Executive Co-Portfolio Holder for Housing Decisions, Thursday 29 February 2024 at 11.30am

HRA Planned Works: External Decorations and Roofline Works Contract Extension

Decided Executive 1 paper

Executive Co-Portfolio Holder for Housing Decisions decided this item on Thursday 29 February 2024. Below is the council's own wording, with the papers it was decided on.

Item6

Resolved

Having considered the comments of the Landlord Services Advisory Board (Executive Working Group), the Executive Co-Portfolio Holder for Housing, Cllr Paul Rivers, RESOLVED to, Recommendation 1. an extension to the current Ian Williams (Planned) contract by one year (terms and conditions to remain the same) for planned external redecoration and roofline replacement works. Reason(s) for Recommendation: 1. Waverley have a duty to ensure that the condition of the external fabric of council homes are maintained to a reasonable standard, to ensure that the components maintain performance and are not subject to premature failure. 2. Cyclical maintenance, including external redecorations and roofline replacement works; are typically included in our annual budgets and asset management strategy. 3. Ian Williams Limited (Planned) currently supply external redecoration and roofline replacement services to Waverley via a measured term contract, which commenced in April 2019, and was procured on a ‘5+1+1+1+1+1’ year term. 4. Waverley have developed a good working relationship with the incumbent contractor, Ian Williams (Planned). The quality of the product delivered on-site has been consistent and reasonable over the last few years. Ian Williams (Planned) are providing a good service and value for money. 5. The Planed Works Team recommend extending this current arrangement for an additional year, until March 2025. This option provides Waverley with the time to procure replacement contracts as well as releasing resources to complete other high-priority procurement workloads.
Word for word from the decision Waverley published for this meeting. Source: modgov.waverley.gov.uk

Follow this further

Built from Waverley's papers

What the report saysPro

Report to Executive Co-Portfolio Holder for Housing Decisions

Executive summary

The report outlines the request to enter into an extension period of the existing planned works contract for external redecorations and roofline works, with Ian Williams (Planned) from April 2024 to March 2025.

2. Recommendation to Executive

That the Executive Co-Portfolio Holder for Housing (Operations and Services) approves: 1  an extension to the current Ian Williams (Planned) contract by one year (terms and conditions to remain the same) for planned external redecoration and roofline replacement works.

3. Reason(s) for Recommendation:

Waverley have a duty to ensure that the condition of the external fabric of council homes are maintained to a reasonable standard, to ensure that the components maintain performance and are not subject to premature failure.

Cyclical maintenance, including external redecorations and roofline replacement works; are typically included in our annual budgets and asset management strategy.

Ian Williams Limited (Planned) currently supply external redecoration and roofline replacement services to Waverley via a measured term contract, which commenced in April 2019, and was procured on a ‘5+1+1+1+1+1’ year term.

Waverley have developed a good working relationship with the incumbent contractor, Ian Williams (Planned). The quality of the product delivered on- site has been consistent and reasonable over the last few years. Ian Williams (Planned) are providing a good service and value for money.

The Planed Works Team recommend extending this current arrangement for an additional year, until March 2025. This option provides Waverley with the time to procure replacement contracts as well as releasing resources to complete other high-priority procurement workloads.

4. Exemption from publication - No

Purpose of report

The current contract ends in March 2024 unless the contract is formally extended. The contract was designed with an extension clause, in accordance with the contract terms and the initial procurement process.

2 Therefore, agreement is sougt to extend the current contract with Ian Williams (Planned) for an additional one year period – April 2024 to March 2025 (as per contract terms allow) to continue to carry out planned external redecorations and roofline replacement works on a rolling programme basis.

6. Strategic Priorities

The report supports the Council’s Corporate Commitment to promote “good quality housing for all income levels and age groups” and aims to “be the best council landlord in the southeast and to be acknowledged so by our tenants”.

Background

The Planned Works Team have developed a good working relationship with the incumbent contractor, Ian Williams (Planned), and the quality of the product delivered on-site has been consistent.

The team are currently on target to complete the following by the end of FY 23/24, to a good standard:

 External Redecorations to about 290 houses and 6 flat blocks containing 26 flats, at a cost of about £375k.  Roofline Replacement Works to about 20 house and 14 flat blocks containing 72 flats, at a cost of about £250k.

8. Consultations

Tenant Satisfaction Surveys. Landlord Services Advisory Board.

9. Key Risks

The current contract will end in March 2024 unless extended. If the contract ends, then no programmed external redecorations or roofline replacement works will be carried out in FY 2024/25, to the detriment of the housing stock.

3 10. Financial Implications

The budget FY 2024/25 is currently awaiting final approval, which is due in February 2024.

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
HRA Planned Works: External Decorations and Roofline Works Contract ExtensionReport 600 KB DownloadRead as text

At this meeting

Whole meeting
1MINUTESOn the agenda 5HRA Planned Works: Kitchen and Bathroom Contract ExtensionDecided
6HRA Planned Works: External Decorations and Roofline Works Contract ExtensionThis decision

Who was there

1 of 2 attended
NP
Councillor Nick PalmerCommittee Member, apologies
PR
Councillor Paul RiversCommittee Member, present

On this subject at Waverley

Search all
  1. HRA Planned Works: External Decorations and Roofline Works Contract ExtensionThis decision
  2. HRA Planned Works: External Decorations and Roofline Works Contract ExtensionAgreed
  3. HRA Planned Works: Kitchen and Bathroom Contract ExtensionAgreed
  4. HRA Planned Works: Kitchen and Bathroom Contract ExtensionDecided

More from Waverley Executive Co-Portfolio Holder for Housing Decisions

All decisions
MeetingDecisionOutcome
26 Sep 2024 Approval to commence tendering for Leasehold Buildings Insurance contractHaving considered the comments of the Landlord Services Advisory Board (Executive Working Group), the Executive Co-Po... Agreed Open
26 Sep 2024 Approval to commence procurement of Stock Condition Surveys for HRA Home AssetsHaving considered the comments of the Landlord Services Advisory Board (Executive Working Group), the Executive Co-Po... Decided Open
26 Sep 2024 Approval to commence tendering for Kitchen and Bathroom Installation ContractHaving considered the comments of the Landlord Services Advisory Board (Executive Working Group), the Executive Co-Po... Decided Open
26 Sep 2024 Approval to commence tendering for Damp and Mould Specialist Services contractHaving considered the comments of the Landlord Services Advisory Board (Executive Working Group), the Executive Co-Po... Decided Open
26 Sep 2024 Approval to commence tendering for Roof Replacement ContractHaving considered the comments of the Landlord Services Advisory Board (Executive Working Group), the Executive Co-Po... Decided Open

We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies