Cranleigh Leisure Centre New Build

Approved Executive 1 paper

AI summaryWaverley Executive recommends proceeding with the £35,999,544 Cranleigh Leisure Centre new build to Passivhaus standard, subject to full Council approving a £4,862,292 supplementary estimate on 27 January 2026.

AI summaryIn plain English

Written from the decision and the officer reportPDF Pro
OutcomeApprovedProgress new build to Passivhaus and full facility mix
Money£4,862,292 supplementary estimate£2,651,900 CIL plus £2,210,392 borrowing
What happens nextFull Council 27 January 2026Final budget approval required before build contract
Who it affectsCranleigh residents and leisure usersPlus high street, ward councillors and Everyone Active

What was decided

Subject to full Council approving the supplementary estimate, proceed with Option 1 of the new build, achieving both Passivhaus certification and the full agreed facility mix. Report 2.1

Delegate to the Joint Strategic Director of Finance and Resources the authority to enter into the build contract and other necessary contracts, within the approved budget. Report P3, P4, P5

Recommend that Council, at its 27 January 2026 meeting, approves a supplementary estimate of £4,862,292, funded from £2,651,900 CIL and £2,210,392 internal borrowing. Report P7, P8

Why

The existing Cranleigh Leisure Centre is 56 years old and at the end of its expected life, with a high risk of further closures and a predicted £7.3m needed over five years just to keep it open. Report 3.1, 6.1, 6.3

Option 1 is the most strategically aligned choice: it delivers the Council approved Passivhaus scheme, retains the agreed facility mix, and turns a £26,000 per year deficit asset into an average £450,000 per year revenue generator. Report 3.3, 11.3

The £4,862,292 cost increase reflects market conditions and design development since the October 2023 budget, and aligns with cost pressures seen on other current leisure new build projects. Report 3.5, 6.9

What happens next

Full Council to consider the £4,862,292 supplementary estimate on 27 January 2026; subject to approval, officers will progress the main works build contract with the preferred contractor. Report 4.1, 4.2, P7

Indicative programme: detailed design Feb to Spring 2026, construction start Summer 2026, new centre complete Winter 2027, old centre demolition Spring 2028. Report 6.14, P56

Officers will continue to pursue additional CIL and external funding to reduce or replace the proposed borrowing, and will run a value engineering exercise with the contractor. Report 6.11

The money

  • £35,999,544 Reviewed total project cost plan for Option 1 Report 1.1
  • £4,862,292 Supplementary estimate requested, covering cost plan increase Report P7, 3.5, 6.9
  • £2,651,900 CIL funding awarded to the project Report P7
  • £2,210,392 Internal borrowing proposed to cover the remaining shortfall Report P7
  • £31,137,252 Capital budget approved by Council in October 2023 Report P36
  • £31,137,708 Previously approved budget figure stated in financial implications
  • £2,000,000 CIL allocation from 2023/24 round, confirmed 23 April 2024
  • £651,900 Additional CIL from 2024/25 round, approved 1 April 2025
  • £358,000 Additional cost to retain at least 100 car parking spaces during construction Report 3.6, 6.9
  • £1.67m Cost of 2009 refurbishment of the existing centre Report 6.1
  • £7.3m Predicted spend over 5 years just to keep the existing centre open
  • £26,000 Current annual payment to leisure operator to run the centre at a deficit Report 11.3
  • £450,000 Average annual revenue projected under Option 1 Report 11.3
  • £596,000 Additional annual income from the new Everyone Active Leisure Operating Contract Report P34
  • £1.7m Section 106 contribution excluded from payback calculation

Options considered

  • Chosen: Option 1: Progress existing proposal with Passivhaus certification and full agreed facility mix. Most strategically aligned, delivers Council approved scheme, turns deficit into revenue, recommended in exempt options assessment Report 2.1, 11.3, P90, P91
  • Rejected: Option 2: Remove Passivhaus design certification. Loss of guaranteed energy savings, higher energy costs, programme delay, re-planning required, lower management fee return Report 11.4
  • Rejected: Option 3: Redesign centre to keep within current budget. Loss of facility provision, around 750m² floor space reduction, significant delay, new planning application, payback exceeds asset life Report 11.5
  • Rejected: Option 4: Do nothing and manage closure of the current centre. Loss of service, LOC penalty with Everyone Active, ongoing cost, loss of future income, increased carbon footprint from displaced visits Report 11.6

