The Executive RESOLVED that, 1. the allocation of Strategic CIL funding to the projects as set out in the agenda report (paragraph 4.24) be approved, subject to the completion of the final relevant checks and signing of funding agreements, the details of which are delegated to the Strategic Director in ... EXE 99/22
Word for word from the decision Waverley published for this meeting.Source: modgov.waverley.gov.uk
1) It is recommended that the Executive agree the recommendations of the CIL Advisory Board and approve the allocation of Strategic CIL funding to the projects as set out in this report. This is subject to the completion of the final relevant checks and the signing of funding agreements, the details of which are delegated to the Strategic Director in consultation with the Portfolio Holder for Housing (Delivery).
2) It is recommended that the Executive agree the recommendation of the CIL Advisory Board to remove the ‘Community CIL’ from future Strategic CIL Bidding Cycles, for the reasons as set out within this report.
Reason for the recommendation
In order to ensure robust and effective expenditure, in line with the CIL Regulations 2010 (as amended), and in accordance with the Council’s approved CIL governance arrangements which include detailed eligibility and assessment criteria. 4. Background
4.1In accordance with the CIL Regulations 2010 (as amended), Strategic CIL must be spent on “the provision, improvement, replacement, operation or maintenance of infrastructure to support the development of its area”
4.2‘Infrastructure’ is defined within the Planning Act 2008. It includes: roads and other transport facilities, flood defences, schools and other educational facilities, medical facilities, sporting and recreational facilities, and open spaces.
4.3CIL should not be used to remedy pre-existing deficiencies in infrastructure provision, unless those deficiencies will be made more severe by new development.
4.4The Council has approved the CIL governance arrangements to allow for an annual bidding cycle for the allocation of Strategic CIL receipts to enable the delivery of specific infrastructure projects that will support development in the Borough. This approval also included the use of a scoring criteria for evaluating bids for infrastructure from the Strategic CIL Fund. These governance arrangements were considered by Overview and Scrutiny prior to approval. Under delegated powers, the CIL Advisory Board made minor amendments to the Scoring Criteria, to reflect updated circumstances, and this was used for the 2022/23 CIL Bidding Cycle.
4.5Infrastructure providers were invited to submit bids to the 2022/23 Strategic CIL Bidding Cycle between the 1st of July 2022 and the 14th of October 2022.
4.6In accordance with the agreed CIL governance arrangements, the Executive is delegated to approve bids for the allocation of Strategic CIL Funding, on the recommendation of the CIL Advisory Board, subject to an upper limit of £2.5m per individual award, above which approval reverts to Full Council.
Available Strategic CIL
4.7As of 1st January 2023, the amount of Strategic CIL available was £4,455,275.14.
4.8In accordance with the CIL Regulations 2010 (as amended), the Council agreed that it will only award Strategic CIL up to the value of actual amounts received. CIL receipts whereby a Demand Notice has been raised but the amount is yet to be received will be subject to allocation at future bidding rounds.
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.