AI summaryWaverley Executive backs £36m Cranleigh Leisure Centre rebuild with Passivhaus standard, subject to full Council approving £4.86m extra on 25 February 2026.
Written from the decision and the officer reportPDF Pro
OutcomeApprovedProceed with Passivhaus new build and full facility mix
Money£35,999,544 total project costExtra £4,862,292 sought from CIL and borrowing
What happens nextFull Council vote 25 February 2026Then sign build contract with preferred contractor
Who it affectsCranleigh residents and visitorsLeisure centre users, parish and ward councillors
What was decided
The Executive agreed to recommend Option 1, progressing the new Cranleigh Leisure Centre to Passivhaus certification with the agreed facility mix, subject to full Council approving a £4,862,292 supplementary estimate on 25 February 2026. Report P3, P7
Delegated authority was given to the Joint Strategic Director of Finance and Resources to enter the build contract and related agreements within the approved budget and procurement rules. Report P5
The recommendation to Council is to fund the extra £4,862,292 from £2,651,900 of Community Infrastructure Levy (CIL) and £2,210,392 of internal borrowing. Report P7
Why
The existing centre, built in 1969, is judged at the end of its useful life and at high risk of failure, with surveys estimating £7.3m of maintenance over five years to keep it open with no improvement. Report 3.1, 6.3, 6.4
The current centre is the only one of four in the contract that runs at a deficit, costing £26,000 per year, while the new Passivhaus centre is forecast to generate average net revenue of £450,000 per year. Report 6.2, 11.3
The cost plan has risen from £31,137,252 (approved in October 2023) to £35,999,544 because of five extra quarters of inflation, market-rate increases for Passivhaus elements, design development, and a £358,000 provision to keep 100 car parking spaces during construction. Report 3.5, 6.9, 6.10, P55, P57
What happens next
The report goes to full Council on 25 February 2026 for approval of the supplementary estimate. Report 4.1, P66
If approved, officers will sign the main works build contract with the preferred contractor, with detailed design completing in Spring 2026, construction starting in Summer 2026, new centre completion in Winter 2027, and old centre demolition in Spring 2028. Report 4.2, 6.15, P66
Officers will continue to seek further CIL and external funding, which could replace the proposed borrowing and shorten the payback period.
£31,137,252 Original capital budget approved by full Council in October 2023 Report P41
£4,862,292 Supplementary estimate requested, funded from £2,651,900 CIL and £2,210,392 borrowing Report P7
£2,651,900 CIL funding allocation for the leisure centre build and wider infrastructure Report P7
£2,210,392 Internal borrowing proposed to cover the remaining shortfall Report P7
£1,722,000 Previous S106 funding assumption now reduced to £286,960
£286,960 Revised S106 funding after internal review of S106 agreements
£7.3m Predicted cost over 5 years to keep the existing building open, with no improvement Report 6.4
£26,000 p.a. Current deficit subsidy paid to the operator to run the existing centre Report 6.2
£450,000 p.a. Forecast average net revenue from the new Passivhaus centre Report 11.3
£596,000 Additional annual income secured by the new Everyone Active Leisure Operating Contract Report P38
£358,000 Extra cost to retain at least 100 car parking spaces during construction, extending programme by 9 weeks Report 3.6, P57
Options considered
Chosen: Option 1: Progress the existing proposal with Passivhaus certification and the full agreed facility mix. Delivers the Council-approved scheme, retains Passivhaus energy and carbon performance, and turns a deficit asset into a revenue generator of about £450,000 a year Report 11.3, 3.3, P3
Rejected: Option 2: Remove the Passivhaus design certification standard. Loses guaranteed energy savings, raises energy costs, requires redesign and planning resubmission, and lengthens payback beyond the asset's 55-year life Report 11.4
Rejected: Option 3: Redesign the centre to stay within the current budget. Loses facility provision, requires a new planning application, and pushes the subsidised payback to about 60 years Report 11.5
Rejected: Option 4: Do nothing, cease the new build and manage closure of the current site. Loses the service for the local community, triggers a financial penalty under the Leisure Operating Contract, and forfeits the forecast revenue to the general fund Report 11.6
Implications
Financial: Council is asked to approve a £4,862,292 supplementary estimate, with £2,210,392 of additional borrowing within the Treasury Management limits. Report P7
Financial: The new centre is forecast to pay back the Council's direct investment over 50 years, or 52 years including CIL and S106 funds, up from 44 and 50 years at the October 2023 approval.
Financial: Reliance on historical S106 projected payments has been removed after an internal audit identified a funding risk, cutting S106 from £1,722,000 to £286,960, with the gap met from borrowing.