Implications

  • Financial: Project cost rises to £35,999,544, with payback on the Council's direct investment extending from 44 to 48 years; the total investment payback, including CIL and S106, would rise from 47 to 52 years.
  • Financial: Option 1 includes a contingency of approximately 12% of the overall budget to cover cost escalation and inflation risk.
  • Legal: Build contract procurement was run compliantly via the Procure Partnerships Framework under the Procurement Act 2023, and the additional budget above £250,000 requires full Council approval under Finance Procedure Rules. Report P109
  • Equalities: The Impact Assessment finds no disproportionately adverse impact on protected groups; Option 1 delivers inclusive design including dementia comfort, neurodivergent and Changing Places provision. Report P116, P117, P61
  • Climate: A Passivhaus leisure centre is expected to use 60-70% less energy than a standard build, with solar panels generating about 25% of demand, supporting the Council's 2030 carbon neutral target. Report 3.7, 3.8, P128
  • Risk: The £2m CIL offer has a condition that works must start within 18 months; permission has been obtained to extend the construction start date, but losing the funding would make the project unviable. Report P87
  • Staffing: A specialist Project Manager is in place with a working group covering Leisure, Finance, Legal, Sustainability, Procurement, Property, Car Parks and Corporate Projects, plus an Employers Agent and Clerk of Works for the build stages. Report P119

Who and where

  • Cranleigh Leisure Centre users and the wider Cranleigh community Report 3.1, 11.3
  • Cranleigh village centre businesses and high street Report 3.6, P60
  • Everyone Active, as operator under the Waverley Leisure Operating Contract Report P34, 11.6
  • Future successor authority, which will inherit the asset Report P67
  • Council taxpayers in Waverley Report 3.5

Timeline

  • September 2021: Feasibility Update Report commissioned Report P31
  • December 2021: Full Council allocated capital budget for a low carbon new build to Passivhaus standard Report P31
  • October 2023: Full Council approved revised capital budget of £31,137,252 and Passivhaus certification Report P36
  • 23 April 2024: Council confirmed £2,000,000 CIL allocation from 2023/24 round Report P99
  • October 2024: Planning application WA/2024/02091 submitted Report P39
  • 1 April 2025: Additional £651,900 CIL allocation from 2024/25 round approved Report P99
  • August 2025: Local Planning Authority granted planning permission Report P42
  • 16 December 2025: Update report considered by Overview and Scrutiny Committee, which requested additional information Report 13.1, 13.2, P137
  • 13 January 2026: Executive resolved to recommend Option 1 and supplementary estimate Report 2.1, P3
  • 27 January 2026: Full Council to decide on the £4,862,292 supplementary estimate Report 2.3, P7, 4.1, P56
  • Feb - Spring 2026: Completion of detailed design Report 6.14, P56
  • Summer 2026: Construction start on site Report 6.14, P56
  • Winter 2027: New leisure centre construction completion Report 6.14, P56
  • Spring 2028: Demolition of old centre Report 6.14, P56

Plain English for the jargon

  • CIL: Community Infrastructure Levy, a charge developers pay to fund local infrastructure
  • Passivhaus: A building standard for very low energy use, with independently certified airtightness and fabric performance
  • LOC: Leisure Operating Contract, the contract under which Everyone Active runs Waverley's leisure centres
  • D&B: Design and Build, a procurement route where one contractor designs and constructs the building
  • PCSA: Pre-Construction Services Agreement, a contract for early contractor design and pricing work
  • FF&E: Furniture, Fittings and Equipment
  • RIBA stages: Royal Institute of British Architects work stages, from concept design through to construction
  • S106: Section 106 planning obligation contributions from developers
  • tCO2e: Tonnes of carbon dioxide equivalent, a standard measure of greenhouse gas emissions
What was decided, why, and what happens next

Pro reads every officer report for you and explains each decision in plain English: the money, the options, the risks, the timeline, each with the paragraph it came from.

Written by AI from the council's published papers. AI can get things wrong: the council's own wording below is the record.Report a problem
ItemEXE 13/25

Resolved

That the Executive resolved to: · Subject to full Council approving the supplementary estimate (as revised under recommendation 2.2.1 below), proceed with Option 1 of the Cranleigh Leisure Centre new build project, which is to progress the existing proposal as per the planning application, achieving both Passivhaus certification and full agreed ... EXE 13/25
Word for word from the decision Waverley published for this meeting. Source: modgov.waverley.gov.uk

