The Executive RESOLVED, 1. To recommend to Full Council that an additional budget allocation of £784,000 be agreed for Phase 4 of the Ockford Ridge Regeneration Project, bringing the total allocated budget to £1.765m, to enable the deep retrofit of seven homes, piloting the use of green renewable energy sources ... EXE 96/22
Word for word from the decision Waverley published for this meeting.Source: modgov.waverley.gov.uk
3.1The Council has already committed to the delivery of the regeneration of the Ockford Ridge estate which includes both regeneration and refurbishment of homes. To date, three phases of refurbishment have been completed and a budget of £981,000 was approved at full Council in February 2022 to deliver this next phase.
The project will deliver modern, safe, and secure, sustainable homes and support delivery of the Council’s Corporate Strategy 2020 – 2025, Climate Change and Sustainability Strategy 2020 - 2030, Carbon Neutrality Action Plan 2020 - 2030 and Housing Asset Management Strategy 2022-2030 commitments and targets.
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.