Legal: The contract value falls under the threshold in Schedule 1 of the Procurement Act 2023; procurement was run via the Procure Partnerships Framework in 2025 and external legal advisers are instructed on the build contracts. Report P131
Equalities: Officers conclude there are no direct equality and diversity implications from the recommendation, but a different option would have a disproportionately adverse impact on people with protected characteristics. Report P138
Climate: The Passivhaus design is expected to cut energy use by 60 to 70 percent and energy costs by 89 percent; the existing Cranleigh Leisure Centre accounts for 8.5 percent (263 tCO2e) of the council's organisational emissions. Report P156
Risk: Officers flag a risk that if the project does not start in time the £2m CIL offer could be lost, though an extension to the construction start date has already been obtained. Report P103
Risk: Parking disruption during construction is mitigated by a contractor commitment to keep at least 100 spaces on the Village Way site throughout the build. Report 3.6, P106
Who and where
Cranleigh Leisure Centre users and residents of Cranleigh and surrounding villages Report 9.2, P81, P82
Nearby businesses, the Market, Co-op, Cranleigh Medical Centre and Cranleigh League of Friends, consulted as neighbouring organisations Report P81
Cranleigh Amateur Swimming Club and Surrey Coalition of Disabled People, consulted on facility design and accessibility Report 9.10
Cranleigh Parish Council and the Ward Councillors, kept informed through project milestones Report P81, 9.9
Everyone Active, the leisure operator under the Waverley Leisure Operating Contract Report P38, 11.6
Council taxpayers and the future successor authority, who will hold the rebuilt asset Report 8.2, 11.3
Timeline
September 2021: Sport, Leisure and Culture Consultancy appointed to update the feasibility report Report P37
December 2021: Full Council allocated capital budget for a low-carbon new-build centre to Passivhaus standard on Village Way car park Report P37
1 July 2023: New Leisure Operating Contract with Everyone Active began, securing £596,000 additional annual income Report P38
October 2023: Full Council approved the £31,137,252 budget and Passivhaus standard for the new build Report P41
October 2024: Planning application WA/2024/02091 submitted Report P45
November 2024 to March 2025: Procurement via Procure Partnerships Framework completed; Willmott Dixon identified as preferred bidder Report P46
August 2025: Planning permission granted for the new build leisure centre Report P48
September and October 2025: Cost plan review and business case viability assessment undertaken Report P49
16 December 2025: Overview and Scrutiny Committee considered the update report and requested additional information Report 13.1
10 February 2026: Executive agreed to recommend Option 1 and the supplementary estimate to full Council Report 4.1
25 February 2026: Full Council asked to approve the £4,862,292 supplementary estimate Report 4.1, P66
Spring 2026: Completion of detailed design Report P66
Summer 2026: Indicative construction start on site Report P66
Winter 2027: Indicative completion of new centre construction Report P66
Spring 2028: Indicative demolition of the old leisure centre Report P66
Plain English for the jargon
CIL: Community Infrastructure Levy, a charge on new development that local councils can use to fund infrastructure
Passivhaus: A rigorous German energy efficiency standard for buildings that delivers very low energy use and guaranteed airtightness
Section 106 (S106): A legal agreement under section 106 of the Town and Country Planning Act used to secure developer contributions toward local infrastructure
Supplementary estimate: Additional budget approval sought from full Council because the original budget is no longer enough
Leisure Operating Contract (LOC): The contract under which Everyone Active operates Waverley's four leisure centres, awarded in 2023
What was decided, why, and what happens next
Pro reads every officer report for you and explains each decision in plain English: the money, the options, the risks, the timeline, each with the paragraph it came from.
Written by AI from the council's published papers. AI can get things wrong: the council's own wording below is the record.Report a problem
ItemEXE 36/25
Resolved
RESOLVED that: Subject to full Council approving the supplementary estimate (as revised under recommendation below), proceed with Option 1 of the Cranleigh Leisure Centre new build project, which is to progress the existing proposal as per the planning application, achieving both Passivhaus certification and full agreed facility mix. Delegated authority ... EXE 36/25
Word for word from the decision Waverley published for this meeting.Source: modgov.waverley.gov.uk
1.1This report provides an updated project position with reviewed cost plan of £35,999,544 for the Cranleigh Leisure Centre new build project. 1.2. It duly considers the options, as detailed at point 11, and makes recommendations to proceed with the existing approved proposal for the construction of the new centre. The recommended option delivers the Council approved scheme of a Passivhaus certified centre offering the agreed facility mix. It also turns a deficit asset into a positive revenue generator. 1.3. The team has been awarded £2,651,900 of CIL funding to be used toward the leisure centre build, and wider infrastructure works including increased car parking and electric vehicle charging. Whilst the allocation of strategic CIL has been approved, the addition of this funding to the project budget has not. This report seeks approval for the budget, using the allocated funding. 1.4. To cover the remainder of the £2,210,392 budget required, the proposal is to fund this from borrowing. 1.5. Officers will continue to actively explore further additional CIL funding and other external funding sources. If successful, this would replace this additional borrowing. However, the timelines unfortunately do not align, and we need to progress to adhere to the programme and minimise the amount that costs could rise further. 1.6. Since the original approval in October 2023, there has been a change to the Section 106 funding, as set out in the Financial Implications section (12.1.5). There is no change to the overall budget requested and therefore no requirement to seek additional budget approval. However, the change in funding source impacts the payback period of the scheme, and this has been reflected in Appendix 2.
Recommendations
2.1That the Executive resolves to:
2.1.1. Subject to full Council approving the supplementary estimate (as revised under recommendation 2.2.1 below), proceed with Option 1 of the Cranleigh Leisure Centre new build project, which is to progress the existing proposal as per the planning application, achieving both Passivhaus certification and full agreed facility mix.
2 Cranleigh Leisure Centre new build
2.1.2. Delegate to the Joint Strategic Director of Finance and Resources the authority to enter into the build contract, together with all other contracts and legal agreements connected with the Cranleigh Leisure Centre new build project as may be necessary, in compliance with Procurement Procedure Rules, the Council’s Constitution and within the approved budget (as revised under recommendation 2.2.1 below).
2.2That the Executive recommends that Council, at the meeting on 25 February 2026, resolves to:
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.