Follow this further

Built from Waverley's papers

What the report saysPro

Report to Executive

Executive summary

1.1This report provides an updated project position with reviewed cost plan of £35,999,544 for the Cranleigh Leisure Centre new build project. 1.2. It duly considers the options, as detailed at point 11, and makes recommendations to proceed with the existing approved proposal for the construction of the new centre. The recommended option delivers the Council approved scheme of a Passivhaus certified centre offering the agreed facility mix. It also turns a deficit asset into a positive revenue generator. 1.3. The project team has been awarded £2,651,900 of CIL funding to be used toward the leisure centre build, and wider infrastructure including increased car parking and electric vehicle charging. Whilst the allocation of strategic CIL has been approved, the addition of this funding to the project budget has not. This report seeks approval for the budget, using the allocated funding. 1.4. To cover the remainder of the £2,210,392 budget required, the proposal is to fund this from borrowing. 1.5. The team will continue to actively explore further additional CIL funding and other external funding sources. If successful, this would replace this additional borrowing. However, the timelines unfortunately do not align, and we need to progress to adhere to the programme and minimise the amount that costs could rise further.

Recommendations

2.1That the Executive resolves to: 2.1.1. Subject to full Council approving the supplementary estimate (as revised under recommendation 2.2.1 below), proceed with Option 1 of the Cranleigh Leisure Centre new build project, which is to progress the existing proposal as per the planning application, achieving both Passivhaus certification and full agreed facility mix.

2.1.2. Delegate to the Joint Strategic Director of Finance and Resources the authority to enter into the build contract, together with all other contracts and legal agreements connected with the Cranleigh Leisure Centre new build project as may be necessary, in compliance with Procurement Procedure Rules, the Council’s Constitution and within the

2 Cranleigh Leisure Centre new build

approved budget (as revised under recommendation 2.2.1 below).

2.32.2 That the Executive recommends that Council, at the meeting on 27 January 2026, resolves to:

2.2.1 Approve allocation of budget by way of a supplementary estimate totalling £4,862,292 to fund progression of Option 1 of the Cranleigh Leisure Centre new build project in accordance with the revised business case set out in Exempt Appendix 2 of this report, to be funded from;  £2,651,900 CIL funding allocation  £2,210,392 internal borrowing.

3. Reason(s) for recommendation:

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
Cranleigh Leisure Centre New BuildReport 408 KB DownloadRead as text

At this meeting

Whole meeting

Who was there

9 of 9 attended
PF
Councillor Paul FollowsChair, present
TF
Councillor Tony FaircloughVice Chair, present
JC
Councillor Janet CroweCommittee Member, present
VK
Councillor Victoria KiehlCommittee Member, present
GL
Councillor Gemma LongCommittee Member, present
MM
Councillor Mark MerryweatherCommittee Member, present
KM
Councillor Kika MiryleesCommittee Member, present
PR
Councillor Paul RiversCommittee Member, present
LT
Councillor Liz Townsend BEMCommittee Member, present

On this subject at Waverley

Search all
  1. Cranleigh Leisure Centre New BuildThis decision
  2. Cranleigh Leisure CentreApproved
  3. Cranleigh Leisure CentreApproved
  4. Wa/2024/02091 - waverley borough council cranleigh leisure centre village way cranleigh gu6 8afDecided
  5. Cranleigh Leisure Centre New BuildAgreed
  6. Cranleigh Leisure Centre - new build tenderApproved

More from Waverley Executive

All decisions
MeetingDecisionOutcome
1 Sep 2026 Lease Renewal on Unit 3, Enterprise Centre, Farnhamthat 1) Delegated authority be given to the Director of Assets and Property for the granting of the lease of Unit 3, ... Agreed Open
1 Sep 2026 New Contract for Communal Block Cleaning Servicesthat 1) Delegated authority be given to the Director of Housing Service to enter into the Block Cleaning Services con... Decided Open
1 Sep 2026 Acquisition of Land off Hale Road, Adjacent to Farnham Park, Farnhamthat 1) The Executive request consent from West Surrey Shadow Authority to enter into a Conditional Purchase Agreemen... Agreed Open
1 Sep 2026 Waverley Fire Loss - Underinsurance at 13 & 14 Springwood, Station Lane, MilfordRECOMMENDED that Council RESOLVE to: 1) Approve a supplementary estimate increase of £106,269.98 for FY26/27 to be fu... Approved Open
1 Sep 2026 Recycling and Waste Collection and Street Cleansing Services Contracts Arrangements from 1 November 2027that 1) An 8-year extension to the current Waste Collection and Street Cleansing Contract with an option of a contrac... Approved Open

We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies