AI summaryWaverley Executive endorses 69 High Street Godalming refurbishment plan, subject to Full Council approving an extra £540,000 and adding a delay option.
Written from the decision and the officer reportPDF Pro
OutcomeDecidedSubject to amended report and new delay option
Money£540,000 extra requestedFrom Revenue Account Reserve, to Full Council
What happens nextFull Council 22 October 2025Final budget decision needed
Who it affects69 High Street, GodalmingFuture Loungers café and 10+ homes
What was decided
The Executive endorsed the report recommending Full Council approve an additional £540,000 to progress demolition and refurbishment of 69 High Street, Godalming, and to appoint ETEC Group Limited as contractor. Report 2.1, P3, 2.2, P5
The endorsement is conditional on the report to Council being amended to include the additional information requested by the Overview and Scrutiny Committee. Report 9.2
The Executive also asked that an Option 6 be added to allow the Council to delay its decision until the December meeting.
Why
Tendered costs now exceed the budget originally approved in August 2023, driven by a 23% uplift in construction prices between Q1 2021 and Q3 2025 and the need to replace the existing structure rather than reinforce it. Report 6.14, P42, P43, P45
Officers assessed five options and recommend Option 1, continuing the project, as it delivers the original purpose of the purchase and prevents crystallisation of a financial loss shown by recent valuations. Report 11.1, 11.3, P73, P81
Loungers Ltd is secured under an Agreement for Lease as the future tenant, and a compliant procurement was completed via the Procure Partnerships Framework in 2024. Report 6.5, 6.9, P88
What happens next
Full Council will consider the report and the additional £540,000 budget request on 22 October 2025. Report 4.1, P13
If approved, officers will progress executing the main works contract with ETEC Group Limited and the Strategic Director of Economy, Planning and Place is authorised to enter the contract. Report 4.1, P6
Any decision on the separate residential element, expected to deliver at least 10 new homes, will require further Executive and Full Council approval later this year or in early 2026. Report 6.16
The money
£540,000 Additional budget requested, funded from Revenue Account Reserve (General Fund working balance) Report P3, P84
£271,229 Total subsidy requirement from the General Fund after revised cost assessment Report P85
£85,000 Contingency funding in the budget, equivalent to 5%, in addition to the contractor's 2.5% allowance Report 10.1, P65
£1.66m Spend to date on the project, including acquisition costs Report P86
£58k Annual running costs that would still be payable if the project is paused Report P86
23% Uplift in BCIS tender prices between Q1 2021 and Q3 2025 Report P42
47 years Revised payback period for the scheme, up from 41 years Report P85
Options considered
Chosen: Option 1: Continue the project by appointing the contractor, with revised payback timeline. Delivers original purpose and prevents crystallisation of a financial loss; recommended by officers Report 11.3, P73, P81
Rejected: Option 2: Do nothing and pause the project, retaining the asset in its current form. Running costs of £58k annually would still apply and original purpose not delivered Report P74, P86
Rejected: Option 3: Put the property on the market and seek to divest the asset as soon as possible. Would result in a financial loss to the Council Report P75, P87
Rejected: Option 4: Deliver the commercial fit out then put the property on the market with residential consent for the rear. Would result in a financial loss to the Council Report P76, P87
Rejected: Option 5: Complete the commercial fit out with a view to sell the commercial asset only once the tenant is in place. Discounted at this stage but may be revisited once works and tenant are in place Report 11.4, P77
Chosen: Option 6: Delay the Council's decision until the December meeting. Added by the Executive as a condition of endorsement, not in the original report
Implications
Financial: Revised project budget exceeds the previously approved budget by up to £540,000 and requires Full Council approval under Finance Procedure Rules because it is over £250,000. Report P84, P91
Financial: Payback period increases from 41 to 47 years; subsidy requirement from the General Fund is £271,229. Report P85
Risk: Lease is for 15 years with a break option at year 10, both shorter than the 47-year payback, creating re-letting or disposal risk if the tenant leaves. Report 10.2
Risk: Insufficient contingency could allow unforeseen site issues to increase costs; £85,000 (5%) is included as mitigation. Report 10.1, P65
Risk: Archaeological discoveries during demolition could delay the programme; an archaeologist's watching brief is factored in. Report 10.5, P71
Legal: Procurement was compliant via the Procure Partnerships Framework in 2024 and the contract value falls under thresholds in Schedule 1 of the Procurement Act 2023; Best Value duty considered satisfied. Report P88, P90
Equalities: The Public Sector Equality Duty has been considered and no equality and diversity implications arise directly from this report. Report P94, P97
Climate: The building is designed to achieve an EPC rating of Good, with a blue roof system, solar array, new double-glazed windows and no gas installed on the site. Report P52, P102
Who and where
Loungers Ltd, the future tenant operating under the Lounge Café Bars brand under a 15-year Agreement for Lease with a break option at year 10 Report 6.5, 10.2
Residents and visitors to Godalming High Street, with the café expected to act as an anchor tenant supporting daytime and evening footfall Report 6.6, 6.7
Future residents of at least 10 new homes on the rear of the site, subject to a separate later approval Report 6.16
Waverley Borough Council as owner and funder via the General Fund, with the asset to be retained by the future successor authority Report 8.3, P57
Ward councillors for the Godalming area, who have been kept up to date with progress Report 9.3
Timeline
February 2022: Council approved acquisition of 69 High Street for affordable housing under the HRA and commercial use under the General Fund Report 6.2, P25
May 2022: Purchase of the property completed Report 6.3
29 August 2023: Full Council approved the Business Case to progress the development, splitting into commercial and residential phases Report 6.4, 16.3
August 2024: Local Planning Authority granted new and improved Planning Permission Report P32
Summer 2024: Competitive procurement completed via a Framework for a 2-stage Design & Build contractor Report 6.9
January 2025: Contractor appointed under a Pre-Construction Services Agreement (PCSA) to take design from RIBA Stage 3 to Stage 4 Report 6.10
23 September 2025: Resources Overview and Scrutiny Committee received a verbal update Report 9.2
8 October 2025: Special Overview and Scrutiny meeting discussed the paper Report 9.2
14 October 2025: Executive endorsed the report subject to the two conditions in the decision
22 October 2025: Full Council to consider the additional £540,000 budget and the new Option 6 to delay Report 4.1, P13
Summer 2027: Expected completion of the contract; exempt information likely to be released for public inspection then Report 5.4
Plain English for the jargon
PCSA: Pre-Construction Services Agreement, a two-stage arrangement where a contractor is appointed first to develop the design and price before the main works contract is signed
RIBA Stage 3 and 4: Royal Institute of British Architects' design stages: Stage 3 is Planning Approval design and Stage 4 is Full Technical Design
HRA: Housing Revenue Account, the ring-fenced account local authorities use for housing-related income and spending
General Fund: The main council account for non-housing revenue and spending, funded by council tax, business rates and government grants
EPC: Energy Performance Certificate, a rating of a building's energy efficiency from A (most efficient) to G
BCIS: Building Cost Information Service, which publishes construction cost indices used to track tender price inflation
What was decided, why, and what happens next
Pro reads every officer report for you and explains each decision in plain English: the money, the options, the risks, the timeline, each with the paragraph it came from.
Written by AI from the council's published papers. AI can get things wrong: the council's own wording below is the record.Report a problem
ItemEXE 74/25
Resolved
RESOLVED that: 1. Subject to the amendment of the report to Council to include the additional information requested by the Overview and Scrutiny Committee and the inclusion of ‘Option 6’ to delay the Council’s decision until its meeting in December, The content of the report be endorsed by the Executive ... EXE 74/25
Word for word from the decision Waverley published for this meeting.Source: modgov.waverley.gov.uk
1.1This report considers the options, and makes recommendations, to proceed with a construction contract for the demolition of part of the existing building and the refurbishment of the commercial unit at 69 High Street, Godalming, following completion of the Pre-Construction Services Agreement (PCSA) by the contractor, pricing of the works, and a reassessment of the options available.
Recommendations
2.1That the Executive resolves to endorse the content of this report and recommend to the full Council meeting on 22nd October 2025:
2.1.1 That full Council approves the required additional budget of £540,000 to progress the project at 69 High Street, Godalming, to be funded from the Revenue Account Reserve (General Fund working balance).
2.2That, strictly subject to full Council approving the required additional budget, the Executive resolves to:
2.2.1 Approve the appointment of ETEC Group Limited as contractor to complete all works associated with the demolition of the building at 69 High Street, Godalming and its refurbishment for the commercial unit only.
2.2.2 Delegates to the Strategic Director of Economy, Planning and Place the authority to enter into the contract with ETEC Group Limited, together with such other contracts and legal agreements connected with the 69 High Street project as may be necessary, in compliance with Procurement Procedure Rules, the Council’s Constitution and within the approved budget (as revised under recommendation 2.1.1 above).
3 Reason(s) for recommendation:
3.1Proceeding with the construction contract for the demolition of part of the existing building and the refurbishment will:
facilitate the fit-out of the commercial unit for the future tenant; and
2 69 High Street Godalming development
clear the rear portion of the site to enable future residential development
3.2This has been evaluated as the recommended option, as outlined in Exempt Appendix 1.
4 Next steps
4.1Following a decision by Executive, this report will be considered by Full Council on 22nd October 2025. Should the recommendations be approved, officers will progress the executing of the main works contract with ETEC.
5 Exemption from publication
5.1Part of this report is exempt from publication.
5.2Appendices 1 and 2 are to be treated as exempt for the purposes of the Council’s Access to Information Procedure Rules because they contain commercially sensitive information and are therefore exempt by virtue of paragraph 3 of Part 1 of Schedule 12A to the Local Government Act 1972 as follows:
- Information relating to the financial or business affairs of any particular person (including the authority holding that information).
5.3The content is restricted to all councillors.
5.4It is likely that the exempt information can be expected to be made available for public inspection on completion of the contract in Summer 2027.
6 Background and Proposal
Context
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.