Resolved
The Executive RESOLVED to: Approve the appointment of Bidder C as contractor to complete the pre-construction services.
Executive approved this item on Tuesday 7 January 2025. Below is the council's own wording, with the papers it was decided on.
Resolved
The Executive RESOLVED to: Approve the appointment of Bidder C as contractor to complete the pre-construction services.
1.1This paper enables the next stage of the commercial element of the 69 High Street development, by recommending that the Executive approve the appointment of a contractor to complete Pre- Construction Services for that commercial element.
1.2It confirms that a compliant procurement process has taken place and that Bidder C should be appointed as soon as possible. 2. Recommendation to Executive
2.1That the Executive approves the appointment of Bidder C as contractor to complete the pre-construction services.
3. Reason(s) for Recommendation:
3.169 High Street, Godalming, was purchased as a development project with mixed-use planning permission by the General Fund to deliver - directly and through the HRA - on the Council’s Corporate Strategy.
3.2The appointment of Bidder C via a Pre-Construction Services Agreement for the commercial element only will follow the recommendations and result of a compliant procurement process, and allow progression of the whole project to the next stage.
3.3The Pre-Construction Services Agreement will appoint a contractor to complete final design work on the demolition and refurbishment scheme for the commercial element submitted and approved by the Planning Committee.
3.4Appointment of the Contractor at this stage will enable input from them on the design to allow for a best value solution for the build.
4. Exemption from publication
Yes, part of the report. Appendix 1 is exempt from publication.
The content of the Appendix 1 is to be treated as exempt for the purposes of the Council’s Access to Information Procedure Rules because it contains commercially sensitive information and is therefore exempt by virtue of paragraph 3 of Part 1 of Schedule 12A to the Local Government Act as follows:
Information relating to the financial or business affairs of any particular person (including the authority holding that information). The content is restricted to all councillors.
5.1To approve the entering into of a Pre-Construction Services Agreement (PCSA) with the winning bidder for the demolition and refurbishment of the commercial element of the 69 High Street project, Godalming.
6. Strategic Priorities
6.1The redevelopment of 69 High Street meets the Strategic Priority of the Council for housing, and the enabling redevelopment of the commercial (retail) element of the site meets the Strategic Priority for regeneration.
6.2The project will bring forward ‘decent and affordable homes’ through demolition of the large retail unit to allow for homes to the rear of the site; they will be built and retained by the Council.
6.3It will also support the priority of ‘a more prosperous borough’ – the delivery of the new, smaller and more appropriate retail unit with a commercial tenant in place will support the local economy and high street.
7.1In February 2022 Full Council approved the acquisition of 69 High Street, Godalming initially through the General Fund as a mixed-use redevelopment asset with planning permission to support, with the HRA, the Council’s aspirations contained within the Corporate Strategy 2020-25, including:
To bring forward affordable housing, in this case in Godalming town centre. To deliver a positive contribution to Godalming by preserving the integrity of the high street.
7.2The purchase was completed in May 2022, and in November 2022 the Executive noted a proposal for a “mixed-use” scheme outlined within the Project Initiation Document (PID).
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
PDF |
69 High Street, Godalming: Award Pre-ConstructionReport | 710 KB | DownloadRead as text |
Follow Executive at Waverley and we tell you when its next papers are published, before the meeting rather than after it.
| Meeting | Decision | Outcome | |
|---|---|---|---|
| 1 Sep 2026 | Lease Renewal on Unit 3, Enterprise Centre, Farnhamthat 1) Delegated authority be given to the Director of Assets and Property for the granting of the lease of Unit 3, ... | Agreed | Open |
| 1 Sep 2026 | New Contract for Communal Block Cleaning Servicesthat 1) Delegated authority be given to the Director of Housing Service to enter into the Block Cleaning Services con... | Decided | Open |
| 1 Sep 2026 | Acquisition of Land off Hale Road, Adjacent to Farnham Park, Farnhamthat 1) The Executive request consent from West Surrey Shadow Authority to enter into a Conditional Purchase Agreemen... | Agreed | Open |
| 1 Sep 2026 | Waverley Fire Loss - Underinsurance at 13 & 14 Springwood, Station Lane, MilfordRECOMMENDED that Council RESOLVE to: 1) Approve a supplementary estimate increase of £106,269.98 for FY26/27 to be fu... | Approved | Open |
| 1 Sep 2026 | Recycling and Waste Collection and Street Cleansing Services Contracts Arrangements from 1 November 2027that 1) An 8-year extension to the current Waste Collection and Street Cleansing Contract with an option of a contrac... | Approved | Open |
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Keeps you signed in and runs your free-paper allowance. Always on.
Counts visits and which pages are used. First-party only, no advertising, never shared.