Waverley Borough Council
Executive, Tuesday 1 August 2023 at 6.00pm

New Build Housing Delivery - Chiddingfold

Approved Executive 1 paper

Executive approved this item on Tuesday 1 August 2023. Below is the council's own wording, with the papers it was decided on.

ItemEXE 33/23

Resolved

The Executive RESOLVED to: i. enter into a contract with the preferred contractor Feltham Construction Limited for the delivery of the works. ii. give delegated authority to the Executive Head of Legal and Democratic Services to approve the final form of any legal agreements and to Strategic Director (Place) to ... EXE 33/23
Word for word from the decision Waverley published for this meeting. Source: modgov.waverley.gov.uk

Follow this further

Built from Waverley's papers

What the report saysPro

Report to Executive

Executive summary

1.1The purpose of this report is to seek formal approval to enter into a contract for the demolition of existing and delivery of 26 new homes across five sites in Chiddingfold.

1.2Members have already considered and approved the business cases for and delivery of these homes and full project budget at a meeting of Full Council on 13 December 2022. However, progression of construction design, the provision of information from the utility companies and other work to de-risk the project, additional budget is required to ensure that the contingency is in place when we enter into contract. The scheme remains financially viable. 2. Recommendation to Executive

It is recommended that the Executive approves:

i. Entering into a contract with the preferred contractor Feltham Construction Limited for the delivery of the works.

ii. Giving delegated authority to the Executive Head of Legal and Democratic Services to approve the final form of any legal agreements and to Strategic Director (Place) to enter into the JCT Contract.

iii. Giving delegated authority to the Strategic Director (Place) to approve pre contract agreements with the preferred contractor to enable the development of the project and authorise spend in accordance with the budget.

iv. Giving delegated authority to the Strategic Director (Place) to enter into any related contractual documentation (including collateral warranties or agreements) relating to the project.

v. Giving delegated authority to the Strategic Director (Place) to enter into any ancillary agreements related to the project provided that these are within the project budget.

vi. The sale of five shared ownership homes to be delivered on the Chiddingfold sites with the Executive Head of Housing Services in consultation with Portfolio Holders for Housing (Delivery and Operations) to approve the final terms of such sales having regard to market value and giving the Executive Head of Legal and Democratic Services authority to approve the final form of the sale agreements and any ancillary related legal agreements.

vii. Giving delegated authority for Executive Head of Housing Services in consultation with Portfolio Holders for Housing (Delivery and Operations) to approve the future sale of percentage shares.

It is recommended that Executive recommends to Council that: i. An allocation of an additional £402,332 budget from reserves is approved.

Reason for recommendations

3.1The Executive and Full Council have previously approved the Business Cases for each of the five sites and the recommended authority is required to enter into the contract with a build contractor and approve additional budget to facilitate delivery of the new homes on these sites through one JCT Design and Build Contract. Through delivery of the project there may be a requirement to enter into project related contractual documents or ancillary agreements.

3.2The Waverley Corporate Strategy 2020-2025 sets out the Vision and Strategic Priorities for the Council. One of the strategic priorities is to ‘provide good quality housing for all income levels.’

3.3Build More, Build Better, Build for Life Affordable Homes Delivery Strategy 2022 – 2025 sets out the Council’s commitment to build homes to buy or rent for households from all income levels. The strategy has been supported by evidence studies including the Waverley Housing Affordability Study 2021.

3.4Delivery of 26 homes at Chiddingfold including five shared ownership homes meets these priorities and commitments.

4. Exemption from publication

4.1Part Exempt – Open Report / Exempt Annexe

Note pursuant to Section 100B(5) of the Local Government Act 1972

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
New Build Housing Delivery: ChiddingfoldReport 489 KB DownloadRead as text

At this meeting

Whole meeting

Who was there

9 of 13 attended
PF
Councillor Paul FollowsChair, apologies
PC
Councillor Peter ClarkVice Chair, in the Chair, present
TF
Councillor Tony FaircloughCommittee Member, present
VK
Councillor Victoria KiehlCommittee Member, present
MM
Councillor Mark MerryweatherCommittee Member, present
KM
Councillor Kika MiryleesCommittee Member, present
NP
Councillor Nick PalmerCommittee Member, present
PR
Councillor Paul RiversCommittee Member, present
LT
Councillor Liz Townsend BEMCommittee Member, present
SW
Councillor Steve WilliamsCommittee Member, present
MH
Councillor Michael HigginsCommittee Member, in attendance
AM
Councillor Andy MacLeodCommittee Member, in attendance, virtual

All 13 on the meeting page

On this subject at Waverley

Search all
  1. New Build Housing Delivery - ChiddingfoldThis decision
  2. Cranleigh Leisure Centre New BuildApproved
  3. New Build Housing Delivery - WitleyApproved
  4. Housing Revenue Account - New Build Housing DeliveryDecided
  5. New Build Housing Delivery - WitleyApproved
  6. Cranleigh Leisure Centre New BuildAgreed

More from Waverley Executive

All decisions
MeetingDecisionOutcome
1 Sep 2026 Lease Renewal on Unit 3, Enterprise Centre, Farnhamthat 1) Delegated authority be given to the Director of Assets and Property for the granting of the lease of Unit 3, ... Agreed Open
1 Sep 2026 New Contract for Communal Block Cleaning Servicesthat 1) Delegated authority be given to the Director of Housing Service to enter into the Block Cleaning Services con... Decided Open
1 Sep 2026 Acquisition of Land off Hale Road, Adjacent to Farnham Park, Farnhamthat 1) The Executive request consent from West Surrey Shadow Authority to enter into a Conditional Purchase Agreemen... Agreed Open
1 Sep 2026 Waverley Fire Loss - Underinsurance at 13 & 14 Springwood, Station Lane, MilfordRECOMMENDED that Council RESOLVE to: 1) Approve a supplementary estimate increase of £106,269.98 for FY26/27 to be fu... Approved Open
1 Sep 2026 Recycling and Waste Collection and Street Cleansing Services Contracts Arrangements from 1 November 2027that 1) An 8-year extension to the current Waste Collection and Street Cleansing Contract with an option of a contrac... Approved Open

We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies