Resolved
RESOLVED to agree to the recommendations set out in the report.
Landlord Services Advisory Board (Executive Working Group) agreed this item on Thursday 29 February 2024. Below is the council's own wording, with the papers it was decided on.
Resolved
RESOLVED to agree to the recommendations set out in the report.
The report outlines the request to enter into an extension period of the existing planned works contract for kitchen and bathroom replacements with PILON from April 2024 to March 2026.
2. Recommendation to Executive
That the Executive Co-Portfolio Holder for Housing (Operations and approves: 1 an extension to the current PILON contract by two years (terms and conditions to remain the same) for planned kitchen and bathroom replacement works.
3. Reason(s) for Recommendation:
Waverley have a duty to ensure that all their homes have reasonably modern facilities and meet the Decent Homes standard.
PILON currently supplies planned kitchen and bathroom replacement services to Waverley via a measured term contract, which was signed in June 2022, and procured on a ‘2+2’ year term.
Waverley have developed a good working relationship with the incumbent contractor, PILON. The quality of the product delivered on-site over the last 18 months has been consistent. PILON are providing a good service and value for money.
The Planned Works Team recommend extending this current arrangement for two years until March 2026. This option provides Waverley with time to procure replacement contracts as well as releasing resources to complete other current high-priority procurement workloads.
4. Exemption from publication - No
The current contract ends in March 2024 unless the contract is formally extended. The contract was designed with an extension clause, in accordance with the contract terms and the initial procurement process.
Therefore, agreement is sought to extend the current contract with PILON for two additional years – from April 2024 to March 2026 (as per contract terms allow) to continue to carry out planned kitchen and bathroom replacement works on a rolling programme basis.
2 6. Strategic Priorities
The report supports the Council’s Corporate Commitment to promote “good quality housing for all income levels and age groups” and aims to “be the best council landlord in the southeast and to be acknowledged so by our tenants”.
The Planned Works team have developed a good working relationship with the incumbent contractor PILON, and the quality of the product delivered has been consistent since their start in 2022.
Waverley is currently on target to complete about 60 planned kitchens and planned 75 bathrooms at a cost of about £900k, by the end of FY 2023/24, to a good standard.
This workstream by PILON has also produced a tenant satisfaction score of 94%.
8. Consultations
Tenant Satisfaction Surveys and Landlord Services Advisory Board.
9. Key Risks
The current contract will end in March 2024 unless extended. If the contract ends, then no programmed kitchen and bathroom replacement works will be carried out in FY 2024/25, to the detriment of the housing stock.
The budget for FY 2024/25 is currently awaiting final Council approval, which is due 20 February 2024.
3 The proposed combined budget for FY 2024/25 is £875k, which would enable similar completion results to last years, c130 replacements.
Legal advice was sought in this matter and Andrew Ogalo, Contracts and Procurement Solicitor (Interim) provided legal advice. Confirming that the original ‘2+2’ year agreement commenced on 1st July 2022, for a period of two years (running until March 2024), with the option to extend for a period of two additional years (from April 2024 until March 2026).
12. Human Resource Implications - None
13. Equality and Diversity Implications - None
14. Climate Change/Sustainability Implications
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
PDF |
HRA Planned Works: Kitchen and Bathroom Contract ExtensionReport | 598 KB | DownloadRead as text |
Follow Landlord Services Advisory Board (Executive Working Group) at Waverley and we tell you when its next papers are published, before the meeting rather than after it.
| Meeting | Decision | Outcome | |
|---|---|---|---|
| 30 Jul 2026 | Capital Programme updateRESOLVED that the Capital Programme update be noted. | Noted | Open |
| 30 Jul 2026 | Council Response to Tenant Panel Proposal on Repairs, Maintenance and Service AppointmentsRESOLVED that: · the tenant panel proposal be noted, · the principles of a standardized appointments and communicatio... | Noted | Open |
| 30 Jul 2026 | Low Carbon Heating SolutionsRESOLVED that the Low Carbon Heating Solutions report be noted. | Noted | Open |
| 30 Jul 2026 | Water Hygiene ReportRESOLVED that the monthly Water Hygiene Report be noted. | Noted | Open |
| 30 Jul 2026 | Landlord Services Improvement Plan Update [2025-26]RESOLVED that the Landlord Services Improvement Plan update was noted. | Noted | Open |
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Keeps you signed in and runs your free-paper allowance. Always on.
Counts visits and which pages are used. First-party only, no advertising, never shared.