The Executive RESOLVED to: 1. approve the phasing of the project. 2. approve the Outline Business Case and project timeline for the Phase 1 of the revised project (Exempt Annexe 1). 3. recommend to Full Council the approval of a budget of £230,000 (Exempt Annexe 2), to be met from ... EXE 36/23
Word for word from the decision Waverley published for this meeting.Source: modgov.waverley.gov.uk
Waverley Borough Council Report to: Executive Committee Date: 1st August 2023 Ward(s) affected: Godalming Central & Ockford Report of Director: Strategic Director - Place Author: Debbie Smith, Development Programme Manager and Caroline Wallis, Asset Investment Manager Tel: 01483 523 314 Email: [email protected] / [email protected] Executive Portfolio Holders: Mark Merryweather Tel: 01483 277283 Email: [email protected] Report Status: Part Exempt
69 High Street, Godalming Executive Summary
1.1In March 2022, Full Council approved the acquisition of 69 High Street, Godalming as a General Fund mixed use asset to support the Council’s aspirations contained within the Corporate Strategy 2020-25, including:
To bring forward affordable housing, in this case in Godalming town centre, and To deliver a positive contribution to Godalming by preserving the integrity of the high street
1.2The purchase was completed in May 2022, and in November 2022 the Executive noted a “mixed use” Project Initiation Document (PID) to: 1 progress the design optimisation scheme, in line with corporate priorities, to optimise housing numbers, and ensure the site – in the central high street – does not remain vacant and development of the scheme is done at pace.
This report describes the outcome of the Stage 1 (RIBA stage 0-2) work in that PID.
1.3For the reasons described, it is proposed to progress work in two stages, with priority given to accelerating completion of the commercial element while development work continues in parallel on the residential element for completion at a later date.
1.4The financial prospects for this project as a whole have been adversely affected by the severe macro-economic climate, and especially cost inflation and high interest rates. Consideration has also been given to the relative net benefits of progressing the residential element under the Housing Revenue Account rather than the General Fund. While the payback timescales overall have extended accordingly, it is still estimated that both elements of the project will ultimately be revenue positive.
1.6As detailed in the Asset Investment Strategy potential exit options have also been evaluated.
1.7This report seeks approval to:
progress the project as a phased approach progress to the next phase of the project in accordance with the approach outlined, and to approve the budget required to facilitate this.
The anticipated timeline to reach the end of RIBA Stage 3 (submission of planning application) is 4 months, at which point Officers will return to the Executive with recommendations of next steps.
2 Recommendation to Executive:
2.1To approve the phasing of the project.
2.2To approve the Outline Business Case and project timeline for the Phase 1 of the revised project (Exempt Annexe 1).
2.3To recommend to Full Council the approval of a budget of £230,000 (Exempt Annexe 2), to be met from the Asset Investment Reserve, to progress phase 1 of the revised project. This will be to deliver the commercial element of the project to RIBA Stage 4 (the detailed design phase) and to enable the submission of a planning application for the commercial unit.
2.4To delegate to the Strategic Director of Place, in consultation with the Lead Portfolio Holder, the submission of a new planning application for the commercial unit, including demolition to facilitate delivery and preparation for the prospective housing.
2.5To recommend to Full Council the approval of an overall capital budget of £1.96 million (including the £230,000 referred to above), as per the breakdown in Exempt Appendix 4, to cover the anticipated cost of the capital works to the commercial unit, with delegation to Executive to approve the final budget once tender returns for the construction contract have been received.
2.6To delegate authority to the Executive Head of Assets to enter into a long-term (15 years) commercial lease for 69 High Street.
2.7To delegate to the Strategic Director of Place to:
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.