Resolved
RESOLVED to agree to the recommendations set out in the report.
Landlord Services Advisory Board (Executive Working Group) agreed this item on Thursday 29 February 2024. Below is the council's own wording, with the papers it was decided on.
Resolved
RESOLVED to agree to the recommendations set out in the report.
The report outlines the request to enter into an extension period of the existing planned works contract for external redecorations and roofline works, with Ian Williams (Planned) from April 2024 to March 2025.
2. Recommendation to Executive
That the Executive Co-Portfolio Holder for Housing (Operations and Services) approves: 1 an extension to the current Ian Williams (Planned) contract by one year (terms and conditions to remain the same) for planned external redecoration and roofline replacement works.
3. Reason(s) for Recommendation:
Waverley have a duty to ensure that the condition of the external fabric of council homes are maintained to a reasonable standard, to ensure that the components maintain performance and are not subject to premature failure.
Cyclical maintenance, including external redecorations and roofline replacement works; are typically included in our annual budgets and asset management strategy.
Ian Williams Limited (Planned) currently supply external redecoration and roofline replacement services to Waverley via a measured term contract, which commenced in April 2019, and was procured on a ‘5+1+1+1+1+1’ year term.
Waverley have developed a good working relationship with the incumbent contractor, Ian Williams (Planned). The quality of the product delivered on- site has been consistent and reasonable over the last few years. Ian Williams (Planned) are providing a good service and value for money.
The Planed Works Team recommend extending this current arrangement for an additional year, until March 2025. This option provides Waverley with the time to procure replacement contracts as well as releasing resources to complete other high-priority procurement workloads.
4. Exemption from publication - No
The current contract ends in March 2024 unless the contract is formally extended. The contract was designed with an extension clause, in accordance with the contract terms and the initial procurement process.
2 Therefore, agreement is sougt to extend the current contract with Ian Williams (Planned) for an additional one year period – April 2024 to March 2025 (as per contract terms allow) to continue to carry out planned external redecorations and roofline replacement works on a rolling programme basis.
6. Strategic Priorities
The report supports the Council’s Corporate Commitment to promote “good quality housing for all income levels and age groups” and aims to “be the best council landlord in the southeast and to be acknowledged so by our tenants”.
The Planned Works Team have developed a good working relationship with the incumbent contractor, Ian Williams (Planned), and the quality of the product delivered on-site has been consistent.
The team are currently on target to complete the following by the end of FY 23/24, to a good standard:
External Redecorations to about 290 houses and 6 flat blocks containing 26 flats, at a cost of about £375k. Roofline Replacement Works to about 20 house and 14 flat blocks containing 72 flats, at a cost of about £250k.
8. Consultations
Tenant Satisfaction Surveys. Landlord Services Advisory Board.
9. Key Risks
The current contract will end in March 2024 unless extended. If the contract ends, then no programmed external redecorations or roofline replacement works will be carried out in FY 2024/25, to the detriment of the housing stock.
3 10. Financial Implications
The budget FY 2024/25 is currently awaiting final approval, which is due in February 2024.
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
PDF |
HRA Planned Works: External Decorations and Roofline Works Contract ExtensionReport | 600 KB | DownloadRead as text |
Follow Landlord Services Advisory Board (Executive Working Group) at Waverley and we tell you when its next papers are published, before the meeting rather than after it.
| Meeting | Decision | Outcome | |
|---|---|---|---|
| 30 Jul 2026 | Capital Programme updateRESOLVED that the Capital Programme update be noted. | Noted | Open |
| 30 Jul 2026 | Council Response to Tenant Panel Proposal on Repairs, Maintenance and Service AppointmentsRESOLVED that: · the tenant panel proposal be noted, · the principles of a standardized appointments and communicatio... | Noted | Open |
| 30 Jul 2026 | Low Carbon Heating SolutionsRESOLVED that the Low Carbon Heating Solutions report be noted. | Noted | Open |
| 30 Jul 2026 | Water Hygiene ReportRESOLVED that the monthly Water Hygiene Report be noted. | Noted | Open |
| 30 Jul 2026 | Landlord Services Improvement Plan Update [2025-26]RESOLVED that the Landlord Services Improvement Plan update was noted. | Noted | Open |
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Keeps you signed in and runs your free-paper allowance. Always on.
Counts visits and which pages are used. First-party only, no advertising, never shared.