Resolved
Decision meeting.
Landlord Services Advisory Board (Executive Working Group) decided this item on Thursday 26 January 2023. Below is the council's own wording, with the papers it was decided on.
Resolved
Decision meeting.
It is recommended that the Board advise and make comments to the Co-Portfolio Holder for Housing on the following proposals:
It is recommended that the Co-Portfolio Holder for Housing: endorses the signing of Asbestos removal contract with Envirocall LTD, maximum contract duration 2022 to 2028 secures £1.2m capital funding in the Housing Revenue Account to finance the six year term. endorses the signing of Asbestos Surveying and Analysis contract with Environtec LTD; maximum contract duration 2022 to 2028, and secures £1.2m Revenue funding in the Housing Revenue Account to finance the six year term.
Please be advised that these contracts initiated August 2022 are operating under a authorised letter of intent. Contracts have already been signed by contractors and require countersigning by Waverley. Due to the change in procurement procedure this is being raised now for retrospective approval by the Co-Portfolio Holder for Housing.
Waverley Borough Council has a statutory requirement to identify, manage and remove asbestos containing materials within council owned properties. This is to protect residents and contractors working in these properties from harmfull exposure to asbestos, as outlined in the Control of Asbestos Regulations 2012. These contracts are required inorder to facilitate the fulfilment of these obligations
The previous contracts in place to carry out these services facilitated by Gully Howard Technical and Merryhill Envirotec ended August 2022.
The services provided under these contracts affect multiple stake holders who rely on them to carry out workstreams in a safe and informed manner. Responsive Repairs Voids Planned works Environmental Services.
In advance of the procurement, Ridge consultancy was commissioned to create the tender documents and evaluate the tender responses. The tender reports for both contracts are set out in Annexe One and Two.
Tender periods were live between 2 February and 4 March 2022. Six responces were submitted for the Asbestos removal tender. Five responces were submitted for the Asbestos Survey and Analysis tender.
Procurement was conducted with the support of the Council’s procurement offier and followed secition 20 leaseholder engagement requirments.
Contracts are JCT minor works and were complied by Ridge consultancey. They were issued to each contractor in October 2022 for signing, contracts were returned to Waverley December 2022 for counter signing.
5. Relationship to the Corporate Strategy and Service Plan
The report supports the Council’s Corporate commitment to promote “Good quality housing for all income levels and age groups” and aim to “be the best council landlord in the South East and to be acknowledged so by our tenants.” These contracts also support the Housing Asset Management , Strategic Objective to ensure our properties are safe, secure and compliant, meeting all our landlord obligations.
6. Implications of decision
If we are unable to enter contracts formally, we would subsequently be putting at risk our ability to meet our statutory requirements. We would also have a lack of ability to endorse the terms of the contract should the contractors fail to deliver the respective services as required.
6.1Resource (Finance, procurement, staffing, IT) Drafted by: Candice Keet, Senior Accountant
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
PDF |
Asbestos Survey and Works ContractsReport | 299 KB | DownloadRead as text |
Follow Landlord Services Advisory Board (Executive Working Group) at Waverley and we tell you when its next papers are published, before the meeting rather than after it.
| Meeting | Decision | Outcome | |
|---|---|---|---|
| 30 Jul 2026 | Capital Programme updateRESOLVED that the Capital Programme update be noted. | Noted | Open |
| 30 Jul 2026 | Council Response to Tenant Panel Proposal on Repairs, Maintenance and Service AppointmentsRESOLVED that: · the tenant panel proposal be noted, · the principles of a standardized appointments and communicatio... | Noted | Open |
| 30 Jul 2026 | Low Carbon Heating SolutionsRESOLVED that the Low Carbon Heating Solutions report be noted. | Noted | Open |
| 30 Jul 2026 | Water Hygiene ReportRESOLVED that the monthly Water Hygiene Report be noted. | Noted | Open |
| 30 Jul 2026 | Landlord Services Improvement Plan Update [2025-26]RESOLVED that the Landlord Services Improvement Plan update was noted. | Noted | Open |
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Keeps you signed in and runs your free-paper allowance. Always on.
Counts visits and which pages are used. First-party only, no advertising, never shared.