep 2025 The Issues and Options Consultation for the new Waverley Local PlanIt was agreed that references should clarify its age and limited relevance, with consultation questions framed to gat... Agreed Open
15 Sep 2025 The Surrey Hills National Landscape Management Plan 2025 to 2030It was agreed that Part 4 (Policy Framework) was of particular importance to Waverley Borough Council as a local plan... Agreed Open
15 Sep 2025 Proposed Revised Overview & Scrutiny Committee ArrangementsIt was agreed that such an arrangement was both necessary and logical given the increasing extent of joint working. H... Agreed Open
23 Jun 2025 Committee Work ProgrammeThat the Committee Work Programme be noted. Noted Open

We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies